WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Steps towards beam commissioning: RF system group Paolo Craievich :: RF Section :: Paul Scherrer Institut SwissFEL Commissioning Workshop, 21 January 2016 FHNW Campus Brugg-Windisch
2
SwissFEL Injector Page 2 StationStructureModulatorKlystronBand Gun1PSI1ScandiNova1ThalesS-Band Booster6RI4ScandiNova4ThalesS-Band X-Band2CERN1ScandiNova1SLACX-Band Deflector1INFN1ScandiNova1ThalesS-Band Linac 1 S band (2 x4 m) Gun Laser Heater Booster1Booster 2 BC 1 S band (4x4 m) X band (2 x 0.75 m) Deflector C band (4 x 2 m) SINEG01 SINSB01SINSB03SINXB01 SINDI01S10CB01 SINSB04 SINSB02
3
SwissFEL C-Band Linac Page 3 S10CB01S20CB01S30CB01S30CB14.1S30CB13 LinacStructureModulatorKlystronBand Linac 136PSI9Ampegon9ToshibaC-Band Linac 216PSI4Ampegon4ToshibaC-Band Linac 352PSI13ScandiNova13ToshibaC-Band Deflector2MHI0---C-Band
4
Project Milestones Page 4 9 C-band modules Ref. T. Schietinger * *
5
SINEG01: Installation of the RF gun system Page 5 Modulator transport Modulator assembly (water, oil) + klystron (shield) Interlock cabling (LLRF and electricians) Modulator connection to grid and tests Modulator IOC commissioning Diode tests Cooling stations ready 30.03 (KKV01) Water cooling RF Gun Installation of the RF waveguides and water connections Laser alignment on the cathode Installation of the load-lock chamber 18.05 Bake-out and leakage tests RF measurements LLRF activities PSYS tests Ready for first RF 25.05 RF conditioning – 1 week LLRF Optimization (with cooling system) Ready for beam 20.06 Legend: Done, To be done, Interfaces to other expert groups Installation Sequence (Ref.: Installationen für Injektor Commissioning - http://i.psi.ch/MBQN)
6
SINSB01 and SINSB02 systems Page 6 Modulator transport Modulator assembly (water, oil, shield klystron, housing) Modulator connection to grid & tests Diode tests Cooling stations ready 30.03 (KKV01) Connection water cooling structure & solenoids Assembly Waveguides + final water connections Bake-out cavity LLRF activities + interlock tests First RF 20.05 and 30.05 RF conditioning LLRF optimization (with cooling rack) RF ready for beam 13.06 and 27.06 2x
7
Page 7 SINSB03 and SINSB04 systems SINSB03 KKV02 22.04 Modulator transport Modulator assembly (water, oil, shield klystron, housing) Diode tests Assembly Waveguides + final water connections Bake-out cavity Ready for first RF 30.06 – with Beam 21.07 SINSB04 KKV02 22.04 1 cavity in WLHA for pre-assembly 1 cavity at RI. Production sequence completed MEGA power splitters with vacuum leak Vacuum group prepares a dummy chamber pipe to substitute cavities 2x
8
SINDI01 (deflector) and SINXB01 (X-band) Page 8 5-cell RF deflector KKV03 22.04 X-band system KKV02 22.04 Modulator transport Modulator assembly (water, oil, shield klystron, housing) Modulator connection to grid & tests Diode tests Connection water cooling structure Assembly Waveguides + final water connections Bake-out cavity LLRF activities + interlock tests Ready for first RF 30.08 and RF ready for beam 20.09 Modulator transport Modulator assembly (water, oil, shield klystron, housing) Modulator connection to grid & tests Diode tests Connection water cooling structure Assembly Waveguides + final water connections Bake-out cavity LLRF activities + interlock tests Ready for first RF 06.06 and RF ready for beam 20.06
9
Page 9 C-band Linac – Installation 1/3 ~9m Actually 14 over 26 modules are already installed First HV modulator (by Ampegon) will be transported from OBLA modulator assembly (water, oil, shield klystron, housing) modulator connection to grid & tests PSYS tests water connections to the 4 structures + BOC Interlock test for diode mode Waveguide installation Diode mode Interlock test for RF Ready for conditioning
10
Page 10 We intend to install the last module in the SwissFEL tunnel in September 2016. At the moment the structure production meets the schedule. C-band Linac – Installation 2/3 Courtesy F. Loehl
11
C-band Linac – Installation 3/3 HV modulators Both modulator orders (12 Ampegon & 13 ScandiNova) are placed and the Kick-off meetings took place. Contractual delivery dates: Nov 15Dec 16Jan 17Feb 17Mar 17Apr 17 Ampegon122232 ScandiNova11335
12
C-band MHI deflectors (S03CB14.1) Page 12 PSI ordered two C-band deflecting cavities and related waveguides to MHI-MS They will be ready for commissioning in October 2016 The two deflecting cavities will be powered by the last station of Linac3 using an high power RF switch The waveguide switch is provided by Nihon Koshua The power test of the switch is in progress Last module in Linac3 (S03CB13) Deflecting cavities (S03CB14.1)
13
RF Gun – 1 week SINSB01-02-03-04 – 2 weeks: operation at 10 Hz, conditioning at 100 Hz, RI structures never run at 100 Hz and nominal power SINXB01 – 2 week for 10 Hz operation SINDI01 – 1 week for 10 Hz operation S01CB01 functional test – 2 months S01CB02 from Jan. 2017 S10CB03–07, S30CB01–04 Jan. 2017 – May 17 S30CB14.1 (deflector) S10CB08–09, S20CB01–04, S30CB05–13 RF conditioning Page 13
14
Energy gains against timing Energy gains against temperature of the accelerating structures Functional tests of the S01CB01 module with beam Tuning of the RF parameters Dark current measurements System commissioning with beam Page 14