Presentation to CITY OF PALM COAST, FLORIDA FINANCIAL FORECAST AND CAPITAL FACILITIES FEES ANALYSIS Prepared in Conjunction With the Utility System Revenue Bonds, Series 2007 December 19, 2006 Presented By Public Resources Management Group, Inc.
2
2 AGENDA Series 2007 Bonds Financial Forecast Background and Purpose Customer Statistics / Revenue Projections Capital Improvement Funding Adequacy of System Rates Debt Service Coverage Capital Facilities Fees Analysis Conclusions and Recommendations
3
3 SERIES 2007 BONDS Fund certain capital improvements to the water and wastewater system Total Construction Fund proceeds = $45,635,000 Primary Projects include: Water Treatment Plant No. 3$29,950,000 Land Acquisition 7,200,000 Beachside Wastewater Facilities 5,200,000 OKR Master Pump Station & FM 2,000,000 Raw Water Mains 1,285,000 Total Loan Principal $50,765,000 Includes capitalized interest through September 30, 2008 Coupon Rates ranging from 4.09% to 4.86% Term of 30 years Issuance Requires Preparation of Financial Forecast
4
4 FINANCIAL FORECAST
5
5 BACKGROUND AND PURPOSE Prepared in Anticipation of the Issuance of the Series 2007 Bonds Evaluate the Sufficiency of Rates Five-year Financial Forecast and Funding Analysis – FY 2007-2011 Meet System Expenditures Fund Capital Improvement Plan Satisfy Rate Covenants Defined in the Bond Resolution Maintain Financial Stability of System
6
6 BACKGROUND AND PURPOSE (Con’d) Analysis included Forecast of: Customer Statistics and Revenues Operating Expenses Capital Improvement Funding System Cash Flow and Fund Balances
7
7 CUSTOMER STATISTICS During FY 2006, the City Served on Average: 38,796 Water Accounts 29,912 Sewer Accounts Active Account Growth of System (to FY 2006) Compounded Growth Rate of 11.60% since 2000 Utility Customer Growth Projections
8
8 CUSTOMER STATISTICS REVENUES PROJECTIONS (Con’d) Projected revenues from rates based on the following: Customer and Sales (use) Forecast Current rates and charges as Adopted at time of Acquisition No Change for Five Years Ends in Fiscal Year 2008 An Annual Price Indexing Adjustment of 2.2% was assumed for Fiscal Year 2009 – 2011 Applied to Monthly User Charges, Capital Facilities Fees, and Miscellaneous Charges
9
9 CUSTOMER STATISTICS REVENUES PROJECTIONS (Con’d) Proposed rate adjustment of 12.5% proposed for Fiscal Year 2009 to Recover: Increased debt service requirements associated with projected Utility System Revenue Bonds Inflationary Effects on Operating Expenditures Increase in Capital Improvement Plan/Costs Construction Cost have Materially Increased Increased Regulations Additional Capital Needs (Identified after “owning” system – Improved level of service) Blend of Pay-as-you-go Capital and Debt Financing Includes First Year of Price Index Adjustment Generally Consistent with Capital Finance Plan (SRF) Loan) Presented in May 2006
10
10 CUSTOMER STATISTICS REVENUES PROJECTIONS (Con’d) Existing Monthly Water and Wastewater Rates have not been adjusted since 1995 Exception – Water Conservation Rate Structure in 2005 Represents 13 years without change in rates Projected Increase in Inflation from the time of the System Acquisition (Nov. 2003 to 2009) approximates 14.5% Projected Increase in Inflation from last rate increase (1995 to 2009) approximates 38.5%
11
11 OPERATING EXPENSES Forecast Based on FY 2007 Adopted Budget Forecast Recognized: System Growth in Accounts Served/Flows Inflationary allowances Labor Cost Increases and Personnel Additions Contingency Allowance of 2.0% was included in the Forecast to Account for Unanticipated Expenses
12
12 CAPITAL IMPROVEMENT PROGRAM FUNDING The City’s Capital Improvement Plan was assumed to be funded with a combination of the following sources: Capacity Fees New Development Series 2007 Bonds Water Projects SRF Loans Low Interest / Wastewater Projects Renewal and Replacement Fund Deposits From Operations Operating Reserves Available Funds
13
13 ADEQUACY OF SYSTEM RATES
14
14 PROJECTED OPERATING RESULTS
15
15 WATER AND WASTEWATER COMPARISON Typical 5/8” Meter Monthly Bill At 5,000 Gallons
16
PROPOSED CAPITAL FACILITIES FEES
17
17 PURPOSE OF CAPITAL FACILITIES FEES Application Common in Utility Industry Historically Used by Utility as a Capital Financing Tool Recover Capital Cost of Capacity Allocable to New Users Must Meet “Rational Nexus” Provisions Dictated by Case Law Fees Must be Reasonable Support Capital Needs for System Growth Growth Must “Pay Its Own Way” Long Term Effect = Stabilize Rates for Service (e.g., Reduces Need for Future User Rate Increases” Shifts Portion of Cost Recovery Burden to Development Links to Financing of Capital Expenditures for Future Users Reduces Debt Service Component of Rates for Existing Users
18
18 MAJOR OBJECTIVES Can Only Be Used to Provide Funding for Expansion of Water and Sewer Service Should Not Be Used to Fund Capital Needs Related to Deficiencies in the Existing System or Pay for Any Operating Costs Should Be Based on System-Level Capital Cost Requirements Anticipated for Providing Service to New Development
19
19 CRITERIA Based on CIP Prepared by City’s Consulting Engineers and Identified in the Five-Year Financial Forecast CIP Planning Horizon Fiscal Year 2007 – Fiscal Year 2011 Only Water Production/Wastewater Treatment and Backbone Transmission Costs Recognized Distribution/Collection Project Costs Were not Recognized Generally Not System-Wide Costs Benefit Specific Customers Or Funded By Specific Charge (e.g., Meter Installation) Generally Contributed to Utility as Part of Development Process Supports Benefit Rule Identified by Case Law
20
20 PROPOSED WATER AND WASTEWATER CAPITAL FACILITIES FEES Water System Capital Facilities = $10.80 Per Gallons of Requested Capacity or $2,430/ERC Wastewater System Capital Facilities = $13.78 Per Gallon of Requested Capacity or $2,480/ERC Combined Proposed Fees Represent Increase From Current Fees
21
21 WATER AND WASTEWATER CAPITAL FACILITIES FEES COMPARISON
22
22 COMPARISON OF WATER AND WASTEWATER CAPITAL FACILITIES FEES (Con’d) Some Reasons Why Capital Facilities Fees Differ Among Utilities Source of Supply Proximity to Source of Supply Type of Treatment Availability of Grant Funding to Finance CIP Administrative Decision to Maintain Fees at a Level Below What Could Justifiably Be Charged Age of System/Level of Renewals and Replacements Utility Life Cycle (Growth-Oriented vs. Mature) LOS Per ERC Standards Density/Size of System
23
23 WATER AND WASTEWATER CAPITAL FACILITIES FEES COMPARISON
24
24 MONTHLY RATES CONCLUSIONS AND RECOMMENDATIONS Existing System Rates Are Not Adequate To Meet System Expenditures Throughout The Forecast Period. Adopt The Proposed 12.5% Increase To Monthly User Rates Effective November 1, 2008. Adopt Annual Indexing Provision. Proposed Rates Should Be Adequate To Comply With The Minimum Rate Covenants As Defined In The City’s Bond Resolution
25
25 CAPITAL FACILITIES FEES CONCLUSIONS AND RECOMMENDATIONS Fees are Based on Recommended Capital Improvement Program and Capacity Requirements Adopt Recommended Water and Wastewater Fees Make Proposed Capital Facilities Fees Changes Effective as Soon as legally allowed Priority of Use of Funds Collected Fund CIP to Avoid Outside Financing Debt Fund Future Expansion-Related Debt