SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012
2
What Happened Since February? Sensors Micron delivered trapezoidal sensors with new atoll design Construction database under development Ladder assembly Double-origami ladder built at IPMU, Japan 4 construction sites for series production Mechanics Design completed for all layers Cooling Detail design converging Mockup tests ongoing Electronics DC/DC converters and other parts tested FADC design completed, layout in progress 24 September 2012M.Friedl (HEPHY Vienna): SVD Status2 Concerns/recommendations In Feb 2012 BPAC report (all addressed)
3
SVD Schedule In early 2012, a detailed schedule was worked out and is now maintained by Christian More than 200 unique items with dependencies, duration and responsible persons MS Project & PDF versions are available at http://www.hephy.at/project/belle/belle2svd/schedule http://www.hephy.at/project/belle/belle2svd/schedule Present schedule: start of physics run on 30 November 2015 24 September 2012M.Friedl (HEPHY Vienna): SVD Status3
4
24 September 2012M.Friedl (HEPHY Vienna): SVD Status4 Sensors Ladder Assembly Mechanics Cooling Electronics Summary
5
Sensors HPK About 70% of sensors delivered already Micron 3 new wafers (big trapezoidal + baby sensors) delivered in August 2012 Now with atoll type p-stop very similar to HPK design Sensor tests show excellent quality Will be tested in beam & irradiated & tested again in October 2012 Construction Database being developed 24 September 2012M.Friedl (HEPHY Vienna): SVD Status5
6
Sensors Milestones HPK 12 November 2012: L3 sensor order April 2013: L4-6 sensor delivery to be completed July 2013: L3 sensor delivery to be completed Micron November 2012: beam test & irradiation analysis 3 December 2012: place order with Micron September 2013: final Micron sensor delivery Ladder assembly starts in July 2013 24 September 2012M.Friedl (HEPHY Vienna): SVD Status6
7
24 September 2012M.Friedl (HEPHY Vienna): SVD Status7 Sensors Ladder Assembly Mechanics Cooling Electronics Summary
8
Ladder Assembly Sites Discussion among all parties during summer 2012 B2GM Plan for sharing of production: L3: Melbourne L4: Tata (at CERN due to export restrictions) L5: HEPHY Vienna L6: IPMU We also agreed that it is important to keep some flexibility in our plan, so that one site can help another if trouble/delay occurs 24 September 2012M.Friedl (HEPHY Vienna): SVD Status8
9
Ladder Assembly Single Origami modules (HEPHY, 2010 and 2011) Double Origami module (IPMU, 2012) Both: collaborative effort of HEPHY, IPMU and Tata 24 September 2012M.Friedl (HEPHY Vienna): SVD Status9
10
Ladder Assembly Milestones Prototype December 2012/January 2013: full L5 prototype ladder Thereafter: final optimization of jigs Series Production L3 starts in July 2013 L4-6 start in September 2013 Duration 1 year for each layer SVD Assembly Starting in September 2014 @ KEK 24 September 2012M.Friedl (HEPHY Vienna): SVD Status10
11
24 September 2012M.Friedl (HEPHY Vienna): SVD Status11 Sensors Ladder Assembly Mechanics Cooling Electronics Summary
12
Mechanics Detailed design for all layers completed 24 September 2012M.Friedl (HEPHY Vienna): SVD Status12
13
Mechanics: Open Issues Ladder mount on end rings Not finalized yet, but converging Thermal Contact for L3 hybrids heat pipes look promising 24 September 2012M.Friedl (HEPHY Vienna): SVD Status13
14
Mechanics Milestones Collaborative support Regular “brain-storming meetings” with experienced engineers from MPI Munich & DESY (many thanks!) Machining support by MPI, DESY and Cracow Mockups Exist for all parts (some in early stage, others matured) Precise (close to final) overall SVD mockup to be built at KEK from November 2012 until April 2013 24 September 2012M.Friedl (HEPHY Vienna): SVD Status14
15
24 September 2012M.Friedl (HEPHY Vienna): SVD Status15 Sensors Ladder Assembly Mechanics Cooling Electronics Summary
16
Cooling Cooling Mockup at DESY Operated with XFEL CO2 unit (similar to MARCO which will become available by the end of 2012) Distribution & Routing Number of lines is defined First design for manifolds and routing available, to be optimized for available space and cable paths 2 options for transfer lines Expecting close-to-final state in 2013 24 September 2012M.Friedl (HEPHY Vienna): SVD Status16
17
24 September 2012M.Friedl (HEPHY Vienna): SVD Status17 Sensors Ladder Assembly Mechanics Cooling Electronics Summary
18
Electronics: Front-end All Origami versions and most other parts (edge hybrids, pitch adapters) are ready Remaining parts can simply be derived from existing designs and will be ready by the end of 2012 New idea: all barrel sensors to be read out with Origami? 24 September 2012M.Friedl (HEPHY Vienna): SVD Status18
19
Electronics: Junction Box Junction Box 24 September 2012M.Friedl (HEPHY Vienna): SVD Status19 Rad-hard DC/DC converters instead of regulators Tested with APV25 hybrids: no noise penalty
20
Electronics: FADC Milestones FADC Design completed Analog & digital level translation boards built and tested OK Now working on PCB layout Surrounding components FADC Controller, Buffer, Backplane Will be designed after FADC Full prototype system to be built in Q1/2013 Based closely on existing readout system built in 2007 Big system test with PXD and beam in October 2013 @ DESY 24 September 2012M.Friedl (HEPHY Vienna): SVD Status20
21
Electronics: FTB (DAQ Link) Firmware development ongoing Optical link tests at 2.54 and 3.175 Gb/s successful Second iteration of PCB for minor corrections underway 24 September 2012M.Friedl (HEPHY Vienna): SVD Status21
22
24 September 2012M.Friedl (HEPHY Vienna): SVD Status22 Sensors Ladder Assembly Mechanics Cooling Electronics Summary
23
Lots of progress in all fields Detailed (and maintained) schedule available on the web Sensors all deliveries to be completed in 2013 Ladder assembly Prototype ladder in early 2013, series production in late 2013 Mechanics Overall geometry solved, now optimizing details Cooling Mockup tests at DESY Electronics DC/DC converters tested OK, FADC layout in progress 24 September 2012M.Friedl (HEPHY Vienna): SVD Status23