VIA University College JMOG VIA University College Agenda – Quantities soil work Physical state and density Quantities of soil – Truncated pyramid – Truncated.

Similar presentations


Presentation on theme: "VIA University College JMOG VIA University College Agenda – Quantities soil work Physical state and density Quantities of soil – Truncated pyramid – Truncated."— Presentation transcript:

1 VIA University College JMOG VIA University College Agenda – Quantities soil work Physical state and density Quantities of soil – Truncated pyramid – Truncated cone – Square net method – The very simple method Opgaver – Indbygning – Jordmængde Dagens link

2 VIA University College JMOG VIA University College Physical state and density Physical state: -Solid -Loose -Compressed Density (dry / humidified / wet)

3 VIA University College JMOG VIA University College Quantities – Truncated pyramid Example: Height, h = 5 m BIG square, G = 400 m 2 SMALL square, g = 100 m 2 Remember top soil – how much was that in average?

4 VIA University College JMOG VIA University College Quantities – Truncated cone Example: Height, h = 10 m SMALL radius, a = 10 m BIG radius, b = 20 m Remember top soil – how much was that in average?

5 VIA University College JMOG VIA University College Quantities – Square net method Where a 2 = grid area h = difference between existing kote and new kote (=depth) Example: a 2 er 1*1 m 2 = 1 m 2 h 1 = 0,5 m h 2 = 0,7 m h 3 = 0,6 m h 4 = 1,6 m Remember top soil – how much was that in average?

6 VIA University College JMOG VIA University College Quantities – The very simple method Existing plane and new plane are devited in suitable triangles according to fit the new terrain This example in a1, a2 og a3 Remember top soil – how much was that in average?

7 VIA University College JMOG VIA University College Advantages and Disadvantages To be disquessed….. First 3 methodsThe very simple method

8 VIA University College JMOG VIA University College Assignment – Building in sand Building in 100 m 3 of sand How much sand should we order to the buildingsite? How much does the sand weight if it is wet? Why do we need these informations and calculations?

9 VIA University College JMOG VIA University College Assignment – Quantities of soil Our client would like to have a copy of this area. How much soil should be removed?

10 VIA University College JMOG VIA University College Assignment – Quantities of soil


Download ppt "VIA University College JMOG VIA University College Agenda – Quantities soil work Physical state and density Quantities of soil – Truncated pyramid – Truncated."