Loss Normal Loss : The Loss which was expected
Abnormal Loss : The Loss which was not expected
4
Example A & Co manufactured 500 ceiling fans to fill an order by incurring : Direct material Rs. 150,000 Direct Labor Cost ,000 F.O.H (60% of Labor cost) ,000 Total Factory Cost ,10,000
5
Solution Work in process 310,000 Material 150,000 Payroll 100,000
F.O.H applied ,000
6
Rework Cost on Defective Work
Material Rs. 1,000 Labor ,000 F.O.H (60% of Labor cost) ,800
7
Solution Normal Loss Abnormal Loss F.O.H Control 5800 Material 1000
Labor F.O.H Material Lab FOH Work in process
8
Solution Normal Loss Abnormal Loss Finish goods 310,000
Work in process ,000 Finish goods 368,000 Work in process 368,000
9
Per Unit Cost Cost of goods manufactured units manufactured
Normal Loss Abnormal Loss 310,000 500 = 620 368,000 = 736
10
Example Spoiled inventory units 50 fans. Spoiled units
Total cost = 310,000 x 50 =31000 500
11
Example Spoiled inventory units 50 fans (Alternative option) .
Spoiled units Material ,000 x =15,000 500 Labor ,000 x = 10,000 FOH ,000 x = 6,000 31,000
12
Spoiled Goods Normal Loss Abnormal Loss Scrap Inventory 10,000
FOH Control ,000 Work in process ,000 Scrap Inventory 10,000 Work in process 10,000
13
Spoiled Goods Normal Loss Abnormal Loss Finish goods 279,000
Work in process 279,000 Finish goods 300,000 Work in process 300,000
14
Per Unit Cost in Spoiled Inventory
Cost of goods manufactured units manufactured Per unit cost = Normal Loss Abnormal Loss 279,000 450 =620 300,000 = 667
15
Material Requisition It is a document through which work station incharge received material from store.
16
Documents Material Requisition Work station incharge
Purchase Requisition Store incharge Purchase order Supplier
17
Important Documents
18
Purchase Requisition Description Material code Quantity
Saba & Co Lawrence Road Lahore. PURCHASE REQUISTION No: 614 Date of Request Date Wanted Request by department Description Material code Quantity Requested by Approved by COPY-1 PRCHASING DEP
19
Purchase Order STICH MASTER PURCHASE ORDER Township Lahore No. 2518
This number must appear on all packages and forms. Date To, Ship to: Date Wanted Ship Via FOB Terms Description Catalogue No Quantity
20
DEBIT NOTE Saba MASTERS Township Lahore. DEBIT NOTE No.-------
Date------ TO-(Supplier) We are debiting your account with the value of under mentioned material for the Reasons stated. Meanwhile we wait for your instruction. Quantity Description Rate Amount Reasons Date received Goods Received Note No
21
Store Ledger Card Qty Rate Amount
Date Receipt /Consumption Issue /Sale Balance Qty Rate Amount
22
Bin Card Re order level__________ Maximum level __________
EOQ _________________ Minimum level __________ Danger level ____________ Date Ref Quantity Received Quantity issued Balance
23
Inventory Turnover Ratio
Inventory Turnover ratio shows the stock position of the store room. In how many times inventory used. Inventory Turn over Ratio Cost of goods sold or Material consumed Average Inventory
24
Average Inventory Opening Inventory Closing Inventory 2
25
Example Opening stock 1000 units Material Purchase 7000 units
Closing Stock units Material consumed Rs. 7500
26
Material consumed Solution Inventory Turn over Ratio Average Inventory
7500 ( )/2 = = 10 time
27
Expression Of Inventory In Days
No of days Inventory Turn over Ratio = 36 days 10