Dave Addison August 2008 UK Link Data centre Move Wellingborough to Kettering
2
Introduction UK Link Technology refresh (UKLTR) commissioned two new Data centres with TCS in Feb 2008 Peterborough and Wellingborough We are now planning to exit from Wellingborough by 30 th September 2008 Operate from Kettering and Peterborough
3
Approach During the move we will: Run Services from Peterborough with Additional Resilience Move the Wellingborough kit to Kettering BT 211CN data centre that is available at the time of Wellingborough closure Initially run Kettering as Fail over Site Peterborough and Kettering resume DC Dual Capability once Kettering is fully operational
4
Existing Setup Intermediate Setup Final Setup PeterboroughWellingboroughKettering SA M INV Kettering DC build in progress SA M INV Addition al Resilienc e Kettering DC build Complete – tested- audited SA M Full dual site resilience Existing kitNew kit
5
High Level Timeline Active-Active data centre operations Active-Passive data centre operations Single data centre operation at P’boro (24 hours each) Production service failover 1 st Jul1 st Aug 1 st Sep1 st Oct 1 st Nov 1 576 P’boro – Kettering operations P’boro – W’boro operations 3 42 1 st Dec 1. 12th Aug - Delivery of additional hardware (for resilience) at P’boro 2. 23rd Aug - Temporary data centre area ready at Kettering 3. 29th Aug - Build and test completed for additional hardware at P’boro 4. 29th/30th Aug – Operate from P’boro with additional resilience 5. 15th Sep – Failover resilience available at Kettering 6. 30th Sep - Closure of W’boro data centre 7. 21st/22nd Nov – Full dual site resilience
6
Outages / Next Steps 29 th /30 th August – Peterborough Additional Resilience Implementation No shipper and network impacts as done in housekeeping windows All to send in files as usual Planned for a 5 hour system outage on Saturday 30th 17:30 – 22:30 as Contingency 15 th September 2008 – Transfer kit from Wellingborough to Kettering Wellingborough officially closes 30 th September Movement of kit independent of production service at Peterborough Moving and installation testing will take 24 hours Repeat a subset of the UKLTR Operational Acceptance Tests Kettering DC available as Fail over site
7
Outages / Next Steps 21 st /22 nd November – Full Dual Site Resilience No shipper and network impacts as done in housekeeping windows All to send in files as usual In event of failure, revert to using Peterborough as the main site. Planned for a 5 hour system outage on Saturday 30 th 17:30 – 22:30 as Contingency’