Download presentation
Presentation is loading. Please wait.
Published byDarlene Dean Modified over 8 years ago
1
4-1 Operations Management Forecasting Chapter 4
2
4-2 Learning Objectives When you complete this chapter, you should be able to : Identify or Define : Forecasting Types of forecasts Time horizons Approaches to forecasts
3
4-3 Learning Objectives - continued When you complete this chapter, you should be able to : Describe or Explain: Moving averages Exponential smoothing Trend projections Regression and correlation analysis Measures of forecast accuracy
4
4-4 What is Forecasting? Process of predicting a future event Underlying basis of all business decisions Production Inventory Personnel Facilities
5
4-5 Short-range forecast Up to 1 year; usually less than 3 months Job scheduling, worker assignments Medium-range forecast 3 months to 3 years Sales & production planning, budgeting Long-range forecast 3 + years New product planning, facility location Types of Forecasts by Time Horizon
6
4-6 Short-term vs. Longer-term Forecasting Medium/long range forecasts deal with more comprehensive issues and support management decisions regarding planning and products, plants and processes. Short-term forecasting usually employs different methodologies than longer-term forecasting Short-term forecasts tend to be more accurate than longer-term forecasts.
7
4-7 Influence of Product Life Cycle Stages of introduction and growth require longer forecasts than maturity and decline Forecasts useful in projecting staffing levels, inventory levels, and factory capacity as product passes through life cycle stages Introduction, Growth, Maturity, Decline
8
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458 4-8 Types of Forecasts Economic forecasts Address business cycle, e.g., inflation rate, money supply etc. Technological forecasts Predict rate of technological progress Predict acceptance of new product Demand forecasts Predict sales of existing product
9
4-9 Seven Steps in Forecasting Determine the use of the forecast Select the items to be forecasted Determine the time horizon of the forecast Select the forecasting model(s) Gather the data Make the forecast Validate and implement results
10
4-10 Product Demand Charted over 4 Years with Trend and Seasonality Year 1 Year 2 Year 3 Year 4 Seasonal peaksTrend component Actual demand line Average demand over four years Demand for product or service Random variation
11
4-11 Actual Demand, Moving Average, Weighted Moving Average Actual sales Moving average Weighted moving average
12
4-12 Realities of Forecasting Forecasts are seldom perfect Most forecasting methods assume that there is some underlying stability in the system Both product family and aggregated product forecasts are more accurate than individual product forecasts
13
4-13 Forecasting Approaches Used when situation is ‘stable’ & historical data exist Existing products Current technology Involves mathematical techniques e.g., forecasting sales of color televisions Quantitative Methods Used when situation is vague & little data exist New products New technology Involves intuition, experience e.g., forecasting sales on Internet Qualitative Methods
14
4-14 Overview of Qualitative Methods Jury of executive opinion Pool opinions of high-level executives, sometimes augment by statistical models Delphi method Panel of experts, queried iteratively Sales force composite Estimates from individual salespersons are reviewed for reasonableness, then aggregated Consumer Market Survey Ask the customer
15
4-15 Involves small group of high-level managers Group estimates demand by working together Combines managerial experience with statistical models Relatively quick ‘Group-think’ disadvantage Jury of Executive Opinion
16
4-16 Sales Force Composite Each salesperson projects his or her sales Combined at district & national levels Sales reps know customers’ wants Tends to be overly optimistic
17
4-17 Delphi Method Iterative group process 3 types of people Decision makers Staff Respondents Reduces ‘group-think’ Respondents Staff Decision Makers (Sales?) ( What will sales be? survey) (Sales will be 45, 50, 55) (Sales will be 50!)
18
4-18 Consumer Market Survey Ask customers about purchasing plans What consumers say, and what they actually do are often different Sometimes difficult to answer How many hours will you use the Internet next week?
19
4-19 Overview of Quantitative Approaches Naïve approach Moving averages Exponential smoothing Trend projection Linear regression Time-series Models Associative models
20
4-20 Quantitative Forecasting Methods (Non-Naive) Quantitative Forecasting Linear Regression Associative Models Exponential Smoothing Moving Average Time Series Models Trend Projection
21
4-21 Set of evenly spaced numerical data Obtained by observing response variable at regular time periods Forecast based only on past values Assumes that factors influencing past and present will continue influence in future Example Year:19981999200020012002 Sales:78.763.589.793.292.1 What is a Time Series?
22
4-22 Trend Seasonal Cyclical Random Time Series Components
23
4-23 Persistent, overall upward or downward pattern Due to population, technology etc. Several years duration Mo., Qtr., Yr. Response Trend Component
24
4-24 Regular pattern of up & down fluctuations Due to weather, customs etc. Occurs within 1 year Mo., Qtr. Response Summer Seasonal Component
25
4-25 Common Seasonal Patterns Period of Pattern “Season” Length Number of “Seasons” in Pattern WeekDay7 MonthWeek4 – 4 ½ MonthDay28 – 31 YearQuarter4 YearMonth12 YearWeek52
26
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458 4-26 Repeating up & down movements Due to interactions of factors influencing economy Usually 2-10 years duration Mo., Qtr., Yr. Response Cycle Cyclical Component
27
4-27 Erratic, unsystematic, ‘residual’ fluctuations Due to random variation or unforeseen events Union strike Tornado Short duration & nonrepeating Random Component
28
4-28 Any observed value in a time series is the product (or sum) of time series components Multiplicative model Y i = T i · S i · C i · R i (if quarterly or mo. data) Additive model Y i = T i + S i + C i + R i (if quarterly or mo. data) General Time Series Models
29
4-29 Naive Approach Assumes demand in next period is the same as demand in most recent period e.g., If May sales were 48, then June sales will be 48 Sometimes cost effective & efficient
30
4-30 MA is a series of arithmetic means Used if little or no trend Used often for smoothing Provides overall impression of data over time Equation MA n n Demand in Previous Periods Periods Moving Average Method
31
4-31 You’re manager of a museum store that sells historical replicas. You want to forecast sales (000) for 2003 using a 3-period moving average. 19984 1999 6 20005 20013 20027 Moving Average Example
32
4-32 Moving Average Solution
33
4-33 Moving Average Solution
34
4-34 Moving Average Solution
35
4-35 959697989900 Year Sales 2 4 6 8 Actual Forecast Moving Average Graph
36
4-36 Used when trend is present Older data usually less important Weights based on intuition Often lay between 0 & 1, & sum to 1.0 Equation WMA = Σ(Weight for period n) (Demand in period n) ΣWeights Weighted Moving Average Method
37
4-37 Actual Demand, Moving Average, Weighted Moving Average Actual sales Moving average Weighted moving average
38
4-38 Increasing n makes forecast less sensitive to changes Do not forecast trend well Require much historical data Disadvantages of Moving Average Methods
39
4-39 Form of weighted moving average Weights decline exponentially Most recent data weighted most Requires smoothing constant ( ) Ranges from 0 to 1 Subjectively chosen Involves little record keeping of past data Exponential Smoothing Method
40
4-40 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 ·A t - 3 + (1- ) 3 A t - 4 +... + (1- ) t- 1 ·A 0 F t = Forecast value A t = Actual value = Smoothing constant F t = F t -1 + ( A t -1 - F t -1 ) Use for computing forecast Exponential Smoothing Equations
41
4-41 During the past 8 quarters, the Port of Baltimore has unloaded large quantities of grain. ( =.10). The first quarter forecast was 175.. QuarterActual 1180 2168 3159 4175 5190 6205 7180 8182 9? Exponential Smoothing Example Find the forecast for the 9 th quarter.
42
4-42 F t = F t -1 + 0.1( A t -1 - F t -1 ) QuarterActual Forecast, F t ( α =.10) 1 180175.00 (Given) 2168 3159 4175 5190 6 205 175.00 + Exponential Smoothing Solution
43
4-43 Quarter Actua Actual Forecast, F t ( α =.10) 1180 175.00 (Given) 2168 175.00 +.10( 3159 4175 5190 6205 Exponential Smoothing Solution F t = F t -1 + 0.1( A t -1 - F t -1 )
44
4-44 QuarterActual Forecast,F t ( α =.10) 1180 175.00 (Given) 2168 175.00 +.10(180 - 3159 4175 5190 6205 Exponential Smoothing Solution F t = F t -1 + 0.1( A t -1 - F t -1 )
45
4-45 QuarterActual Forecast,F t ( α =.10) 1180 175.00 (Given) 2168 175.00 +.10(180 - 175.00) 3159 4175 5190 6205 Exponential Smoothing Solution F t = F t -1 + 0.1( A t -1 - F t -1 )
46
4-46 QuarterActual Forecast,F t ( αααα =.10) 1180 175.00 (Given) 2168 175.00 +.10(180 - 175.00) = 175.50 3159 4175 5190 6205 Exponential Smoothing Solution F t = F t -1 + 0.1( A t -1 - F t -1 )
47
4-47 F t = F t -1 + 0.1( A t -1 - F t -1 ) QuarterActual Forecast, F t ( α =.10) 1180175.00 (Given) 2168 175.00 +.10(180 - 175.00) = 175.50 3159 175.50 +.10(168 - 175.50) = 174.75 4175 5190 6205 Exponential Smoothing Solution
48
4-48 F t = F t -1 + 0.1( A t -1 - F t -1 ) Quarter Actual Forecast, F t ( α =.10) 1995180175.00 (Given) 1996168175.00 +.10(180 - 175.00) = 175.50 1997159175.50 +.10(168 - 175.50) = 174.75 1998175 1999190 2000205 174.75 +.10(159 - 174.75)= 173.18 Exponential Smoothing Solution
49
4-49 F t = F t -1 + 0.1( A t -1 - F t -1 ) QuarterActual Forecast, F t ( α =.10) 1180175.00 (Given) 2168175.00 +.10(180 - 175.00) = 175.50 3159175.50 +.10(168 - 175.50) = 174.75 4 175174.75 +.10(159 - 174.75) = 173.18 5190173.18 +.10(175 - 173.18) = 173.36 6205 Exponential Smoothing Solution
50
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458 4-50 F t = F t -1 + 0.1( A t -1 - F t -1 ) QuarterActual Forecast, F t ( α =.10) 1180175.00 (Given) 2168175.00 +.10(180 - 175.00) = 175.50 3159175.50 +.10(168 - 175.50) = 174.75 4175174.75 +.10(159 - 174.75) = 173.18 5190173.18 +.10(175 - 173.18) = 173.36 6205173.36 +.10(190 - 173.36) = 175.02 Exponential Smoothing Solution
51
4-51 F t = F t -1 + 0.1( A t -1 - F t -1 ) TimeActual Forecast, F t ( α =.10) 4175174.75 +.10(159 - 174.75) = 173.18 5190173.18 +.10(175 - 173.18) = 173.36 6205173.36 +.10(190 - 173.36) = 175.02 Exponential Smoothing Solution 7180 8 175.02 +.10(205 - 175.02) = 178.02 9
52
4-52 F t = F t -1 + 0.1( A t -1 - F t -1 ) TimeActual Forecast, F t ( α =.10) 4 175174.75 +.10(159 - 174.75) = 173.18 5 190173.18 +.10(175 - 173.18) = 173.36 6 205173.36 +.10(190 - 173.36) = 175.02 Exponential Smoothing Solution 7 180 8 175.02 +.10(205 - 175.02) = 178.02 9 178.22 +.10(182 - 178.22) = 178.58 182 178.02 +.10(180 - 178.02) = 178.22 ?
53
4-53 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 A t - 3 +... Forecast Effects of Smoothing Constant Weights Prior Period 2 periods ago (1 - ) 3 periods ago (1 - ) 2 == = 0.10 = 0.90 10%
54
4-54 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 A t - 3 +... Forecast Effects of Smoothing Constant Weights Prior Period 2 periods ago (1 - ) 3 periods ago (1 - ) 2 == = 0.10 = 0.90 10% 9%
55
4-55 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 A t - 3 +... Forecast Effects of Smoothing Constant Weights Prior Period 2 periods ago (1 - ) 3 periods ago (1 - ) 2 == = 0.10 = 0.90 10% 9% 8.1%
56
4-56 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 A t - 3 +... Forecast Effects of Smoothing Constant Weights Prior Period 2 periods ago (1 - ) 3 periods ago (1 - ) 2 == = 0.10 = 0.90 10% 9% 8.1% 90%
57
4-57 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 A t - 3 +... Forecast Effects of Smoothing Constant Weights Prior Period 2 periods ago (1 - ) 3 periods ago (1 - ) 2 == = 0.10 = 0.90 10% 9% 8.1% 90%9%
58
4-58 F t = A t - 1 + (1- ) A t - 2 + (1- ) 2 A t - 3 +... Forecast Effects of Smoothing Constant Weights Prior Period 2 periods ago (1 - ) 3 periods ago (1 - ) 2 == = 0.10 = 0.90 10% 9% 8.1% 90%9%0.9%
59
4-59 Choosing Seek to minimize the Mean Absolute Deviation (MAD) If:Forecast error = demand - forecast Then:
60
4-60 Exponential Smoothing with Trend Adjustment Forecast including trend (FIT t ) = exponentially smoothed forecast (F t ) + exponentially smoothed trend (T t )
61
4-61 F t = Last period’s forecast + (Last period’s actual – Last period’s forecast) F t = F t-1 + (A t-1 – F t-1 ) or T t = (Forecast this period - Forecast last period) + (1- )(Trend estimate last period T t = (F t - F t-1 ) + (1- )T t-1 or Exponential Smoothing with Trend Adjustment - continued
62
4-62 F t = exponentially smoothed forecast of the data series in period t T t = exponentially smoothed trend in period t A t = actual demand in period t = smoothing constant for the average = smoothing constant for the trend Exponential Smoothing with Trend Adjustment - continued
63
4-63 Comparing Actual and Forecasts
64
4-64 Regression
65
4-65 Least Squares Deviation Time Values of Dependent Variable Actual observation Point on regression line
66
4-66 Used for forecasting linear trend line Assumes relationship between response variable, Y, and time, X, is a linear function Estimated by least squares method Minimizes sum of squared errors i YabX i Linear Trend Projection
67
4-67 b > 0 b < 0 a a Y Time, X Linear Trend Projection Model
68
4-68 Least Squares Equations Equation: Slope: Y-Intercept:
69
4-69 Computation Table
70
4-70 Using a Trend Line YearDemand 1997 74 1998 79 1999 80 2000 90 2001 105 2002 142 2003 122 The demand for electrical power at N.Y.Edison over the years 1997 – 2003 is given at the left. Find the overall trend.
71
4-71 Finding a Trend Line YearTime Period Power Demand x2x2 xy 19971741 19982794158 19993809240 200049016360 2001510525525 2002614236852 2003712249854 x=28 y=692 x 2 =140 xy=3,063
72
4-72 The Trend Line Equation
73
4-73 Multiplicative Seasonal Model Find average historical demand for each “season” by summing the demand for that season in each year, and dividing by the number of years for which you have data. Compute the average demand over all seasons by dividing the total average annual demand by the number of seasons. Compute a seasonal index by dividing that season’s historical demand (from step 1) by the average demand over all seasons. Estimate next year’s total demand Divide this estimate of total demand by the number of seasons, then multiply it by the seasonal index for that season. This provides the seasonal forecast.
74
4-74 YX ii = a b Shows linear relationship between dependent & explanatory variables Example: Sales & advertising ( not time) Dependent (response) variable Independent (explanatory) variable Slope Y-intercept ^ Linear Regression Model +
75
4-75 Y X Y a i ^ ii bX i = ++ + Error Observed value YabX = ++ Regression line Linear Regression Model
76
4-76 Linear Regression Equations Equation: Slope: Y-Intercept:
77
4-77 Computation Table
78
4-78 Slope ( b ) Estimated Y changes by b for each 1 unit increase in X If b = 2, then sales ( Y ) is expected to increase by 2 for each 1 unit increase in advertising ( X ) Y-intercept ( a ) Average value of Y when X = 0 If a = 4, then average sales ( Y ) is expected to be 4 when advertising ( X ) is 0 Interpretation of Coefficients
79
4-79 Variation of actual Y from predicted Y Measured by standard error of estimate Sample standard deviation of errors Denoted S Y,X Affects several factors Parameter significance Prediction accuracy Random Error Variation
80
4-80 Least Squares Assumptions Relationship is assumed to be linear. Plot the data first - if curve appears to be present, use curvilinear analysis. Relationship is assumed to hold only within or slightly outside data range. Do not attempt to predict time periods far beyond the range of the data base. Deviations around least squares line are assumed to be random.
81
4-81 Standard Error of the Estimate
82
4-82 Answers: ‘ how strong is the linear relationship between the variables?’ Coefficient of correlation Sample correlation coefficient denoted r Values range from -1 to +1 Measures degree of association Used mainly for understanding Correlation
83
4-83 Sample Coefficient of Correlation
84
4-84 +1.00 Perfect Positive Correlation Increasing degree of negative correlation -.5+.5 Perfect Negative Correlation No Correlation Increasing degree of positive correlation Coefficient of Correlation Values
85
4-85 Coefficient of Correlation and Regression Model r 2 = square of correlation coefficient (r), is the percent of the variation in y that is explained by the regression equation
86
4-86 You want to achieve: No pattern or direction in forecast error Error = ( Y i - Y i ) = (Actual - Forecast) Seen in plots of errors over time Smallest forecast error Mean square error (MSE) Mean absolute deviation (MAD) Guidelines for Selecting Forecasting Model ^
87
4-87 Time (Years) Error 0 0 Desired Pattern Time (Years) Error 0 Trend Not Fully Accounted for Pattern of Forecast Error
88
4-88 Mean Square Error (MSE) Mean Absolute Deviation (MAD) Mean Absolute Percent Error (MAPE) Forecast Error Equations
89
4-89 You’re a marketing analyst for Hasbro Toys. You’ve forecast sales with a linear model & exponential smoothing. Which model do you use? ActualLinear ModelExponential Smoothing YearSalesForecastForecast (.9) 199810.61.0 199911.31.0 200022.01.9 200122.72.0 200243.43.8 Selecting Forecasting Model Example
90
4-90 MSE = Σ Error 2 / n = 1.10 / 5 = 0.220 MAD = Σ |Error| / n = 2.0 / 5 = 0.400 MAPE = 100 Σ|absolute percent errors|/ n = 1.20/5 = 0.240 Linear Model Evaluation Y i 1 1 2 2 4 ^ Y i ^ 0.6 1.3 2.0 2.7 3.4 Year 1998 1999 2000 2001 2002 Total 0.4 -0.3 0.0 -0.7 0.6 0.0 Error 0.16 0.09 0.00 0.49 0.36 1.10 Error 2 0.4 0.3 0.0 0.7 0.6 2.0 |Error| Actual 0.40 0.30 0.00 0.35 0.15 1.20
91
PowerPoint presentation to accompany Heizer/Render – Principles of Operations Management, 5e, and Operations Management, 7e © 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 07458 4-91 MSE = Σ Error 2 / n = 0.05 / 5 = 0.01 MAD = Σ |Error| / n = 0.3 / 5 = 0.06 MAPE = 100 Σ |Absolute percent errors|/ n = 0.10/5 = 0.02 Exponential Smoothing Model Evaluation
92
4-92 Exponential Smoothing Model Evaluation Linear Model: MSE = Σ Error 2 / n = 1.10 / 5 =.220 MAD = Σ |Error| / n = 2.0 / 5 =.400 MAPE = 100 Σ|absolute percent errors|/ n = 1.20/5 = 0.240 Exponential Smoothing Model: MSE = Σ Error 2 / n = 0.05 / 5 = 0.01 MAD = Σ |Error| / n = 0.3 / 5 = 0.06 MAPE = 100 Σ |Absolute percent errors|/ n = 0.10/5 = 0.02
93
4-93 Measures how well the forecast is predicting actual values Ratio of running sum of forecast errors (RSFE) to mean absolute deviation (MAD) Good tracking signal has low values Should be within upper and lower control limits Tracking Signal
94
4-94 Tracking Signal Equation
95
4-95 Tracking Signal Computation
96
4-96 Tracking Signal Computation
97
4-97 Tracking Signal Computation
98
4-98 Tracking Signal Computation
99
4-99 Tracking Signal Computation
100
4-100 Tracking Signal Computation
101
4-101 Tracking Signal Computation
102
4-102 Tracking Signal Computation
103
4-103 Tracking Signal Computation
104
4-104 Tracking Signal Computation
105
4-105 Tracking Signal Computation
106
4-106 Tracking Signal Computation
107
4-107 Tracking Signal Computation
108
4-108 Forecasting in the Service Sector Presents unusual challenges special need for short term records needs differ greatly as function of industry and product issues of holidays and calendar unusual events
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.