Presentation is loading. Please wait.

Presentation is loading. Please wait.

… getting there … 112/02/2014A. Fabich, EN-MEF-LE.

Similar presentations


Presentation on theme: "… getting there … 112/02/2014A. Fabich, EN-MEF-LE."— Presentation transcript:

1 … getting there … 112/02/2014A. Fabich, EN-MEF-LE

2 GIF today 212/02/2014A. Fabich, EN-MEF-LE False floor Cable trays Service area illumination

3 Schedule 3  EN/EL installation until mid September  Irradiator delivery mid September  Irradiator Site-Acceptance-Test at end September  Limited access to EHN1 during few periods of couple of hours  Commissioning with beam in December 12/02/2014A. Fabich, EN-MEF-LE

4 PPE152 shielding 413/5/2014A. Fabich Central passage NA61 target beam

5 Modifications on the Jura side 512/02/2014A. Fabich, EN-MEF-LE

6 PPE152 works 6  August – completed:  Disconnecting NA61 racks, cables and piping  Removal of gang way and (unnecessary) beam line blocks  First layer of blocks installed  Minor actions from September until end of the year  NA61 commissioning  Completing installation in December/January  See EDMS 1364026 for details 12/02/2014A. Fabich, EN-MEF-LE


Download ppt "… getting there … 112/02/2014A. Fabich, EN-MEF-LE."

Similar presentations


Ads by Google