Download presentation
Presentation is loading. Please wait.
Published byAlexander Gregory Modified over 8 years ago
1
Crabbed Waist Scheme at DA NE M. Zobov for DA NE Upgrade Team SuperB IV, 13-15 November 2006 Monte Porzio Catone - Italy
2
Main Purposes 1.To increase the DA NE luminosity by one order of magnitude 2.To test the “crabbed waist” idea – the basic idea of the SuperB project
3
Good occasion to perform the experiment at DA NE 1.Fits DA NE schedule (shut down for SIDDHARTA installation in mid 2007) 2.Satisfies new physics programs (SIDDHARTA, KLOE2,....) 3.Requires minor modifications 4.Relatively low cost (1 mln Euro) 5.No magnetic detectors, no splitter magnets, almost no parasitic crossings
4
32 nd LNF Scientific Committee 31 May-1June 2006 a) b) c)
5
Energy, GeV 0.51 Circumference, m97.69 RF Frequency, MHz368.26 Harmonic Number120 Damping Time, ms17.8/36.0 Bunch Length, cm1-3 Emittance, mm x mrad0.34 Coupling, %0.2-0.3 Beta Function at IP, m1.7/0.017 Max. Tune Shifts.03-.04 Number of Bunches111 Max.Beam Currents, A2.4/1.4 DA NE Parameters (KLOE configuration)
6
Best Daily Integrated Luminosity 10 pb -1 /day L max = 1.53x10 32 cm -2 s -1
7
1.Large Piwinski’s angle = tg( z / x 2.Vertical beta comparable with overlap area y x / 3.Crabbed waist transformation y = xy’/(2 ) Crabbed Waist in 3 Steps P. Raimondi, November 2005
8
Parameters used in simulations Horizontal beta @ IP0.2 m (1.7 m) Vertical beta @ IP0.65 cm (1.7 cm) Horizontal tune5.057 Vertical tune5.097 Horizontal emittance0.2 mm.mrad (0.3) Coupling0.5% Bunch length20 mm (32mm,24mm) Total beam current2 A (2.4A, 1.4A) Number of bunches110 (110) Total crossing angle50 mrad (25 mrad) Horizontal beam-beam tune shift0.011 Vertical beam-beam tune shift0.080 L => 2.2 x 10 33 cm -2 s -1
9
With the present achieved beam parameters (currents, emittances, bunchlenghts etc) a luminosity in excess of 10 33 is predicted. With 2Amps/2Amps more than 2*10 33 is possible Beam-Beam limit is way above the reachable currents M. Zobov (BBC Code by Hirata)
10
Beam-Beam Tails at (0.057;0.097) A x = ( 0.0, 12 x ); A y = (0.0, 160 y )
11
Siddharta IR Luminosity Scan Crab On --> 0.6/ Crab Off L max = 2.97x10 33 cm -2 s -1 L min = 2.52x10 32 cm -2 s -1 L max = 1.74x10 33 cm -2 s -1 L min = 2.78x10 31 cm -2 s -1
12
Crab On: Crab Off: Lmax = 2.97 x 10 33 Lmin = 2.52 x 10 32 Lmax = 1.74 x 10 33 Lmin = 2.78 x 10 31
13
Siddharta IR Luminosity Scan above half-integers L max = 3.05 x 10 33 cm -2 s -1 L min = 3.28 x 10 31 cm -2 s -1
14
Optics, exists a good solution that meets all the requirements: IP-betas emittances phase advance wrt sextupoles dynamic aperture compatibility with old “Dear” parameters background lifetimes physical layout
15
Optical functions and dynamic apertures > 20 sigma_x > 12 sigma_y full coupled
16
IR optics x =0.2m y =6.0mm New betas x =1.4m y =19.0mm Old betas M.Biagini
17
Near IR Layout No splitters (on both sides) No dispersion in sextupoles due to splitters Needs new extremely simplified vacuum pipe (round everywhere, apart the y-one) Dipole fields need to be adjusted (B long lower, B short higher) use splitters power supplies Doublets will be PM All the other elements (quads, sexts etc) are in place, need just to be moved nearby Design almost completed
18
IR layout New beam line IP QD0sQF1s M.Biagini
19
IR: Defined the solution for the Interaction region Permanent Magnets Quads design almost completed by the vendor cost estimate by the vendor vacuum pipe design almost completed
20
View of the modified IR1 region Similar modifications will be made in the IR2, without the low-beta insertion In addition in IR2 the two lines will be Vertically Separated Siddharta
21
QD0 Qf1s Permanent SmCo quads already ordered (about 380K$ for 6 quads) All other IR magnets and power supplies reused Most of the Vacuum Pipes and pumps reused New Vacuum pipes and pumps around 50K$
23
MAFIA Time Domain Simulations B.Spataro and M.Zobov, 04/10/2006 σ z (cm) K l (V/Q) W max (V/Q) W min (V/Q) Z / n (mΩ) P (Watts) 13.589 10 10 1.382 10 11 -9.577 10 10 12.2516 1.51.260 10 10 4.152 10 10 -4.717 10 10 8.24181 2.5.766 10 9 2.699 10 10 -2.777 10 10 9.5283 2.52.609 10 9 2.101 10 10 -1.833 10 10 11.5838 3.01.104 10 9 1.602 10 10 -1.300 10 10 12.7116 I = 20 mA N = 110 bunches f 0 = 3.06 MHz 3D model 2D cross-section
24
B.Spataro and M.Zobov, 13/10/2006
25
mode1mode2mode3mode4 Driven mode solution Short circuit at ports F.Marcellini and D. Alesini 150 W
27
Measures to Increase Positron Current 1.New Injection Kickers 2.New Feedback Systems 3.Ti-Coating
28
New Injection Kickers Expected benefits: higher maximum stored currents Improved stability of colliding beams during injection less background allowing acquisition on during injection ? (D. Alesini and F. Marcellini) New injection kickers with 5.4 ns pulse length have been designed to reduce the perturbation on the stored beam during injection present pulse length ~150ns (old kickers) t t VTVT VTVT FWHM pulse length ~5.4 ns 50 bunches 3 bunches
29
Kickers: design completed, asked vendors for offers test of the pulsers in progress - one borrowed for preliminary tests (30KV max) - one tested up to 50 KV, but out of specks for time- duration - one more shipped (in specks) still problems on the high-voltage feed through (found a working solution already, but working on improvements)
30
Third generation digital bunch-by-bunch feedback system designed for SuperB factory (collaboration SLAC-KEK-LNF) - Features: - extremely compact - gain & phase digital and remote control - possibility to manage any betatron or synchrotron tunes - robust response to big oscillations due to injection (using FIR filter at 8/16 taps) - real time parameter monitoring - powerful beam diagnostics - main DSP loop based on FPGA (Field Programmable Gate Array) iGp the new feedback system under test at SLAC, KEK and LNF A.Drago
31
Multipurpose remotized positioning system y x ICE removal
32
ICE removed
33
Bunch Length Reduction Before at 130 kV Now at 130 kV Now at 180 kV 30% 30% reduction in the e - bunch length as expected no quadrupole instability
34
e - vertical vize Blow up f(V RF, I b ) Data taken during the last KLOE run before ICE removal ! Presently no beam blow up observed with: RF voltage Beam current
35
Wiggling wiggler Motivation: Build wiggler poles symmetric with respect to the beam orbit Wigglers pole modifications: design completed poles should be replaced during the shutdown
36
Cost estimate Kilo-Euros PM quads 300 IR1 vacuum chambers 30 IR2 vacuum chambers20 Kickers pulsers 200 Kickers50 Matching chambers for kickers (and valves)50 Vacuum pumps10 New wigglers poles 200 External labor60 Contingency100 Total 1020
37
Conclusions 1.Numerical simulations give encouraging results 2.Engineering design (mechanical, vacuum, electromagnetic..) is well in progress. 3.We hope to start the crabbed waist collisions already in 2007.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.