ROAD NETWORK The total length of identifiable feeder roads in the Greater Accra Region is 1,327.10km. Composition: Engineered roads-1,204.51km (90.77%) Partially Engineered- 33.24km (2.50%) Non-Engineered road- 89.35km (6.73%)
4
Surface Type distribution as at September 2015 Surface TypeLength (km)Percentage Bitumen180.0513.56% Gravel697.5852.55% Earth449.9133.89% Total1,327.54100.00%
5
PROGRAMME & PROGRESS FOR 2015 Routine Maintenance Programme All engineered roads on the feeder roads network which have not been captured under any periodic maintenance programme are currently being reshaped under our routine maintenance programme.
6
PROGRAMME & PROGRESS FOR 2015 Cont. Bridges Contract Name Funding Source % Completion Remarks Construction of steel bridge over River Abuvie on Abuviekporm Jnc.-Abuviekporm F/Rd Acrow100 Substantially complete Emergency Replacement of Dilapidated Wooden Footbridge with 39.3m Steel Bridge over River Densu on Tetegu Jnc.-Tetegu Road Dutch95 Substantially complete Construction of composite bridge over River Densu at Ayikai Doblo & Bitumen Surfacing of Kasoa-Amasaman Rd Cocobod38.4 Terminated and handed over to DUR
7
PROGRAMME & PROGRESS FOR 2015 Cont. GOG Funded Labour Based Projects Road Name % CompletionRemarks Mmapehia Jn.–Mmapehia & Otaten – Fawotekose F/d (5.2km) 56.25%Ongoing Talebanya Junc. – Talebanya &Nuhuale Junc. – Nuhuale F/ds (6km) 15.00%Ongoing Ameyawkorpe – Safahukope Feeder Road (5km)72.40%Ongoing Ashalearnan – Fawotekose Feeder Road (4.2km)0.00% Contractor warned
8
PROGRAMME & PROGRESS FOR 2015 Cont. Cocobod Funded Projects - Surfacing Road Name % CompletionRemarks Prampram Town Roads F/Rd Ph I (3.1Km)100.00% Substantially Complete Adenta – Frafraha (Km 0+000 – 1+000)100.00% Substantially Complete Oyarifa–Teiman–Abokobi F/Rd Ph.I (Km 0+000 – 2+000)100.00% Substantially Complete Oyarifa–Teiman–Abokobi F/Rd Ph.II (Km 2+000 – 4+100)74.28%Ongoing Pokuase – Osonodompe F/Rd Ph.I (Km 4+000 – 6+000)65.00%Ongoing Pokuase – Osonodompe F/Rd Ph.II (Km 6+000 – 8+250)60.00%Ongoing Pokuase – Osonodompe F/Rd Ph III (Km 0+000 – 4+000)54.71%Ongoing Nyigbenya – Old Ningo F/Rd Ph I (Km 0+000 – 5+000)55.87%Ongoing Nyigbenya – Old Ningo F/Rd Ph II (Km 5+000 – 10+500)87.78%Ongoing Medie – Samsam F/Rd (Km 0+000 – 6+000)48.37%Ongoing
9
PROGRAMME & PROGRESS FOR 2015 Cont. Cocobod Funded Projects – Spot Improvement Road Name % CompletionRemarks Tofloko – Nakomkorpe F/Rd (4.5Km)100.00% Substantially Complete OLA Catholic Church – African Child School Road (2.5Km)100.00% Substantially Complete Danchira – Honi F/Rd (10.7Km)100.00% Substantially Complete Adenta – Commando F/Rd (5Km)100.00% Substantially Complete Abehenease – Obom F/Rd Ph I (Km 0+000 – 8+000)70.93%Ongoing Abehenease – Obom F/Rd Ph II (Km 8+000 – 17+000)100.00% Substantially Complete Abehenease – Opa - Sarpeiman F/Rd (4.5Km)50.00%Ongoing Omankorpe - Dawa F/Rd (7.5Km)53.82%Ongoing
10
PROGRAMME & PROGRESS FOR 2015 Cont. GOG Funded Projects – Surfacing Road Name % CompletionRemarks Afuaman – Nsakina-Bokoborkor (10km)50.00%Ongoing Borshe – Ashongman (2.9km)90.00%Ongoing Ashalaja – Nsuobri (11km)40.00%Ongoing Dawa – Ahwiam – Ningo Ph I (8km)17.09%Ongoing Dawa – Ahwiam – Ningo Ph II (4km)13.40%Ongoing Appolonia – Afienya Ph I (km 0+000-4+400)95.00%Ongoing Appolonia – Afienya Ph II (km 4+400-8+800)68.46%Ongoing Katamanso – S.G.M.C. (5.8km)79.00%Ongoing
11
Routine Maintenance Programme All engineered roads not been captured under any periodic maintenance programme will receive at least one frequency of routine maintenance in the year 2016. Periodic Maintenance Programme All ongoing projects which are not completed by the end of December, 2015 will spill over into the year 2016. Some terminated projects will also be considered for re-award MAINTENANCE PROGRAMME FOR 2016
12
SOME PROBLEMS ENCOUNTERED Inadequate fuel and other items allocated to the region for project supervision Insufficient funds to ensure smooth administration and timely servicing/maintenance of vehicles and office equipment Slow rate of performance by some contractors Delay in payments of contractors certificates affecting performance and increasing abandonment of projects.
13
Routine Maintenance (Before & After) Kordiabe – Ayikuma F/Rd Kasunya-Nyapienya F/Rd
14
SURFACING OF BORSHE – ASHONGMAN ROAD AFTER DURING CONSTRUCTION
15
SURFACING OF OBEYEYIE–AFUAMAN–BORKORBORKOR F/RD CURRENT CONDITION BEFORE COMMENCEMENT
16