DEPARTMENT OF FEEDER ROADS GREATER ACCRA REGION MAINTENANCE PROGRAMME FOR 2015 NOVEMBER 2015.

Similar presentations


Presentation on theme: "DEPARTMENT OF FEEDER ROADS GREATER ACCRA REGION MAINTENANCE PROGRAMME FOR 2015 NOVEMBER 2015."— Presentation transcript:

1 DEPARTMENT OF FEEDER ROADS GREATER ACCRA REGION MAINTENANCE PROGRAMME FOR 2015 NOVEMBER 2015

2 ORDER OF PRESENTATION  Feeder Roads Network  Programme & Progress for 2015  Programme for 2016  Challenges

3 ROAD NETWORK  The total length of identifiable feeder roads in the Greater Accra Region is 1,327.10km. Composition: Engineered roads-1,204.51km (90.77%) Partially Engineered- 33.24km (2.50%) Non-Engineered road- 89.35km (6.73%)

4 Surface Type distribution as at September 2015 Surface TypeLength (km)Percentage Bitumen180.0513.56% Gravel697.5852.55% Earth449.9133.89% Total1,327.54100.00%

5 PROGRAMME & PROGRESS FOR 2015 Routine Maintenance Programme  All engineered roads on the feeder roads network which have not been captured under any periodic maintenance programme are currently being reshaped under our routine maintenance programme.

6 PROGRAMME & PROGRESS FOR 2015 Cont. Bridges Contract Name Funding Source % Completion Remarks Construction of steel bridge over River Abuvie on Abuviekporm Jnc.-Abuviekporm F/Rd Acrow100 Substantially complete Emergency Replacement of Dilapidated Wooden Footbridge with 39.3m Steel Bridge over River Densu on Tetegu Jnc.-Tetegu Road Dutch95 Substantially complete Construction of composite bridge over River Densu at Ayikai Doblo & Bitumen Surfacing of Kasoa-Amasaman Rd Cocobod38.4 Terminated and handed over to DUR

7 PROGRAMME & PROGRESS FOR 2015 Cont. GOG Funded Labour Based Projects Road Name % CompletionRemarks Mmapehia Jn.–Mmapehia & Otaten – Fawotekose F/d (5.2km) 56.25%Ongoing Talebanya Junc. – Talebanya &Nuhuale Junc. – Nuhuale F/ds (6km) 15.00%Ongoing Ameyawkorpe – Safahukope Feeder Road (5km)72.40%Ongoing Ashalearnan – Fawotekose Feeder Road (4.2km)0.00% Contractor warned

8 PROGRAMME & PROGRESS FOR 2015 Cont. Cocobod Funded Projects - Surfacing Road Name % CompletionRemarks Prampram Town Roads F/Rd Ph I (3.1Km)100.00% Substantially Complete Adenta – Frafraha (Km 0+000 – 1+000)100.00% Substantially Complete Oyarifa–Teiman–Abokobi F/Rd Ph.I (Km 0+000 – 2+000)100.00% Substantially Complete Oyarifa–Teiman–Abokobi F/Rd Ph.II (Km 2+000 – 4+100)74.28%Ongoing Pokuase – Osonodompe F/Rd Ph.I (Km 4+000 – 6+000)65.00%Ongoing Pokuase – Osonodompe F/Rd Ph.II (Km 6+000 – 8+250)60.00%Ongoing Pokuase – Osonodompe F/Rd Ph III (Km 0+000 – 4+000)54.71%Ongoing Nyigbenya – Old Ningo F/Rd Ph I (Km 0+000 – 5+000)55.87%Ongoing Nyigbenya – Old Ningo F/Rd Ph II (Km 5+000 – 10+500)87.78%Ongoing Medie – Samsam F/Rd (Km 0+000 – 6+000)48.37%Ongoing

9 PROGRAMME & PROGRESS FOR 2015 Cont. Cocobod Funded Projects – Spot Improvement Road Name % CompletionRemarks Tofloko – Nakomkorpe F/Rd (4.5Km)100.00% Substantially Complete OLA Catholic Church – African Child School Road (2.5Km)100.00% Substantially Complete Danchira – Honi F/Rd (10.7Km)100.00% Substantially Complete Adenta – Commando F/Rd (5Km)100.00% Substantially Complete Abehenease – Obom F/Rd Ph I (Km 0+000 – 8+000)70.93%Ongoing Abehenease – Obom F/Rd Ph II (Km 8+000 – 17+000)100.00% Substantially Complete Abehenease – Opa - Sarpeiman F/Rd (4.5Km)50.00%Ongoing Omankorpe - Dawa F/Rd (7.5Km)53.82%Ongoing

10 PROGRAMME & PROGRESS FOR 2015 Cont. GOG Funded Projects – Surfacing Road Name % CompletionRemarks Afuaman – Nsakina-Bokoborkor (10km)50.00%Ongoing Borshe – Ashongman (2.9km)90.00%Ongoing Ashalaja – Nsuobri (11km)40.00%Ongoing Dawa – Ahwiam – Ningo Ph I (8km)17.09%Ongoing Dawa – Ahwiam – Ningo Ph II (4km)13.40%Ongoing Appolonia – Afienya Ph I (km 0+000-4+400)95.00%Ongoing Appolonia – Afienya Ph II (km 4+400-8+800)68.46%Ongoing Katamanso – S.G.M.C. (5.8km)79.00%Ongoing

11 Routine Maintenance Programme  All engineered roads not been captured under any periodic maintenance programme will receive at least one frequency of routine maintenance in the year 2016. Periodic Maintenance Programme  All ongoing projects which are not completed by the end of December, 2015 will spill over into the year 2016.  Some terminated projects will also be considered for re-award MAINTENANCE PROGRAMME FOR 2016

12 SOME PROBLEMS ENCOUNTERED  Inadequate fuel and other items allocated to the region for project supervision  Insufficient funds to ensure smooth administration and timely servicing/maintenance of vehicles and office equipment  Slow rate of performance by some contractors  Delay in payments of contractors certificates affecting performance and increasing abandonment of projects.

13 Routine Maintenance (Before & After) Kordiabe – Ayikuma F/Rd Kasunya-Nyapienya F/Rd

14 SURFACING OF BORSHE – ASHONGMAN ROAD AFTER DURING CONSTRUCTION

15 SURFACING OF OBEYEYIE–AFUAMAN–BORKORBORKOR F/RD CURRENT CONDITION BEFORE COMMENCEMENT

16 THANK YOU