US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 5, 2016
2
Outline US MICE Budget FY16-03-30 thru Cooling Demo remember US FY is 1oct – 30sept (6 mo from UK) 30sept2017 and that US DOE authorized funding ends 30sept2017 US MICE Budget Breakdown by Activity & FY R&D Risk Register Milestones DOESN’T FY16 4% Continuing Resolution restored! => 96% * $ 6 M = $ 5.76 M ($ 0.24 M less)Balance Sheet – show how this DOESN’T fit within the DOE Funding Profile of $ 9 M, $ 6* M, $ 3 M * FY16 4% Continuing Resolution restored! => 96% * $ 6 M = $ 5.76 M ($ 0.24 M less) plus $ 1.47 M carryover FY15 → FY16 (for ref $ 1.89 M carryover FY14 → FY15 → contingency) April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)2
3
US-DOE MICE Budget Profile through Cooling Demonstration April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)3 April 16 est indicates with & w/o repair of ds Spectrometer Solenoid also deferred RF Vacuum & RF Assembly from FY15 → FY16 Starting in FY2015 DOE requires MICE to include: MICE Construction, MTA Testing of RF Components, MICE Experiment Support, and Program Management + FY19
4
Ramp-down by Activity & FY April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)4 April 2016 estimates indicates with and without repair of ds Spectrometer Solenoid
5
RISK Additional RISKs associated with the repair of the downstream spectrometer solenoid after the recent failure have not yet been re-assessed However, the estimates for the repair of the DS SS magnet include the usual 30-40% construction contingency probability weighted Risk remains ~ $ 700 K which IS included in the funding needs April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)5
6
probability weighted R&D Risk Register April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)6 no changes since October 2015 Review – no additional risks retired keep same level of risk for Spectrometer Solenoid Magnet Repair this RISK is included in Resource Loaded Schedule estimate
7
Milestones 16-03-30 April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)7 Major US MICE Deliverables: updated (Oct2015) MICE Cooling Demo Magnetic Shielding Received in UK 18july2016 (16may) MICE RF Modules Arrive in UK: RF # 1: 16aug2016 ( 9may) RF # 2: 14sept2016 ( 7june) not on critical path so decided not to use contingency to maintain schedule
8
US MICE Critical Procurements PRY for Cooling Demonstration April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)8 see RF Modules on next page from: US MICE Cooling Demonstration Procurements.xlsx
9
US MICE Critical Procurements RF Modules – RF#1 & RF#2 April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)9
10
US MICE Critical Procurements DS Spectrometer Solenoid Repair April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)10
11
Balance Sheet April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)11 includes estimate for repair of ds Spectrometer Solenoid
12
The End April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)12
13
Backup Materials $ available for Magnet Repair vs. MICE Exp. Support assuming no additional funding remaining est for Magnet incl wgt RISK = $ 2,365 K April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)13
14
MICE Est & Cash Flow by US FY April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)14 Includes $ 1470 K carryover FY15 → FY16
15
MICE Est & Cash Flow by US FY April 5, 2016 Peter H. Garbincius | MICE Review (RAL, April 5-6, 2016)15 Mag Int Risk will be delayed until repaired ds Spectrometer Solenoid Magnet is available