Automation of the Lock Acquisition of the 3 km Arm Virgo Interferometer F. Carbognani for The Virgo Collaboration ICALEPCS - Geneva 14 October, 2005
2
2 Outline Virgo Experiment Control and Monitoring Automation Layer Real-Time and Fast Automation Layer Lock Acquisition Procedure Automation Performances Conclusions
3
3 Virgo Experiment Aim: Detection of the gravitational waves emitted by astrophysical sources Consists of a power recycled Michelson interferometer with 3 km long Fabry-Perot cavities in its arms
4
4 Working Point The mirrors must be aligned with a precision of a fraction of a micro-radian The relative distance of the suspended optics must be controlled within a pico- meter Working point maintained by using several digital feedback loops working at 10 kHz.
5
5 Automation Two automation layers: –A control and monitoring automation layer that uses a script-like language to monitor the needed DAQ channels and to control the first automation layer. –A real-time and fast automation layer implemented into the sub-system servers involved in the different loops.
6
6 Real-time and fast automation layer Control and monitoring automation layer Automation Layers Global and Local Control Loops Data Acquisition (DAQ) Automation sequence Data Commands Data
7
7 AlpAli AlpDet AlpSa AlpRecycled (master) Sub-systems servers Action DAQ Data Display –Use the data acquired by the DAQ to compute the state of any subsystem by processing the collected channels related to it. –According to the subsystem state, actions can be performed using the system calls or directly with messages in Cm format. Automation of Locking Procedure (ALP)
8
8 ALP Macros Set of code related to the same automation phase and a script language to define the macro’s content. Macro functionalities: ALP variables declaration, new DAQ channels can be created by performing arithmetic operation (+,-,*,/) between input channels, DAQ channel’s properties can be computed in the time domain (mean,min,max,rms,range) or in frequency domain (FFT, bandRMS …) and stored into ALP variables, Arithmetic operations (+,-,*,/) between ALP variables, test and loop conditions on ALP variables, commands can be sent to act on given sub-system servers, direct call of a macro
9
9 Alignment and Longitudinal Controls ITF Control Photodiode Signals Mirror Corrections Locking Frequency: 10 kHz Alignment Frequency: 500 Hz Global Control Processes signals coming from the photodiodes and sends control signals to suspensions DSP. ALP drives: switch between algorithms (Sensing, Filtering or Driving) “on-the-fly” parameters changes Gc state transitions
10
10 Mirror Local Control Longitudinal swing reduced to tenths of m/s by Inertial Damping. Tidal effects compensated by acting to the top stage, Tidal control. Angular mirror displacements reduced to fraction of mrad by Local Controls Alp drives: switching off the inertial damping loops swapping from local controls to angular drift controls switching the coil drivers to low noise mode Local Controls
11
11 The Injection System First Stage of Frequency Stabilization and Automatic Beam Positioner (ABP) control loop started by ALP at init time Second Stage (SSFS): one ITF error signal as frequency reference engaged (and disengaged when needed) by the Global Control. In case of problems ALP can disengage the loop within few seconds delay
12
12 Suspension Control Crate
13
13 DAQ Automation Layers (Detailed) Locking and Alignment Servo-Loops Local Servo-loops Mirror controls and Injection Photodiodes Readout Global Control Calibration Timing System Alp Automation Frame Building Low latency Frame Buiding Last stage Data Archiving Data Processing
14
14 Locking Procedure The goal of a lock acquisition procedure is to bring the ITF on its working point, by controlling its independent longitudinal lengths MICH = l n -l w PRCL= l rec +(l N + l w )/2 CARM= L N +L W DARM= L N -L W 4 lengths to be controlled: LWLW LNLN l rec lNlN lwlw By using a carrier beam phase modulated at 6 MHz and the Pound- Drever-Hall technique all the four lengths can be reconstructed by mixing the signals coming from photodiodes placed at different output ports of the interferometer.
15
15 Locking Procedure –For the ITF locking a novel strategy, called Variable Finesse Locking has been adopted –Basic Idea: the ITF is locked on the half (gray) fringe, then brought sequentially to the dark fringe through several steps. During those steps the control scheme is changed. –The lock acquisition procedure embeds this strategy and consists in two main sequences: Pre-alignment Sequence Locking Sequence
16
16 Pre-alignment sequence –This sequence, not always executed at each lock acquisition attempt, is implemented by the following three macros: –“Direct_Beam_Alignment”: Alignment of the direct beam into the North and the West arms. –“Cavities_Alignment”: North and West arm cavities independent locking, their non-linear alignment (when really needed) and their linear alignment. –“PR_Coarse_Alignment”: Non-linear alignment of the PR mirror, with respect to the arm cavities mirror alignment performed in the previous macro.
17
17 Locking sequence Implemented by a single macro, called “Lock_Step_request”. STEP 1 : Lock acquired with the PR mirror misaligned by 10 mrads and the ITF on the grey fringe (i.e. Dark Fringe at 50%) STEP 2 : A boost filter added to the PRCL and MICH loops. Dark Fringe from 50 to 40%. STEP 3 : CARM loop controlled by the SSFS. STEP 4 : PR mirror aligned and consequently the power stored in the ITF increases STEP 5 : Dark Fringe from 40 to 20%. A boost filter added to DARM loop. STEP 6 : Dark Fringe from 20 to 8%. STEP 7 : Dark Fringe from 8 to 5%. STEP 8 : Final step to Dark Fringe. Transition of the MICH loop error signal from the B1p DC signal to the B5 demodulated. Angular drift control switched on.
18
18 Locking sequence STEP 9 : Transition of DARM loop error signal from the noisy B8 to the less noisy B1p demodulated. STEP 10 : Output Mode Cleaner (OMC) put on resonance, transition of DARM loop error signal from B1p to B1. After the transition all the noisy mirror motion dampers are switched off. STEP 11 : A filter having a reduced band and a high roll-off is added the MICH loop. STEP 12 : Activation of the tidal control, swapping to low-noise coil drivers. STEP 13 : Re-adjustment of demodulation phase and gain of PRCL loop. STEP 14 : A fraction of the MICH correction signal is sent in counter-phase to the end mirrors. STEP 15 : Permanent lines are added to the different mirror corrections for ITF calibration.
19
19 Automation Client
20
20 Performances Lock Acq procedure fully automated 5 mins Lock to DF variable finesse OMC lock Low noise SSFS
21
21 Performances Commissioning run C6:Jul 29 – Aug 13, 2005 Step1 to Step15 duration distribution Percentage of time spent on the Step1 – Step 15 sequence: 5.29% Duty cycles:Locking : 89% Science mode (locked and stable ITF) : 86%
22
22 Conclusions –The automation has allowed to define a reproducible lock acquisition sequence, thus to stabilize the commissioning environment –Automation has showed all his effectiveness in supporting the ITF operations during commissioning and run periods –The Virgo machine is being provided with a tool allowing the operator to easily, reliably and quickly drive the machine into the working state. –The planned future improvements are: Adding more controls and checks inside macros Monitoring of all Servers status and check of correct handling of the requested commands. Automated subsystem failure recovering plus automated re-locking. Performance optimisation on critical servers currently generating latency peaks.