August 22, 2004 1830 hrs. SEOC LEVEL 1 Activation.

Similar presentations


Presentation on theme: "August 22, 2004 1830 hrs. SEOC LEVEL 1 Activation."— Presentation transcript:

1 August 22, 2004 1830 hrs

2 SEOC LEVEL 1 Activation

3 SEOC OPERATIONAL HOURS 0700 – 1900 All ESFs 0000 – 2400 Operations & Planning

4 Up next – FEMA SERT CHIEF Mike DeLorenzo

5 FEMA Up next – Meteorology

6 Current Operations – Unmet Needs – Future Operations – FEMA

7 METEOROLOGY

8 24 Hour Qualitative Precipitation Forecast

9 Florida Radar – 6:00 PM EDT

10 Recovery Forecast Monday: Scattered showers and thunderstorms likely, mainly after 2 PM Partly cloudy, with a high around 90 Heat indices as high as 100 Chance of rain 60 percent Tonight: Scattered showers and thunderstorms likely, mainly before 8pm Chance of rain 60 percent Low near 74 West wind at 6 mph becoming south-southeast

11 Current Satellite - Tropical Atlantic Tropical Storm Formation Not Expected Through Monday Up next – Operations Chief

12 Up next – Emergency Services OPERATIONS CHIEF

13 EMERGENCY SERVICES

14 Current Operations – –Working on 7 temp. facilities for fire stations –No change in death count @ 25 –Port-o-lets! Unmet Needs – –Mosquito spraying- needed –Lack of staff for medical needs still an issue Future Operations – –Demob: USAR, Strike teams etc. ~75% by Tues –LE opening new command post in Hardee Co –Preparing for transition to forward SERT Emergency Services Up next – Human Services

15 HUMAN SERVICES

16 Current Operations – –Continue to support established DRCs –Continue efforts to meet intermediate and long-term housing needs –Continue to secure housing for displaced population –Continue to support Comfort and Feeding Stations as required –Continue shelter operations as necessary –Contribute distribution of food, water and ice Unmet Needs – –None at this time Future Operations – –Continue efforts to meet intermediate and long term housing needs –Continue to establish new DRCs, Comfort and Feeding stations as necessary Human Services Up next – Infrastructure

17 INFRASTRUCTURE

18 Infrastructure Current Operations – –84,078 customers without electric service –Continue fuel support for impacted county operations (diesel, gasoline and LP) –Continue support of roadway debris clearance & traffic control system repairs –20,100 wire line POTs customers are out of service –98% wireless customers have service in Southwest Florida –Coordinating radio, satellite, cell, POTs and internet connectivity telecom requests Unmet Needs – –Monitoring fuel delivery resources Future Operations – –Continue to support fuel and telecom requests –Continue to monitor and support transportation, electrical, telecom, potable and waste water system restoration –Transition to recovery operations (e.g., debris removal, permanent repairs, etc.) Up next – Military Support

19 ESF 13 – MILITARY SUPPORT

20 Military Support Current Operations – –Strength: 3170 –Security missions continue (798) –Continue to support LSA 1 & 2 –Rotary wing aircraft continue to support recon and damage assessment Unmet needs – –None at this time Future Operations – –Support law enforcement with security forces and traffic control –Provide logistical support and humanitarian support –Right sizing our forces Up next – Logistics

21 LOGISTICS Up next – Finance & Administration

22 Logistics Current Operations – Unmet needs – Future Operations – Up next – Finance & Administration

23 FINANCE & ADMINISTRATION

24 Finance & Administration Current Operations – –Various PO's - equipment & security Unmet Needs – –None at this time Future Operations – –Assist with purchasing & deployment –Continue to document costs Up next – Public Information

25 ESF 14 – PUBLIC INFORMATION Up next – Recovery

26 RECOVERY

27 Recovery Current Operations – –We have Completed Damage Assessments for 34 counties –We have completed two applicant briefings –There are 16 applicant briefings scheduled for next week –16 Teams of Public Assistance Coordinators are ready to go to the impacted counties on Monday, 8/23/04 Unmet needs – –Staffing Future Operations – –Compiling the Damage Project Work Sheets Up next – SERT Chief

28 SERT CHIEF Mike DeLorenzo

29 Don’t forget to turn your phone’s ringer back on! Thanks for your cooperation

30 August 23 at 0730 Branch Chiefs NEXT BRIEFING