Presentation is loading. Please wait.

Presentation is loading. Please wait.

FUSE TEMPUS Project Coordination Meeting Belgrade University, 27 and 28 November, 2014 INTERMEDIATE REPORT (IR) PREPARATION (+ Statement of the Costs Incurred.

Similar presentations


Presentation on theme: "FUSE TEMPUS Project Coordination Meeting Belgrade University, 27 and 28 November, 2014 INTERMEDIATE REPORT (IR) PREPARATION (+ Statement of the Costs Incurred."— Presentation transcript:

1 FUSE TEMPUS Project Coordination Meeting Belgrade University, 27 and 28 November, 2014 INTERMEDIATE REPORT (IR) PREPARATION (+ Statement of the Costs Incurred and Request for Payment)

2 2 reports – INTERMEDIATE and Final (contractual obligation towards the EACEA)  INTERMEDIATE REPORT: progress in relation to planned activities for the first half of the project period  Final Report  Part I: Progress during the second half of the project  Part II: Overall impact of the project during its lifetime

3 THE AIMS OF SUBMITTING THE IR  to communicate to the EACEA the project’s ACHIEVEMENTS / RESULTS AND OVERALL PROGRESS in relation to planned activities for the first half of the project period (in the case of SM – e.g. how exactly institutional management / services / procedures in the area covered by the project have been restructured)  to help beneficiaries review (self-evaluate) their achievements on the project  to ensure that the project is complying with the funding requirements  to communicate to the EACEA areas where the project might need support and what changes in the workplan, in the consortium etc. have taken place  to ask for the 2nd installment (if preconditions are met)

4 THE STRUCTURE OF IR  technical  financial THE DEADLINES FOR SUBMITTING IT AN OUTLINE OF THE DUTIES OF ALL THE PARTNERS IN THE PROJECT IN THE PREPARATION OF THE IR On the basis of the TEMPLATE - also available on http://www.fuse.ni.ac.rs/documents/viewcategory/4-key- documents-visual-technical-templates http://www.fuse.ni.ac.rs/documents/viewcategory/4-key- documents-visual-technical-templates (Annex IV Interim Report – Template)

5

6 What Makes for a Good Report?  All questions in each section - answered comprehensively  Shows how feedback of assessors of your proposal and those field- monitoring the project have been addressed  Clear evidence of the project’s results and impact - given  Precise information in the 'Table of Planned/Achieved Outcomes'  A frank honest account of the project’s obstacles are given, the methods used to overcome them and the outcome  Concrete information is provided (answering "when", "where", "what", "how" and "how many")  Not too long....and not too short  All beneficiaries should contribute information to the report (but it should be edited so that the writing style is coherent throughout)  All beneficiaries should approve the report before it's submitted

7 What Makes for a ‘Not So Good’ Report?  It’s difficult to understand from the report what’s actually happening on the project (missing information, illogical sequences).  The table of achieved outcomes is in the future tense – copied and pasted from the proposal (dates are not updated).  The report is a copy-paste versin of an internal report or a report to another donor – and doesn’t answer the questions asked.  It’s not clear from the report which partner has been responsible for what.  It’s written in different styles and incoherent. (If parts haven't been filled in (n/a at least), the report will be rejected)

8 General advice for Preparing the IR  the time and the human resources needed for the reporting activities – not to be underestimated; (staff assigned to do the job on IR preparation + the decision who exactly writes what + the coordinator informed about that – by 1 March 2015)  the Work Plan – to be kept updated (i.e. changes noted) and the report to be written on the basis of the plan;  the Table of Achieved Outcomes – to be filled in as soon as an activity gets completed;  supporting documents to be collected, scanned, uploaded onto the MNGT platform as soon as an activity has taken place  Insert links, attach PDF files, if possible and applicable

9 Modifications during Project Implementation  Informal changes: Simple changes in activities from what was planned in the project proposal  require prior written authorization from the Agency  duly justified in relation to the project objectives and requested sufficiently in advance,  the budgetary implications of these changes – to be clarified,  a revised work plan – to be presented;  can only be implemented after prior written approval of the EACEA  Formal changes: those impacting the contents of Grant Agreement (change of bank accounts, legal representatives, contact persons, amendments to the budget – e.g. increasing a budget line by more than 10%, etc.)

10 How Reports are Assessed  by the EACEA Project Officer responsible for the project  checks if all the questions asked in each section have been answered and the quality of each answer.  Compares the 'Table of Planned / Achieved Outcomes' with what was planned in project proposal.

11  The reports can be either accepted or rejected  If rejected: Need to submit a new version  Rejection can also be linked to the non-compliance with the reporting requirements, not to the implementation of the project itself.


Download ppt "FUSE TEMPUS Project Coordination Meeting Belgrade University, 27 and 28 November, 2014 INTERMEDIATE REPORT (IR) PREPARATION (+ Statement of the Costs Incurred."

Similar presentations


Ads by Google