Download presentation
Presentation is loading. Please wait.
Published byDarrell Snow Modified over 8 years ago
1
LWU Design Overview Paul Aden
2
BTM WP Scope To design, procurement and assemble; –2 Prototypes –3 Test Chambers –75 Linac Warm Units –52 Beam pipe modules –2 Differential pumping systems –4 mobile installation cleanrooms Total Cost £10.5m Approximately 30 FTEs 2016-2019
3
BTM WP Scope To design, procurement and assemble; –2 Prototypes –3 Test Chambers –75 Linac Warm Units –52 Beam pipe modules –2 Differential pumping systems –4 mobile installation cleanrooms Total Cost £10.5m Approximately 30 FTEs 2016-2019
4
Overview End of Hall before Target Source Warm Linac Spoke Linac Medium Beta High Beta Upgrade Region Dogleg / Dumpline 500m
5
Overview End of Hall before Target Source Warm Linac Spoke Linac Medium Beta High Beta Upgrade Region Dogleg / Dumpline 500m
6
Overview LWUs LWUs & Beam Pipe EVERYTHING Just the red bits LWUs LWUs & Beam Pipe Differential Pumping System Beam Pipe
7
Covered in this CDR LWUs Beam Pipes HEDP LEDP Not including, – Dump – Dogleg – A2T area
8
Overview LWUs LWUs & Beam Pipe CDR 2 CDR 1 LWUs LWUs & Beam Pipe Differential Pumping System Beam Pipe
9
3 rd Party Input Final magnet designs –Quads 19 th February 16 –Correctors 22 nd March 16 Final BPM designs supplied –26 th January 16 BCM Design Decision made –16 th February 16 Final Specifications agreed –24 th March 16 Most recent delivery schedule –3st March 16
10
Value Engineering Reduction of complicated parts Reduction of similar duplicated components Combining multiple chamber types to allow less chamber designs Standardising components wherever possible
11
Module Overview Aluminium slotted girder BPM on entrance or exit Semi–kinematic girder adjustment Pedestal s Quadrupole Magnets Fiducials, laser tracker alignment -50µm Accuracy Built in lifting points ‘Particle Free’ Chamber - ISO 5 or better
12
Design Sheet Chess Document – ESS-0044812
13
Design Sheet
14
Girder Design
15
Girder
16
Adjustment Fixed Length for all LWUs Slotted Girder allows for ‘unlimited’ ‘coarse’ on z Adjustment.
17
Space is tight - Elliptical 10mm 8mm 12mm
18
Adjustment Fixed Length for all LWUs Slotted Girder allows for ‘unlimited’ ‘coarse’ on z Adjustment. Mounting adjustment allows for ±15mm fine adjustment Kinematic mounts allow for vertical adjustment ±25mm on a fine M24 nut. ±50mm Girder Adjustment At the request of ESS Survey and alignment group horizontal girder adjustment is above vertical adjustment
19
Adjustment Slider Plate, Girder directly mounted to these steel plates
20
Semi Kinematic Adjustment Lifting Points Cone Adjusting Screw Vee Adjusting Screw Flat Adjusting Screw Horizontal Movement Clamps Girder Y,Z Plate
21
Y & Z Adjustment Adjusting Screws
22
Vertical Adjustment Vertical Adjustment on Semi-Kinematic mounts ± 50mm
23
Simplified Model
24
General Details ItemMass Girder110Kg Chamber, Max80Kg Girder, Chamber & Mounts215Kg Pedestal Assembly170Kg Complete LWU (assumes Q7 550Kg) 1700kg
25
Mesh Coarse Mesh Min size 3.8mm Max size 19mm
26
Setup
27
Static Structural
28
Stress
30
Static Results Girder Deflection –0.01mm Maximum Magnet Deflection –0.07mm Maximum local stress on mounting points –20MPa
31
Pedestal Positions Due to low deflection and requirement for Egress airy points have not been used. Pedestals have been placed directly under the main load, in the case the magnets.
32
Semi Kinematic Mounts ‘V’ ConeFlat M42 Tie Downs
33
Semi Kinematic Mounts ‘V’ Aligned with Cone ‘V’ Would need altering to change pedestal spacing
34
Egress 700mm x 880mm
35
Modal
36
450 mm 710mm Steel Box Section- hollow to allow for damping sand if needed Mount for central support and wheels Pedestals
37
Girder Lifting Mount Setup:
38
Girder Lifting Mount Lifting Pin inserted through the hole Pin contact area in lifting mount 30mm Diameter Steel Lifting Pin 2000N per mount
39
Girder Lifting Mount
41
Lifting Point Positions Adjustable to CoG
42
Adjustable Lifting Frame
43
Wheels
44
Installation Supports Fixes pedestals together to easy removal and replacement of girder whilst pedestals are not fixed to the floor
45
Design Based on many years experience developing accelerator modules Slotted girders allows for versatility Optimised for ground vibrations Fiducial mounts for survey and alignment –±100µm alignment to local girder network Girder adjustment ± 50mm Magnet/Chamber adjustment ± 25mm, ± 5mm due to other items Large space between pedestals for access/egress
46
Optimised for space Space for diagnostics
47
Thermal Knock on effects; –Re design of LWUs including heat transfer Approximately 6-9 months Approximate additional cost XXX Resources are now limited to do this work –Re Design of LWUs excluding heat transfer (i.e. pipe diameter changes) Approximately 2 months Approximate additional cost XXX
48
Survey & Alignment 4 x 6H7 Fiducial Mounting points at each corner of the girder. 4 x 6H7 Fiducial mounting points at each corner of the pedestal.
49
Adjustment Individual item adjustment on three point kinematic mounts
50
Adjuster & Supports
51
Magnet Adjusters Q5 Magnet spacer
52
Chamber Adjusters
54
Scintillator Mounts
56
Chambers
57
All Welded
58
Chamber Designs
59
Bellows Life cycle Specs etc.
60
Bellows Travel Required ±40mm Securing bolts do not pass flanges Not designed for Vibration
61
Custom Flange Clamping hole to prevent bellows moving through rotatable flange when the retracting the bellows
62
Bolt Extraction Bolt Extraction Direction Slotted CF Flange
63
VAT Seal Wire scanner diagnostics flange Square flange is the standard VAT flange used on series 35 gate valves We did investigate square CF flanges but there in frequent use and complicated design made it difficult to justify
64
VAT Seal
65
Material Selection Tube & main chamber body; 316L Tube to be weld less. Tubes 3.2m, Magnetic permeability less than 1.005 after vacuum firing Flanges 316LN Bellows 316L
66
Pipe Diameters Spoke Section –ID 57.14 mm –OD 63.5 mm –Seamless 316L Elliptical –ID 100 mm –OD 108 mm
67
Chamber Stress
68
Chamber Deflection
69
Vacuum Analysis Checked worse case scenario for LWUS
70
Summary Looked at many conceptual designs
71
Summary Looked at many conceptual designs Made modifications based upon prototype build
72
Design Based on many years experience developing accelerator modules Slotted girders allows for versatility Optimised modal response Fiducial mounts for survey and alignment –±50µm alignment to local girder network Girder adjustment ± 25mm Magnet/Chamber adjustment ± 25mm, ± 5mm due to other items Large space between pedestals for access/egress
73
BPM Test Rig
75
BPM Cassette XZ Stage Wire Clamp (Fixed) Wire Clamp (Spring Tensioned) Home Switches Stages – Dover Motion XYR 100 x 100 Travel
76
Access for cable connection Clamps Face Location Survey Targets 5 BPM’s loaded and surveyed relative to the fixture. BPM Cassette
77
Home switches (Baumer MyCom E) actuated by the wire location body. Relationship between homed position and BPM physical centre determined by CMM optical survey then offsets calculated. Home Switch
78
Transport Method 78 Open plywood box with corner supports Plywood bottom with timber base for reinforcement Anti-Vibration Springs between module and box base 1 2 3 Lifting Points required on 3. Plywood lid Module Airide trailer for low road vibration transmission Springs between girder and box base for shock loads Quantity will depend on girder length & weight Spring dampers
79
Design tasks still to be carried out Finalise vessel drawings for: –Spoke X –Elliptical X Complete modal analysis for inclusion of sand Complete drawing package for BPM test Rig Complete specification for mobile cleanroom design Crate and transportation detailed design work
80
Design Progress
81
Thank You
82
Main Item List Main Chamber Bellows Assembly BPM Integration Particulate cleaning System Support Girder Pedestal frame Kinematic mounting for girder - type 1 Kinematic mounting for girder - type 2 Kinematic lock nut Washer Bolts Nuts Floor Plate Beam Adjustment Kinematic Adjuster - type 1 Kinematic Adjuster - type 2 M24 Fine Pitch Notch Nut Beam Support Plate Adjusting Plate Adjuster Block Clamp Washer Mount Cone Mount Vee Mount Flat Clamping Nuts Clamping Washers Vacuum measurement and Control Penning Gauge / IMG Thermo Couple / Pirani Gauge Penning Gauge controller / IMG Penning Gauge Cable TC / Pirani Gauge control TC / Pirani Gauge Cable Pumping Systems Ion Pump - 75l/s + Controller Pump Controller Pump Cables Valves VAT S54 Right Angled valves DN40 DN10 Venting valve - debate Soft Start Pumping/Vent Flanges, Connections & fittings Various Blanks Various Gaskets Misc Electrical Termination Mounts Electrical Tray Work Fasteners nuts & bolts
83
Additional Item List Misc Cleaning a consumables Vacuum testing consumables Shipping and Transport Costs Shipping Crates Shipping Packing/Mounts Shock Watch Transportation Crate Identification Test Equipment Vacuum Pumps Vacuum Gauges Test racks Pump Controllers Gauge Controllers
84
Diagnostics Chamber Steering Magnets Focusing Magnets LWUs
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.