1 NSW SG 10 Dec 2014 10 Nov 2014 S. Zimmermann, NSW SG 1

2 NSW Milestones LHCC has requested a document with NSW milestones, in particular for 2015, to be able to assess if project remains on track. Will next be checked in autumn 2015. Already got quite a bit if “heat” from ATLAS Upgrade coordination on seemingly slipped schedule compared to the TDR, and admonishment this must not happen again and again … 10 Nov 2014 S. Zimmermann, NSW SG 2

3 Milestones and Schedule: TDR NSW TDR (spring 2013): 10 Nov 2014 S. Zimmermann, NSW SG 3

4 Milestones and Schedule: TDR 10 Nov 2014 S. Zimmermann, NSW SG 4 NSW TDR (spring 2013): Since the TDR the LS2 shutdown was moved by 6 months to start mid 2018 …

5 Schedule: LHCC 11/2014 10 Nov 2014 S. Zimmermann, NSW SG 5 Schedule (LHCC Upgrade Cost Group, Feb 2014) Similar/same for MicroMegas Production Site setup – until end 2014: on track Module -1 production: 1 st half 2014: completed Test beam (module -1): done Design Review for sTGC/MM detector construction: passed successfully in July  green light for module-0 Module 0 construction: autumn 2014: component procurement/ production ongoing, quadruplets to be completed in spring Qualification in GIF++: moved by ~3 months to spring 2015 Start of mass production: Mid 2015, unchanged sTGC schedule Reviews/ Milestones

6 Milestones 2015 Proposal: Detectors 10 Nov 2014 S. Zimmermann, NSW SG 6 MilestoneDate Decision on MM screen printing15/3/2015 ? Final Drawings for MM readout and drift PCBs15/2/2015 ?Fixed interconnect positions. MM Readout PCBs: Tender2/2015 MicroMegas Module-0 completion (incl. validation) + FDR 6/2015 MicroMegas PRR: Start of series production8/2015Includes production site review. Put milestone? MM Mass Production (LM2, SM1, SM2): 20% complete 31/12/2015Number ? MM Mass Production (LM1): 10% complete31/12/2015Number ? sTGC Cathode Boards: Tender1/2015 sTGC Module-0 completion (incl. validation) + FDR5/2015 sTGC PRR: Start of series production6/2015Includes production site review. Put milestone? sTGC Mass Production (Small Sector Modules + Large Sector Inner): 20% completed 31/12/2015 Assemble sTGC module-0 into Small Sector Wedge8/2015Really include ? MM spacer frame design and prototype, assemble MM module-0 8/2015Really include ?

7 Milestones 2015 Proposal: Alignment 10 Nov 2014 S. Zimmermann, NSW SG 7 MilestoneDate Alignment System PDR and Bar FDR/PRR3/2015

8 Milestones 2015 Proposal: Eltx 10 Nov 2014 S. Zimmermann, NSW SG 8 MilestoneDate NSW ASIC Specs + Specs Review (VMM, ROC, ART)2/2015TDS already had a PDR. Date fixed VMM3, TDS2, ART2, ROC1 Submission, after PDR7/2015 VMM3, TDS2, ART2, ROC1 Tests completed31/12/2015 VMM3A, TDS-Prod, ART-Prod Design Completed. FDR. 2/2016What about ROC ? VMM3A, TDS-Prod, ART-Prod, ROC-Prod Submission Q2/2016 ADDC, L1DDC, FEB, Trigger Processor, pad logic PDR 2/2015Date fixed. MMFE Demonstrator4/2015 MMFE Demonstrator series for construction sites6/2015 ADDC prototype 211/2015Prototype 1 now, results for PDR L1DDC prototype 29/2015Prototype 1 now, results for PDR sTGC FEB Demonstrator10/2015 Trigger Processors ?

9 Milestones 2015 Proposal: Mechanics 10 Nov 2014 S. Zimmermann, NSW SG 9 MilestoneDate JD, Hub and Plug – FDR7/2015 Structure – FDR10/2015 JD, Hub, Plug -- Tender9/2015 Structure -- Tender12/2015 Clear/Consolidate CERN Integration Facilities – BB5, 180, … 5/2015