SCSPF CLEANROOM UPDATE Flood Recovery Plan and Status April 30, 2012 Allan Rowe
2
What Happened? At 07:45 a.m. on April 24 th, during a routine crane inspection, a sprinkler head from the B101 High Bay primary fire suppression system was set off by the overhead crane when electrical conduit attached to the crane made contact. An interference has always been present (and known), so this was an accident waiting to happen. An official incident report will be completed by ANL.
3
Who was present? A FNAL cleanroom technician was performing a 1-cell 1.3 GHz assembly when he noticed water was falling from the ceilings of the cleanroom. The crane inspector alerted the cleanroom technician of the problem through the window of the cleanroom.
4
Photos Damaged Sprinkler Head
5
Photos
7
HEPA Damage
8
Photos HEPA Damage
9
Photos Debris in Class 10 CRs
10
Plan Remove all portable hardware, tooling, parts, etc. and transport to IB4 CR area. Clean and prep all components in IB4 and package for return shipment. Verify function of all electronic and mechanical hardware. This will be ongoing for several months for components that got wet. Setup cost center at ANL (FMS) to cover losses.
11
Plan cont. Contract with Midwest Cleanroom Associates to replace complete CR ceiling, verify electrical integrity, etc. Clean high-bay area Clean cleanrooms Transport all CR stuff back to ANL. Re-commission all services
12
List of Equipment that Received Water Damage from 04/24/12 Sprinkler/Crane Incident MAKE/MODELFERMILAB IDSTATUS Climet Particle Monitor CI-750t106932 S&K Torque Wrench - inch lbs. Rusted - needs to be replaced S&K Torque Wrench - foot lbs. Rusted - needs to be replaced Simco Top Gun Ionizing Air Gun - Class 10 area Seems to be fully functional Simco Top Gun Ionizing Air Gun - Anteroom Seems to be fully functional Exit Sign - Class 10 area Millipore A10 TOC Monitor Seems to be fully functional HPR Remote Control Box (Rexroth) - Anteroom HPR has been run for a few minutes and is fully functional HPR Main Control Box/Panel (black box) - Outside of cleanroom HPR has been run for a few minutes and is fully functional Kenwood 2-way RadioR5116Seems to be fully functional Kenwood 2-way RadioR5117Seems to be fully functional Agilent U1733C LCR meter Fluke Multimeter 77 IV HP Deskjet 6940 Printer Lewis Ultrasonics Large US tank Control Panel Panel has been opened, no water damage is apparent B101 Cleanroom Control Panel - HEPA filter and Temperature Performance Panel Panel has been opened, no water damage is apparent B101 Manuals Ink has run, unreadable - need to be re-rpinted Fermilab Vacuum Logbook Need to replace logbook Inficon Transpector 2 RGA Seems to be fully functional Varian Turbo & Controller Seems to be fully functional MKS Vacuum Guages (x2) Seems to be fully functional Manual Valve Control Box Seems to be fully functional Anest Iwata Scroll Meister Rough Pump Seems to be fully functional Vacuum Cart Electrical Strip Seems to be fully functional IBM Thinkpad Lenova T61109674 Need to transfer hard drive info, computer otherwise dead ANL SPECIFIC EQUIPMENT ANL Edwards TIC Pump Cart Everything works except for the pressure guage ANL Climet ANL Motorola FRS Radios (x2) ANL HPR Manual Control Box (outside cleanroom) Seems to be fully functional ANL hand HPR pump Seems to be fully functional ANL Exit Sign - Class 10 area Equipment Status List
13
Cleanroom Repair Schedule FMS Cost Center (for all recovery costs), though scope is not completely known Midwest CR has submitted proposal Overall schedule to be limited by CR ceiling replacement.