18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information, including Fabrice, Richard, Rende, Delphine, Ray, Klaus, Didier, Bettina, Jan, Pierre…. Wikipedia (Eng.): A problem is an obstacle which makes it difficult to achieve a desired goal, objective or purpose.
2
18/March/2008OP-days S.Mataguez / O.Hans2 LINAC 2Source During operation an increased number of flash over on the source, up to 60 in 24h (normal rate is 5/24h). The problem was identified to be grains of “black dust”, coming from the air conditioning system. The air conditioning conducts have an inner insulation layer (black), which went off. First aid was to install filter. During shutdown, vacuum cleaning of the air conditioning conducts and the filters will stay. Richard is optimistic, that we will not have the black dust problem in 2008. General remark for Linac2: Linac2 had an excellent run last year with 98.7% of beam availability.
3
18/March/2008OP-days S.Mataguez / O.Hans3 LINAC 2RFQ The RF tuner on the RFQ was blocked, which resulted in a reduced beam intensity. The problem was found on the piston, where the thread went off. During the technical stop tuners of the RFQ were replaced. During shutdown all tuners (on RFQ, buncher and tanks) were inspected and mechanically improved.
4
18/March/2008OP-days S.Mataguez / O.Hans4 LINAC 2RF amplifiers During the run, Linac2 had a water leak on a RF amplifier. Water hose needed to be exchanged, which means long down time. During shutdown all water hoses were exchanged.
5
18/March/2008OP-days S.Mataguez / O.Hans5 LINAC 2RF Tank 3 During operation 2006, vacuum problems on Linac2 RF tank 3 Repair in shutdown 2006/2007. A polymer skin was poured around the flange. No RF trips in 2007. Vacuum in 2007 was better than in previous years. This repair will stay until Linac4 comes. Reminder: For 2008 the Linac vacuum control system moved to PVSS.
6
18/March/2008OP-days S.Mataguez / O.Hans6 BOOSTERWire Scanner Booster has for each ring one vertical and one horizontal wire scanner. End of the run, 2 of the 8 wire scanner were broken. The situation for the start-up is: All scanners were maintained and calibrated. Vacuum valves were added to simplify their removal. Ring 1 equipped with new (LHC) electronic. But not operational for the start-up.
7
18/March/2008OP-days S.Mataguez / O.Hans7 Beam losses “ SFTPRO Normal Extraction” PSElectrostatic Septum SS31 Beam losses “ SFTPRO Bad Extraction”
8
18/March/2008OP-days S.Mataguez / O.Hans8 PSElectrostatic Septum SS31 Reason for brake-downs is a weak insulation of a new installed power supply cable (in picture red cable). Time to exchange the cable is approximate 3 hours (spare cable is stocked inside the PS). Including time to cool down. 19 th Aug.8 th Sep.29 th Sep.15 th Oct. History of failure:
9
18/March/2008OP-days S.Mataguez / O.Hans9 PSElectrostatic Septum SS31 On the outer tunnel side, septum connection side, a second resistor was added. This relieves mechanical stress on the cable. The old (black and better) cable will be used. What was done to solve the problem?
10
18/March/2008OP-days S.Mataguez / O.Hans10 PSInternal Dump SS48 The PS has two internal dumps, in SS47 and SS48. There very important for setting up of beams, like MTE. Renovated for start up in 2006. 2007 equipped with new control system. Better performance as in previous days. During last week of 2007 operation, a vacuum leak in SS48 was detected.
11
18/March/2008OP-days S.Mataguez / O.Hans11 PSInternal Dump SS48 PS has one spare dump. Spare dump was previously used in the PS and is “hot” (~7mSv/h at contact). During preparation of spare unit, a bearing broke. Difficult to repair. Spare unit is installed and operational. (the original dump SS48 has still the vacuum leak.) Conclusion: The PS has both internal dumps back. But no operational spare dump. We are lucky. We do not have to dump our beams like this Cast iron collimator block damaged by repeated P+/P- beam discharges.
12
18/March/2008OP-days S.Mataguez / O.Hans12 PSPole Face Windings For run 2007 PS changed from 3-current mode to 5-current mode. Several switching between old and new power supply. PFW had numerous down time due to PFW switching and resets. Serious impacts for operational beams (high ripple on EAST-spill) and beam set-ups (MTE). Very brief presented in this talk. Will be detailed presented by: On 26 th July the major problems were solved. 5-current mode is operational.
13
18/March/2008OP-days S.Mataguez / O.Hans13 Beam sharing for East Area 35% towards North Branch 65% towards South Branch PSEast Area MNP23 During operation in 2006 magnet MNP23 failed. The magnet was replaced in the shutdown 2006/2007 by a MCB magnet. BHZ01 Magnet MNP23 Splitter As a consequence the PS could not perform the shared beam operation. North and south branch needed dedicated cycles. Loss of cycle efficiency. Situation will not change for the 2008 run. 2009?
14
18/March/2008OP-days S.Mataguez / O.Hans14 During operation 2007, three major magnets faults in the AD ADMagnet faults QFC54, water leak Repaired during shutdown. Orbit jumps. Reason: DHZ2908, internal short circuit. After replacement, needed 10 days for bake-out. Fire alarm in the AD hall. Reason: BHZ12, ground fault. Cut out the “Y” chamber and installed in refurbished spare magnet.
15
18/March/2008OP-days S.Mataguez / O.Hans15 Three safety issues in 2007 ADSafety Access door ATRAP4, and ASACUSA. The doors were not safe. Piquet solved both problems. Beam stopper Vacuum valve, which operated as second beam stopper caused problems. Problem was a micro- switch. All micro-switches has been replaced. Beam stopper (ALPHA) Beam stopper had too low air pressure. First aid: Added springs. During shutdown new hose installed and 8bar pressure is assured
16
18/March/2008OP-days S.Mataguez / O.Hans16 CPSSummary SolvedNot solved Linac 2 Amplifier (Water leak) RFQ tuner (blocked) Source (flashes) Vacuum on RF tank 3 BoosterFast Wire Scanner PS Septum SS31 Dump SS48 EAST beam sharing (MNP23) AD Magnets (3 faults) Safety (3 faults)
17
18/March/2008OP-days S.Mataguez / O.Hans17 Hardware Problems in the PS complex End of talk Proverb about problems: “When you can't solve the problem, manage it.”