Presentation is loading. Please wait.

Presentation is loading. Please wait.

Interstate 5 / Empire Avenue Interchange Project B-G-P Airport Authority – April 4, 2011.

Similar presentations


Presentation on theme: "Interstate 5 / Empire Avenue Interchange Project B-G-P Airport Authority – April 4, 2011."— Presentation transcript:

1 Interstate 5 / Empire Avenue Interchange Project B-G-P Airport Authority – April 4, 2011

2 Project Overview

3

4 Project Components Empire Avenue Interchange

5 Project Components Buena Vista / San Fernando Railroad Grade Separation

6 Project Components Burbank Boulevard Interchange

7 Project Components Providencia Avenue OH Widening / Weaving Lanes

8 Project Components - Utilities

9 Empire Interchange Renderings Empire Avenue Looking East Valpreda Street to Victory Place Showing Possible Landscaping   San Fernando Blvd Aerial View Looking NW

10 Buena Vista / S.F. Rail Grade Sep. Current Plan No Landscaping Possible Plan City-paid landscaping

11 Project Sequencing 1 2 3 4 1.San Fernando Closure & Temp. Shoofly Track Begin Fwy Widening 2. Buena Vista / S.F. Rail Grade Sep. 3. Empire Interchange / Victory Place Bridge 4. Burbank Bridge End Fwy Widening

12 San Fernando Closure

13 Major Next Steps 1. Utility Agreements 2. Cooperative Agreements 3. Storm water Pump Station Design 4. Metrolink Maintenance Agreement 5. Detailed Detour Planning / Staging 6. Right of Way Transfers 7. City Utility Construction

14 Tentative Project Milestones 1. City Starts Utility Construction Spring 2011 2.Caltrans Starts Construction Early 2012 3.Caltrans Completes Construction 2015

15 Questions and Information 1. City’s “E-notify” email list www.burbankusa.com 2.Caltrans Info Line (855) 454-6335 3.Caltrans Project website www.I-5info.com (Live May 2011)

16 Authority Board Questions


Download ppt "Interstate 5 / Empire Avenue Interchange Project B-G-P Airport Authority – April 4, 2011."

Similar presentations


Ads by Google