Presentation is loading. Please wait.

Presentation is loading. Please wait.

WP : High-Beta Cavity Delivery

Similar presentations


Presentation on theme: "WP : High-Beta Cavity Delivery"— Presentation transcript:

1 WP 11.5.3: High-Beta Cavity Delivery
A Wheelhouse ASTeC, STFC Daresbury Laboratory ESS SRF Elliptical Cavities Collaborations Meeting INFN Milan 20th May 2016

2 Outline Delivery Schedule Infrastructure Quality Assurance Summary
Scope Delivery Plan Risk Register Infrastructure Cleanroom Shielding Cryogenic Plant Cryogenic System RF System Quality Assurance Summary

3 Outline Delivery Schedule Infrastructure Quality Assurance Summary
Scope Delivery Plan Risk Register Infrastructure Cleanroom Shielding Cryogenic Plant Cryogenic System RF System Quality Assurance Summary

4 Scope Niobium procurement: STFC to procure the high RRR Niobium for the high-β elliptical dressed cavities in agreement with the SRF collaboration for the ESS linac. Cavity fabrication of the 84+4 spare high-β elliptical dressed cavity in industry including: Cavity fabrication. Chemical processing. Heat treatment. Vacuum processing. Procedure Qualification and Training: A qualified test procedure to be developed and implemented. A QA/QC system for individual tests in accordance with ESS policies. Trial tests to be performed and performance targets verified. Staff training in procedures and processes. High pressure rinsing. Field flatness and frequency tuning. Assembly of RF antenna and isolation valve in cleanroom. Shipment of dressed cavities to STFC.

5 Scope (Cont) Vertical Test (VT) of SRF cavities:
VT stand to be qualified to meet ESS cavity requirements including new cryogenic and RF system, along with a suitable controls system. A QA/QC system for individual tests in accordance with ESS policies. Testing of the high-β dressed cavities to 22.9 MV/m at 704 MHz, with a Qo better than 5 x 109. Documented test results provided to ESS. Preparation and shipping of cavities to cryomodule integration site: STFC to design and procure shipping fixtures for SRF dressed cavities for transport from industry. STFC to transport SRF cavities from STFC to the cryomodule integration site. STFC to support transport cost in accordance with ESS transportation policy.

6 Project Delivery Majority of the infrastructures is on order
Procedure & Staff Development Cavity Fabrication and Testing Majority of the infrastructures is on order Processes are being mapped out Training plans have been defined Specification for Niobium material is being drafted

7 Project Schedule & Key Milestones
Description Date CAS Stage 1 4 Design and procurement of the VTF including RF system, control system, cryogenic system, cryostat, cavity handling tooling. 9/9/2016 5% 5 Installation and commissioning of the full VTF system with suitable prototype/pre-production cavities. 7/7/2017 8 Critical Design Review, reporting, stage 2 starts after approved CDR Q4 2017 10% Stage 2 9 Receiving and arrival inspection reporting of first batch of niobium material at STFC 20/6/2017 12 FAT at STFC and shipping of high-β cavities for CM 1 to CEA 25/10/2018 18 FAT at STFC and shipping of high-β cavities for CM 2-3 to CEA 3/2/2019 19 FAT at STFC and shipping of high-β cavities for CM 4-6 to CEA 6/6/2019 20 FAT at STFC and shipping of high-β cavities for CM 7-9 to CEA 3/10/2019 21 FAT at STFC and shipping of high-β cavities for CM to CEA 3/3/2020 22 FAT at STFC and shipping of high-β cavities for CM to CEA 3/6/2020 23 FAT at STFC and shipping of high-β cavities for CM to CEA 3/9/2020 24 FAT at STFC and shipping of high-β cavities for CM to CEA* 4/12/2020 28 Preparation of the data package for SAR 2 regarding cavities to CM 2-21 after assembly and SAT at ESS in Lund Q1 2021 *Note for 84 cavities only (excl spares) Factory Acceptance Tests (FAT) Site Acceptance Tests (SAT) System Acceptance Review (SAR)

8 Risk Register 8

9 Risk Register Nb Defects Procurement Management
Agreed during the TAC that eddy current scanning is the best way forward No capability of Nb scanning at the Nb vendors Discussions held with DESY Scanner can be modified: Larger bed required and a program update Scanning times longer but acceptable Need to assess how this can be included within the schedule  Early procurement of Nb material Procurement Management Suffering long delays in procurement due to changes in the process Mitigation strategy:- Elevated within SBS (Procurement provider) Identified SBS resource and regular communication on progress Procurement plan has been developed with John Webber (IKC Program Office) Documentation for major procurement to be started as early Nb material and cavity procurement will need finalised specifications from ESS as soon as possible STFC needs to define latest dates when the specifications are required Specification for Niobium material is being drafted 9

10 Risk Register HOM Management
Special care on the cavity cells shape needs to be taken for the production cavities Rigorous validation of fabrication procedure to be performed by CEA Saclay prior to STFC purchase of fabricated cavities Understanding of the effects of tuning to be gained from the work under taken on the prototypes by CEA Saclay On going evaluation being undertaken at CEA Saclay in conjunction with work being performed by Roger Jones group at Manchester University 10

11 High-Beta Project Team
High-Beta Cavity Delivery Team Management Project Sponsor – P McIntosh (ASTeC) RF & Cryogenic Group Leader – A Wheelhouse (ASTeC) Interim Project Manager – P Atkinson (Technology) New Project Manager – M Ellis (ASTeC) (Started 1st April) QA Manager – M Pendleton (Technology) Operations – Andy Goulden (ASTeC) RF Senior RF Engineer – P Smith (ASTeC) (Started 18th April) RF Engineer – P Goudket (ASTeC) RF Engineer – K Dumbell (ASTeC) Cryogenics Senior Cryogenic Engineer – S Pattalwar (ASTeC) Senior Cryogenic Engineer – R Buckley (ASTeC) Cryogenic Engineer – L Bizel-Bizzellot (ASTeC) Mechanical Senior Mechanical Technician – P Davies (Technology) Mechanical Technician – W Roberts (Technology) Mechanical Technician – R Corcoran (Technology) Cavity Qualification Team Project Manager Michael Ellis Quality Manager Mark Pendelton Mechanical Technician Phil Davies Wyn Roberts Ryan Corcoran RF Engineer Paul Smith Cryogeninc Engineer Louis Bizel-Bizellot Training plan identified

12 Outline Delivery Schedule Infrastructure Quality Assurance Summary
Scope Delivery Plan Risk Register Infrastructure Cleanroom Shielding Cryogenic Plant Cryogenic System RF System Quality Assurance Summary

13 SRF Hall VTF Cleanroom Full crane coverage Cryo-plant Offices upstairs
He Compressor House Offices upstairs Cavity Goods-In & Out downstairs Thin Film Lab Crab Lab 20m VTF Cleanroom Cryo-plant 55m

14 SRF Hall – Cleanroom Layout
Discussions held with a specialist cleanroom firm Cleanroom performance specification defined HPR requirements defined Specification being prepared Mobile cleanroom requirements being defined after DESY visit Tenders need to be progressed urgently He Compressor House Offices upstairs Cavity Goods-In & Out downstairs Thin Film Lab Crab Lab VTF Cleanroom Cryo-plant

15 Shielding Outlined radiation assessment initially performed
More detailed assessment completed by Nuclear Technology

16 Shielding ADD PICTURES FROM SHIELDING REPORT
Concrete thickness is defined – 1.85 m Approval from RPA gained Mechanical shielding design is still being finalised Procurement through central services Digging of hole to commence shortly ADD PICTURES FROM SHIELDING REPORT

17 Cryogenic System He-Liquefier 8 Procurement Schedule

18 Cryogenic Plant Air Liquide Advance Technologies
Cryogenics plant will consist of: He Liquefier (100 l/h) 3000 l LHe Dewar Helium Recovery System (10g/s) Gas Storage Order has been placed with Air Liquide Advance Technologies Project kick-off meeting held 17th March 2017 Preliminary design review was held 9th May 2016 Final design review to held July 2016 Delivery by February 2017 Commissioning of system July 2017 (after cryostat delivery) Air Liquide Advance Technologies PFD & Process description

19 Horizontal Tests in a Cryostat
Aim to test 3 cavities horizontal in the cryostat Diameter sufficient to test 3 vertically if required Helium vessel will be used to cool the cavities: Reduced LHe requirements  75% saving on LHe and gas storage Automatic leak checks on He vessel Higher confidence in performance Quicker cool-down/warm up periods Cryostat order placed with Criotec Schedule discussions held Kick-off meeting 1st June 2016 Requirements to be fully defined and agreed Delivery May 2017 (Improvement from the original date of July 2017) Cryostat Proposed Design

20 Cryostat P&ID Layout To GHe Recovery LHe From Cryo-Plant 40 K GHe JT
FM2230 2K pumps To GHe Recovery TI2005 PI2157 FM2232 HT2040 PRV2181 HTR TI2009 HT2044 LHe PI2156 HTR From Cryo-Plant FM2231 BD2170 HT2041 PRV2180 TI2000 40 K GHe HTR PI2150 TI2011 LI2090 BD1170 PI2155 PRV1180 TI2004 HT2042 TI2008 PRV1181 PI2154 TI2001 PI1151 TI2003 HT2043 PI1150 JT PRV3180 Turbo x 3 PI2151 PI3150 RF Port I-Port WARM GHe TI2002 PI2152 TI2010 OVC TI2006 PI2153 Radiation shield TI2007 IVC TI1011 TI3004 LI1090 TI3006 TI3001 TI1010 TI3003 TI1009 HT1043 TI1001 TI1002 TI1000 T1 HT1040 HT3041 V1 HT3040 TI1003 T2 TI3005 V2 TI3007 TI1004 TI1006 T3 TI1005 TI1007 V3 HT1041 TI1008 TI3000 TI3002 HT1042

21 Upstream Circuit of 2K System
Ambient Temperature Transfer Line Helium Recovery Heater LHe HTR Helium Liquefier 40 K GHe 2K Heat Exchanger HTR 4.2K Helium Bath JT WARM GHe 2K box 2K Superfluid Helium Bath And Cavities T1 V1 T2 V2 T3 Upstream Circuit of 2K System V3 Cryostat

22 RF System Microwave Amplifier
Existing VTF test facility configured for an operational frequency of 1.3 GHz. Modifications required to enable testing at 704 MHz. System has been defined Robust and versatile system Low risk as it is an already operational system at JLab RF amplifiers (500W) on order: RF power level allows for F/E and m/p conditions Delivery early July 2016 Majority of the components are on order or have arrived System integration and commissioning to be completed Dec 2016 Microwave Amplifier Low level block diagram Courtesy of Tom Powers (JLab)

23 Outline Delivery Schedule Infrastructure Quality Assurance Summary
Scope Delivery Plan Risk Register Infrastructure Cleanroom Shielding Cryogenic Plant Cryogenic System RF System Quality Assurance Summary

24 Quality Assurance QUALITY MANAGEMENT SYSTEM – ISO 9001:2008
Development of procedures and processes has commenced Processes are being mapped out Visit to DESY undertaken to assess the full requirements for the procedures , documentation and data collection Training plans have been defined Arrangements with DESY for cleanroom training – September 2016 Need a better understanding of parameters to be recorded Understand data collected on prototype cavities tested to date Quality Plan to be defined

25 Cavity Workflow

26 Data Management Requirements of data management system are being defined Cavity material Cavity fabrication Dressed cavity fabrication VTF assembly Cavity performance testing Discussions on-going with a specialist company Establishing a system for the high-β cavity data collection to meet ESS requirements These requirements are still to be finalised

27 Outline Delivery Schedule Infrastructure Quality Assurance Summary
Scope Delivery Plan Risk Register Infrastructure Cleanroom Shielding Cryogenic Plant Cryogenic System RF System Quality Assurance Summary

28 Next Steps Finalise all orders for the Test Facility
Monitoring of vendors for delivery of Test Facility Finalise and sign-off the Technical Annex Specification and procurement documentation for the Nb material Fixed material requirements and specification will be required as this will be bought ahead of schedule to enable eddy current scanning Continue on-going discussions with potential suppliers (Nb and cavity fabrication) Commencement of staff training Cleanroom training at DESY (Sept 2016) Commencement of development of procedures On-going

29 Summary UK IKC signed off by BIS Infrastructure progressing well
Recruitment of ESS Qualification Team complete Nb defect mitigation in place Schedule needs reviewing Technical Annex progressing Scheduled for the high-β elliptical cavities still meets the timescales for the ESS programme


Download ppt "WP : High-Beta Cavity Delivery"

Similar presentations


Ads by Google