Laser Control Status A. Masi, T. Feniet, K. Szczurek Awake Technical Board November 12 th 2015 Thanks for inputs from: M. Donze`, V. Fedosseev, C. Hessler.

Similar presentations


Presentation on theme: "Laser Control Status A. Masi, T. Feniet, K. Szczurek Awake Technical Board November 12 th 2015 Thanks for inputs from: M. Donze`, V. Fedosseev, C. Hessler."— Presentation transcript:

1 Laser Control Status A. Masi, T. Feniet, K. Szczurek Awake Technical Board November 12 th 2015 Thanks for inputs from: M. Donze`, V. Fedosseev, C. Hessler

2 Awake devices control specifications DevicesQtyControl typeFESA Class Op. GUI TimberComments Motorized laser mirrors 18Ethernet Controller + FESA gateway √√√ Motorized translator in Vacuum 1Ethernet Controller + FESA gateway √√√ Controller still to be chosen Motorized translator in air 2Ethernet Controller + FESA gateway √√√ Controller still to be chosen Motorized filter wheels 12PLC + Phytron driver √√√ Cameras12PXIe + Digital acquisition cards √√√ Only 3 cameras will be acquired, beam parameters evaluated thorough online image processing Motorized flipping mounts 2PLC + I/O module √√√ Laser safety shutters 2PLC + I/O module √√√ Laser beam dumps 2PLC + Phytron driver √√√ Interlocks1PLC + I/O module √√√

3 Awake devices control development status DevicesQtyCables Installed Control electronics Control software Development Status Comments Motorized laser mirrors 18 √ Control chassis to be prepared- Patch panel to be made and installed Working Prototype- Implementation in FESA on going Motorized translator in Vacuum 1 √ Controller still to be chosen Motorized translator in air 2 √ Patch panel to be made and installed Controller still to be chosen Motorized filter wheels 12 √ Control chassis to be produced Working Prototype Cameras12 √ To be ordered To be developed Motorized flipping mounts 2 √ To be ordered and assembled In progress Laser safety shutters 2 √ To be ordered and assembled In progress Laser beam dumps 2 √ To be ordered and assembled In progress Interlocks1 √ To be ordered and assembled Specifications to be clarified

4 Awake devices control development timeline DevicesQtyCables Installed Control electronics ready and Installed Control software commissioned Comments Motorized laser mirrors 18 √ Dec 2015 Motorized translator in Vacuum 1 √ Controller still to be chosen Motorized translator in air 2 √ Controller still to be chosen Motorized filter wheels 12 √ Dec 2015 Jan 2016 Cameras12 √ Jan 2016 April 2016 Motorized flipping mounts 2 √ Jan 2016 Laser safety shutters 2 √ Jan 2016 Feb 2016 Laser beam dumps 2 √ Jan 2016 Feb 2016 Interlocks1 √ March 2016 Specifications to be clarified

5 Conclusions  Technical choices to be finalized as soon as possible to proceed with the development  Specifications to be formalized for Cameras image processing and Interlocks  All the materials must be ordered by end of November to be available by the end of the year at the latest


Download ppt "Laser Control Status A. Masi, T. Feniet, K. Szczurek Awake Technical Board November 12 th 2015 Thanks for inputs from: M. Donze`, V. Fedosseev, C. Hessler."