DOE Mini-Review Summary and Management Updates Mark Palmer Fermilab March 15, 2013.

Similar presentations


Presentation on theme: "DOE Mini-Review Summary and Management Updates Mark Palmer Fermilab March 15, 2013."— Presentation transcript:

1 DOE Mini-Review Summary and Management Updates Mark Palmer Fermilab March 15, 2013

2 DOE Mini-Review Held March 4-5 –Indico : https://indico.fnal.gov/conferenceOtherViews.py?view=standard&confId=6466https://indico.fnal.gov/conferenceOtherViews.py?view=standard&confId=6466 –Passcode: muons13 Management “transition” review –Reviewers: Rod Gerig (ANL), Al Zeller (MSU-FRIB), Ron Lutha (DOE) –Presented limited technical information. Focused on: Structural Issues Presentation of key elements of the Execution Plans by each L1 Manager –Goals Validate reorganization plan Identify shortcomings and critical incomplete tasks –Challenges Schedules vs. free-form R&D –“Incentivized” to deal with the unknowns and specify decision points –We need to continue the effort to specify a full baseline design »Even if it is preliminary! This year’s constrained budget (a situation which arose since the last review) has adversely impacted a range of activities, including the transition Will take a quick walk through the closeout. But before that… March 15, 2013 Mark Palmer | MAP Weekly Meeting2

3 MAP Goals Within the 6-year time frame: To deliver results that will permit the high-energy physics community to make an informed choice of the optimal path to a high-energy lepton collider and/or a next-generation neutrino beam facility As well as… To explore the path towards a facility that can provide cutting edge performance at both the Intensity Frontier and the Energy Frontier To validate the concepts that would enable the Fermilab accelerator complex to support these goals March 15, 2013 Mark Palmer | MAP Weekly Meeting3

4 The Muon Accelerator Program Timeline March 15, 2013 Mark Palmer | MAP Weekly Meeting 4 MAP Feasibility Assessment Advanced Systems R&D Muon Ionization Cooling Experiment (MICE) IDS-NF RDR Proposed Muon Storage Ring Facility ( STORM) Evolution to Full Spec Factory Collider Conceptual  Technical Design Collider Construction  Physics Program Proj X Ph I Proj X Ph II Proj X Ph III & IV Indicates a date when an informed decision should be possible

5 MAP Status I: Reorganization To enable us to effectively accomplish these goals, we are in the process of a project-like reorganization: –Implementing tools to manage the effort –Shifting the focus: Milestones and deliverables more explicitly driven by the detailed execution plan developed by the L1/L2 managers in consultation with the Program Director Now operating as a project at Fermilab An updated organization model with the draft of the revised Program Management Plan is an explicit topic for review by this committee At this point, the structural changes are, I believe, in place to accomplish this –Although it remains a work in progress to fully transition to and take advantage of them Anticipate starting the FY14 cycle with all major project management changes in place and tools populated with current program data –There have been some challenges in effecting key changes March 15, 2013 Mark Palmer | MAP Weekly Meeting5

6 MAP Status II: Organization March 15, 2013 Mark Palmer | MAP Weekly Meeting6

7 MAP Status III: Organization March 15, 2013 Mark Palmer | MAP Weekly Meeting7

8 Summary of Critical Milestones & Decisions March 15, 2013 Mark Palmer | MAP Weekly Meeting8 Jan `13 Feb `13 Mar `13 Apr `13 Aug `13 Feb `14 May `15 Jan `16 Mar `16 Aug `13 Feb `14 Jan `17 Jan `18 Implementing a Detailed RLS & Project Plan

9 MAP Mini-Review March 4-5, 2013 Fermi National Accelerator Laboratory Bruce P. Strauss Ron Lutha Al Zeller Rod Gerig

10 Observations Considerable Progress made since last review Very encouraging results in projectizing MAP activities, as well as good technical results. – Management restructuring of MAP is underway and needs to continue, we are concerned about the large number of fractional FTEs in the PMO. – The addition of the MICE construction L1 activity is commended. – A draft PMP was provided – see recommendations. Near term activities are focused on initial baseline selection at the end of FY15, articulation of the criteria needs to be documented and tracked for successful completion of Phase I. MICE remains critical to the success of MAP; there is an upcoming review at RAL. The results of this review are critical to MAP as well as other funding agencies. March 15, 2013Mark Palmer | MAP Weekly Meeting10

11 Observations The committee notes that no formal agreement is in place between the US and UK regarding MICE. The lack of such an agreement appears to hinder progress. We were shown a proposed MICE construction organizational structure. We note that there are a few open roles. In particular the “Component Integration” role is needed. The committee is encouraged to see increased involvement of the National Laboratories. – We are pleased with the leadership of the US MAP program, continued support from the lab is necessary for success. March 15, 2013Mark Palmer | MAP Weekly Meeting11

12 Observations MASS (Muon Accelerator Staging Study) – this is an encouraging effort that has been underway for ~6 months – Need to continue to develop physics and community interest at each stage Technical recommendations from the August review were addressed, but have not been fully accomplished. We suggest they remain open and be pursued. March 15, 2013Mark Palmer | MAP Weekly Meeting12

13 Recommendations from Prior Review Management 1.Complete the transition to a project-like program by February 2013. – well underway but not complete: see this review’s recommendations. 2.Identify the potential technical show stoppers and provide a short list of efforts for early success by February 2013. - we were shown a list of major challenges, but the project did not present a list of show stoppers. The list of efforts for early success was presented in the FY12 Report. March 15, 2013Mark Palmer | MAP Weekly Meeting13

14 Recommendations 1.Complete the transition of the MAP organization and staffing of the MAP PMO so that it is fully in place by the beginning of FY14. 2.Fully develop the Program Management Plan (PMP) incorporating goals, funding profiles, and schedule for the Feasibility Study (Phase I). Ensure that roles and responsibilities are broadly defined and agreed to. March 15, 2013Mark Palmer | MAP Weekly Meeting14

15 Recommendations 3.There is an upcoming MICE baseline review, we believe that this needs to address the full MICE project including all collaborators and funding agencies. 4.Perform a baseline review of U.S. MAP by November 2013. 3.Develop a risk registry for both MICE and MAP. Begin to formulate mitigation plans. Present at the corresponding reviews in recommendations 3 and 4. March 15, 2013Mark Palmer | MAP Weekly Meeting15

16 Other Updates Upcoming Weekly Meetings –Some re-organization is in progress –Further details next week Upcoming Meetings –See next slide March 15, 2013 Mark Palmer | MAP Weekly Meeting16

17 Some Important Dates Muon Collider Higgs Factory Workshop: March 21-23 @UCLA Keep an eye on the CSS2013 pre-meeting calendar: http://www.snowmass2013.org/tiki-index.php?page=premeetings http://www.snowmass2013.org/tiki-index.php?page=premeetings PASI Workshop: April 3-5 @RAL IDS-NF Plenary Meeting: April 5-7 @RAL CSS 2013: Frontier Facilities – Lepton Colliders: April 10-11 at MIT Lehman-style review of MICE Construction activities: May 7-9 IPAC `13: May 12-17, Shanghai, China –Limited MAP Attendees –Please confirm if you have been approved for travel (email to Harold & me) Coordinated MICE & MAP Collaboration Meetings: –MICE Meeting: June 17-18 at IIT –Joint Day: June 19 at Fermilab –MAP Meeting: June 20-22 at Fermilab March 15, 2013 Mark Palmer | MAP Weekly Meeting17