Download presentation
Presentation is loading. Please wait.
Published byEugene Sutton Modified over 8 years ago
1
June 2016
2
4 Skywalk M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E – Toilets 16 e-toilets operational. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 98 % completed. GIS Web Application Software work in progress.
3
3
4
4
5
5
6
6
7
7 Kerbstone Painting along Wipro/Shikaripalaya Road
8
8
9
9
10
10
11
11
12
12
13
13
14
14
15
15 WMM Road From MSME Building to Exit Gate
16
16
17
17
18
18 Installation of Automated Toilets
19
19
20
20
21
21
22
22
23
23 RWH works – Under Progress SI.NODESCRIPTIONNO OF PITSSTATUS 1RAIN WATER HATVESTING PIT 38COMPLETED 2RAIN WATER HATVESTING PIT 12TO BE AWARDED
24
24 20 feet deep well Rainwater Harvesting Pit at Various locations
25
25
26
26 Contract Awarded Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road
27
27 Contracts on Anvil Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2
28
Thank You
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.