ALICE Trigger Upgrade CTP and LTU Design Review ALICE CTP and LTU Upgrade Design Review CERN 27 th January 2016 Budget, time schedule, resources David.

Similar presentations


Presentation on theme: "ALICE Trigger Upgrade CTP and LTU Design Review ALICE CTP and LTU Upgrade Design Review CERN 27 th January 2016 Budget, time schedule, resources David."— Presentation transcript:

1 ALICE Trigger Upgrade CTP and LTU Design Review ALICE CTP and LTU Upgrade Design Review CERN 27 th January 2016 Budget, time schedule, resources David Evans

2 Budget UK research Council (STFC) awarded about £1.3 million over 5 years (January 2015 to December 2019) for trigger upgrade. Most of this is for manpower of course. Plus travel to keep Marian Krivda at CERN and allow the rest of us regular trips to CERN The £1.3 million includes £223,400 for hardware (capital) i.e. for CTP and LTU A sizable fraction of this will be spent of technical effort from RAL for Board Layout.

3 UK Manpower UK manpower (1/1/15 to 31/12/19) Marian Krivda (electronics engineer) @ 50% = 2.5 FTE Anton Jusko (software engineer) @ 20% = 1 FTE Roman Lietava (physicist – trigger upgrade coordination and software @ 100% = 5 FTE David Evans (Group Leader and Project Leader) Plus students

4 Other Manpower Other manpower Jozef Spalek (Kosice) -> CTP octopus cable + debugging of LM0 board + design proposal for Fan-out board Jan Pospisil (Prague) -> design of Low Latency Interface (2015) Luis Alberto Perez Moreno (Autonomous University of Puebla -> implementation of GBT firmware + CTP emulator (work ongoing) (2015 + 2016)

5 2016 Milestones DateLTU MilestoneCTP MilestoneComments Sept 2015LTU pre-prototype delivered CTP prototype delivered Delivered end of March 2015 Dec 2015LTU specifications finished Finish subject to Design Review Jan 2016CTP and LTU Design Review Feb 2016Schematic capture of LTU board March 2016Electronics Design Review March 2016LTU design completed May 2016PCB layout completed (RAL) Subject to RAL TD availability July 2016LTU prototypes finished July 2016 Basic FW & SW functions and emulator completed Nov 2016LTU prototypes tested CTP specifications finished Dec 2016LTU Production Readiness Review

6 2017 Milestones DateLTU MilestoneCTP MilestoneComments March 2017 25% of LTUs produced March 2017 Fully functional FW and SW completed May 2017 LTU Production finished May 2017 CTP design completed May 2017 Schematic capture of CTP board May 2017 CTP Electronics Design Review June 2017 PCB layout completed (RAL) Subject to RAL TD availability Aug 2017 CTP prototype finished Oct 2017 Basic FW and SW complete Dec 2017 Testing of CTP finished

7 2018-2020 Milestones DateLTU MilestoneCTP MilestoneComments Feb 2018 CTP pre-series production finished Feb 2018 CTP Production Readiness Review June 2018 Integration tests of trigger system with DAQ (in CERN lab) completed Aug 2018 CTP Production Finished March 2019 Installation and testing of trigger system in ALICE cavern completed Aug 2020Commissioning of trigger system with all ALICE detectors and systems completed

8 Summary Finances – should be enough for not much contingency Manpower – tight (extra effort would be useful) Schedule – on schedule but tight in 2016 and 2017. approximately six months contingency built in at the moment


Download ppt "ALICE Trigger Upgrade CTP and LTU Design Review ALICE CTP and LTU Upgrade Design Review CERN 27 th January 2016 Budget, time schedule, resources David."