Project Management History and concepts Critical Path Method (CPM) Original CPM and Modern CPM Valerio Salomon, 20161.

Similar presentations


Presentation on theme: "Project Management History and concepts Critical Path Method (CPM) Original CPM and Modern CPM Valerio Salomon, 20161."— Presentation transcript:

1 Project Management History and concepts Critical Path Method (CPM) Original CPM and Modern CPM Valerio Salomon, 20161

2 History Valerio Salomon, 20162 Egyptian pyramids and sphynx Bible (Noah, Solomon, et al.) Roman Empire Da Vinci, Descartes Gantt, CPM, PERT Microsoft, Primavera IPMA, PMI

3 Concepts for project Valerio Salomon, 20163 Design: development and specification of a new product or service Project: sequence of activities or tasks Project: investment alternatives

4 Gantt chart Valerio Salomon, 20164

5 History of CPM Valerio Salomon, 20165 1956: James E. Kelley, Jr. (Du Pont), John W. Mauchly (EMCC), Morgan Walker (Remington) 1957: building a $10M industrial plant 1958: industrial maintenance, reducing MTTR from 125h to 74h 1959: Eastern Joint IRE-AIEE-ACM ConferenceEastern Joint IRE-AIEE-ACM Conference 1961: Operations ResearchOperations Research

6 CPM concepts Valerio Salomon, 20166 Project ≈ network = ∑(events + tasks) Starting event Ending Event Task Change tires Lift down car Assemble spare tire Lift up car Remove spare tire Unfasten nuts

7 Network logics Valerio Salomon, 20167 B C D A B C D A B C D A

8 Dates and slacks Valerio Salomon, 20168 i t 1 t 2 j t 3 t 4 task name duration Data: t 1 (starting earlier date) t 4 (ending later date) Computed: t 3 (ending earlier date) = t 1 + duration t 2 (starting later date) = t 4 – duration Total slack = Slack = t 4 – t 1 – duration Free slack = t 3 – t 1 – duration

9 Project programming with CPM Valerio Salomon, 20169 IDTask namePredecessorDuration [week] 1A–2 2B13 3C21 4D12 5E44 12345678 AA BB CC DD EE 12345678

10 Original CPM (data input) Valerio Salomon, 201610 A2A2 1 2 3 4 2

11 Original CPM (solution) Valerio Salomon, 201611 A2A2 1 0 0 2 2 2 3 5 7 4 4 4 2 8 8

12 Modern CPM (data input) Valerio Salomon, 201612 A 2 B 3 D 2 C 1 E 4

13 Modern CPM (solution) Valerio Salomon, 201613 0 A2 022 2 B5 437 2 D4 224 5 C6 718 4 E8 448


Download ppt "Project Management History and concepts Critical Path Method (CPM) Original CPM and Modern CPM Valerio Salomon, 20161."