Towards Sustainable and Efficient Monitoring NW Hydro Operators Forum - May 8, 2013
2
Dam Safety Team Operations Personnel SCL Management Dam Safety Engineers Consultants and Contractors Regulators
3
Original SCL Dam Safety Team in early 1900’s
4
Boundary Project Team Members
5
SCL Management and Agency Team Members
6
Dam Safety Program Operation and Maintenance Periodic Inspections Monitoring Analysis/Evaluation of Dams Corrective Actions Emergency Action Plans
7
Everything Begins with Accurate Surveying
8
Dam Safety Program Structural Monitoring Dam Safety Instruments Dam Safety Monitoring Reports
9
New RXTX Frames and Communication Conduit
10
Extensometer Head Replacement
11
Dam Safety Program Structural Monitoring