Museum of Islamic Art Project Package # 3 Site Logistics and Progress Presentation
2
INDEX Site Layout & Crane Locations Dates of Main Activities Structural Works Progress – Museum Building Two Level Bridge-Progress & Completion Dates Pedestrian Bridge-Progress & Completion Dates External Stone Cladding Dewatering & Sea Wall (Granite) Removal of the Temporary Platform Fill Around the Building Revetment Works
3
SITE LAYOUT & CRANE LOCATIONS Site as of date 25 March 2005.
4
DATES of MAIN ACTIVITIES Starting the Stone Cladding : 02.04.2005 Important dates to enable the removal of the temporary platform fill –20.07.2005 Chiller will be on site –28.07.2005 Generator will be on site –10.08.2005 Internal Pedesterian Atrium Bridges on Site –12.09.2005 Curtain Wall on Site (Last Material) –21.09.2005 Atrium Dome on Site 15.07.2005 Piles for Boat Dock 10.10.2005 Roofing Completing Date Some Major Structural Completion Dates –31.05.2005 Two Level Bridge –11.06.2005 Pedesterian Bridge –29.05.2005 Car Park/Plaza/Ramp
5
PLANNED DATES FOR STRUCTURAL COMPLETION West Garden : 10.04.2005 Octagone Area 12.09.2005 East Garden : 11.05.2005 Educational Wing 13.05.2005 Two Level Bridge 31.05.2005 Pedesterian Bridge 11.06.2005
6
TWO LEVEL BRIDGE STRUCTURAL DATES 25.03 20.04 11.04 17.04 21.04 Sea Wall Zone D Start : 28.05 Finish : 10.06 22.0427.04 16.04 Temporary Backfill Start : 11.04 Finish : 30.04 Slab Level 1 11.05 18.05 16.05 14.0528.04 Revetment Work Finish : 17.04 Slab Level 2 31.05
7
PEDESTRIAN BRIDGES EXCAVATION DATES Dewatering And Excavating Area Part of Shoreline to be Temporarily filled to enable Pedesterian Bridge Construction A 18
8
PEDESTRIAN BRIDGES EXCAVATION DATES Dewatering And Excavating Area Part of Shoreline to be Temporarily filled to enable Pedesterian Bridge Construction Temporary Fill Start :10.04.05 Finish :25.04.05 Dewatering And Excavating Start :28.04.05 Finish :29.05.05 A 18 A
9
PEDESTRIAN BRIDGE STRUCTURAL DATES 25.05 23.05 21.05 Revetment Work Start : 20.05 Finish : 28.05 19.05 16.05 Slab Level 1 11.06 Sea Wall Zone C Start : 11.06 Finish : 01.07 Temporary Backfill Start : 20.05 Finish : 04.06 27.05 25.05 29.05 31.05
10
EXTERNAL STONE CLADDING Museum Building South Elevations Zone A 02.04 / 29.04 Zone C 09.04 / 20.05 Zone B 04.06 / 20.06 Zone D 16.07 / 02.09 Zone S 02.07 / 26.08 Zone P 02.07 / 26.08 Zone W 09.07 / 16.09 Zone X 12.09 / 07.10 Zone Y 12.09 / 07.10 Zone T 28.06 / 08.07
11
EXTERNAL STONE CLADDING Museum Building North Elevations Zone F 23.04 / 03.06 Zone G 23.04 / 10.06 Zone H 30.05 / 17.08 Zone U 28.06 / 08.07 Zone O 02.07 / 26.08 East Garden 30.04 / 17.06 Zone V 02.07 / 26.08 West Garden 30.04 / 27.05 East Elevation 20.04 / 03.06 West Elevation 18.06 / 22.07
12
DEWATERING & SEA WALL Typical Cross-Section of the sea wall.
13
DEWATERING & SEA WALL Test Pit for the dewatering will be done before the phase #1. #1 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05
14
DEWATERING & SEA WALL Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 #1 #2
15
DEWATERING & SEA WALL Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 #1 #2 #3
16
DEWATERING & SEA WALL Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 4 : Dewatering & Excavating will start at 25.06.05 Sea Wall – Start: 02.07.05 Finish : 22.07.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 #1 #2 #4 #3
17
DEWATERING & SEA WALL Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 4 : Dewatering & Excavating will start at 25.06.05 Sea Wall – Start: 02.07.05 Finish : 22.07.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 Areas to be filled temporarily to enable Dewatering for the adjacent zones. #1 #2 #4 #3
18
DEWATERING & SEA WALL Phase # 5 : Dewatering & Excavating will start at 16.07.05 Sea Wall - Start: 23.07 Finish : 12.08.05 Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 4 : Dewatering & Excavating will start at 25.06.05 Sea Wall – Start: 02.07.05 Finish : 22.07.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 Areas to be filled temporarily to enable Dewatering for the adjacent zones. #1 #2 #4 #3 #5
19
DEWATERING & SEA WALL Phase # 5 : Dewatering & Excavating will start at 16.07.05 Sea Wall - Start: 23.07 Finish : 12.08.05 Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 4 : Dewatering & Excavating will start at 25.06.05 Sea Wall – Start: 02.07.05 Finish : 22.07.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 Areas to be filled temporarily to enable Dewatering for the adjacent zones. #1 #2 #4 #3 #5
20
DEWATERING & SEA WALL Phase # 5 : Dewatering & Excavating will start at 16.07.05 Sea Wall - Start: 23.07 Finish : 12.08.05 Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 4 : Dewatering & Excavating will start at 25.06.05 Sea Wall – Start: 02.07.05 Finish : 22.07.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 Phase # 6 : Dewatering & Excavating will start at 06.08.05 Sea Wall - Start: 13.08.05 Finish : 02.09.05 Areas to be filled temporarily to enable Dewatering for the adjacent zones. #1 #2 #4 #6 #3 #5
21
DEWATERING & SEA WALL Phase # 5 : Dewatering & Excavating will start at 16.07.05 Sea Wall - Start: 23.07 Finish : 12.08.05 Phase # 2 : Dewatering & Excavating will start at 19.05.05 Sea Wall - Start: 28.05.05 Finish : 10.06.05 Phase # 4 : Dewatering & Excavating will start at 25.06.05 Sea Wall – Start: 02.07.05 Finish : 22.07.05 Phase # 1 : Dewatering & Excavating will start at 05.05.05 Sea Wall – Start: 14.05.05 Finish : 27.05.05 Phase # 3 : Dewatering & Excavating will start at 04.06.05 Sea Wall - Start: 11.06.05 Finish : 01.07.05 Phase # 6 : Dewatering & Excavating will start at 06.08.05 Sea Wall - Start: 13.08.05 Finish : 02.09.05 Areas to be filled temporarily to enable Dewatering for the adjacent zones. Phase # 7 : Dewatering & Excavating will start at 27.08.05 Sea Wall – Start: 03.09.05 Finish : 23.09.05 #1 #2 #4 #7 #6 #3 #5
22
DEWATERING & SEA WALL Chillers will arrive 20.07.05 and Sea Wall will start 23.07.05 #1 #2 #4 #7 #6 #3 #5
23
DEWATERING & SEA WALL Generator will arrive 28.07.05 and Sea Wall will start 13.08.05 Chillers will arrive 20.07.05 and Sea Wall will start 23.07.05 #1 #2 #4 #7 #6 #3 #5
24
DEWATERING & SEA WALL Generator will arrive 28.07.05 and Sea Wall will start 13.08.05 Chillers will arrive 20.07.05 and Sea Wall will start 23.07.05 The Latest Curtain Wall & Atrium Bridges & Atrium Dome Material will arrive 12.09.05 Sea Wall will start 03.09.05 #1 #2 #4 #7 #6 #3 #5
25
DEWATERING & SEA WALL These areas will be used for temporary storage of sea walls blocks
26
REMOVAL of TEMPORARY PLATFORM Phase # 1 : Excavation will start after the completion of SeaWall Phase # 1,2,3 finished Start: 02.07.05 Finish : 12.08.05 #1 #2 #4 #7 #6 #3 #5
27
REMOVAL of TEMPORARY PLATFORM Phase # 2 : Excavation will start after the completion of Excavating Phase # 1 finished Start: 12.08.05 Finish : 03.09.05 Phase # 1 : Excavation will start after the completion of SeaWall Phase # 1,2,3 finished Start: 02.07.05 Finish : 12.08.05 #1 #2 #4 #7 #6 #3 #5
28
REMOVAL of TEMPORARY PLATFORM Phase # 3 : Start: 03.09.05 Finish : 23.09.05 Phase # 2 : Excavation will start after the completion of Excavating Phase # 1 finished Start: 12.08.05 Finish : 03.09.05 Phase # 1 : Excavation will start after the completion of SeaWall Phase # 1,2,3 finished Start: 02.07.05 Finish : 12.08.05 #1 #2 #4 #7 #6 #3 #5
29
REMOVAL of TEMPORARY PLATFORM Phase # 4 : Start: 23.09.05 Finish : 15.10.05 Phase # 3 : Start: 03.09.05 Finish : 23.09.05 Phase # 2 : Excavation will start after the completion of Excavating Phase # 1 finished Start: 12.08.05 Finish : 03.09.05 Phase # 1 : Excavation will start after the completion of SeaWall Phase # 1,2,3 finished Start: 02.07.05 Finish : 12.08.05 #1 #2 #4 #7 #6 #3 #5
30
REMOVAL of TEMPORARY PLATFORM Phase # 4 : Start: 23.09.05 Finish : 15.10.05 Phase # 3 : Start: 03.09.05 Finish : 23.09.05 Phase # 2 : Excavation will start after the completion of Excavating Phase # 1 finished Start: 12.08.05 Finish : 03.09.05 Phase# 5 : Start: 15.10.05 Finish : 07.11.05 Phase # 1 : Excavation will start after the completion of SeaWall Phase # 1,2,3 finished Start: 02.07.05 Finish : 12.08.05 #1 #2 #4 #7 #6 #3 #5
31
REMOVAL of TEMPORARY PLATFORM Phase # 4 : Start: 23.09.05 Finish : 15.10.05 Phase # 3 : Start: 03.09.05 Finish : 23.09.05 Phase # 2 : Excavation will start after the completion of Excavating Phase # 1 finished Start: 12.08.05 Finish : 03.09.05 Phase# 5 : Start: 15.10.05 Finish : 07.11.05 Phase # 6 : Start: 07.11.05 Finish : 15.12.05 Phase # 1 : Excavation will start after the completion of SeaWall Phase # 1,2,3 finished Start: 02.07.05 Finish : 12.08.05 #1 #2 #4 #7 #6 #3 #5
32
REVETMENT WORKS Step # 1 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 10.04.05 Finish : 17.04.05
33
REVETMENT WORKS Step # 2 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 04.05.05 Finish : 10.05.05 Step # 1 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 10.04.05 Finish : 17.04.05
34
REVETMENT WORKS Step # 2 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 04.05.05 Finish : 10.05.05 Step # 3 : Revetment Works will start after the Excavation Step #1, #2 Start: 09.09.05 Finish : 26.09.05 Step # 1 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 10.04.05 Finish : 17.04.05
35
REVETMENT WORKS Step # 2 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 04.05.05 Finish : 10.05.05 Step # 3 : Revetment Works will start after the Excavation Step #1, #2 Start: 09.09.05 Finish : 26.09.05 Step # 4 : Revetment Works will start after the Revetment Works Step #3 Start: 26.09.05 Finish : 14.12.05 Step # 1 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 10.04.05 Finish : 17.04.05
36
REVETMENT WORKS Step # 2 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 04.05.05 Finish : 10.05.05 Step # 3 : Revetment Works will start after the Excavation Step #1, #2 Start: 09.09.05 Finish : 26.09.05 Step # 4 : Revetment Works will start after the Revetment Works Step #3 Start: 26.09.05 Finish : 14.12.05 Step # 1 : Revetment Works will start after The Pile Caps and before the slab of the bridge Start: 10.04.05 Finish : 17.04.05 Step # 5 : Revetment Works will start after the Excavation Step #6 Start: 14.12.05 Finish : 31.12.05