Building Committee Presentation March 03, 2015
2
MAIN ENTRANCE
4
TYPICAL CLASSROOM ELEVATION
5
Miller Driscoll Building Committee Construction Update Thursday March 3, 2016 5:00 PM - 7:00 PM Presented by: Turner Construction, CMA 5 Additions & Alterations Miller-Driscoll School
6
Current Monthly Activity – Continued Concrete Foundations – Completed Demolition at Miller Connection – Started Mass Site Cuts & Fills – 50% Complete with Foundations – Underground Utilities in Pre-K wing Complete – Administration relocated storage area in Miller Lower Level 6
7
7 Additions & Alterations Miller-Driscoll School Construction at Miller ConnectorConstruction at Driscoll Connector
8
8 Additions & Alterations Miller-Driscoll School New Mechanical Room Foundations New Addition Foundations
9
Additions & Alterations Miller-Driscoll School March - Monthly Activity – Complete Foundations – Start Steel Erection – Pour Slab in Pre-K – Relocate Access Road into Site South of Current Access – Install Water, Gas, Electrical and IT conduits from Wolfpit – Start demolition and layout in Lower Level Miller Storage area 9
10
10 Miller Lower Level – Storage Area Additions & Alterations Miller-Driscoll School
11
Storm-water Erosion Control – Complaint to Mr. Mike Conklin, Environmental Affairs about erosion control from the 2-24-16 Rainstorm – 1.57” of Rain; – Erosion Control Breech in six locations on site. – Wilton Environmental Affairs Noted a Violation formally – Repairs and additional silt fence, hay bales and check dams were installed when the area dried out – Mr. Conklin has reviewed repairs and has requested a few precautionary measures and will continue to be monitoring the site on a regular basis 11
12
12 Additions & Alterations Miller-Driscoll School Erosion Control Looking NorthSediment leaving the site
13
13 Additions & Alterations Miller-Driscoll School Erosion Control Breech NE
14
14 Additions & Alterations Miller-Driscoll School Repaired Silt FenceRepaired Silt Fence/Silt Sock
15
15 Additions & Alterations Miller-Driscoll School Secondary Lines of Silt Fence installedStone Check Dams
16
Critical Schedule Planning – Roof & Exterior Shell Installation starts in April 2016 – Planning with Administration for Summer Renovation – Moving Companies – Received Budget – Re-evaluate the Project Schedule Overall 16 Additions & Alterations Miller-Driscoll School
17
17 Additions & Alterations Miller-Driscoll School
18
Public Out Reach – Parent Committee Mtg 3-15-16 @ 5:00pm – Steel Beam – Students Handprints 18
19
Additions & Alterations Miller-Driscoll School Steel Beam Signage 19