1 The status of RF components G. Riddone, M. Filippova RF development meeting on 24.02.2010

2 The aim of the meeting: to clarify priorities and milestones of supplying the RF components. Projects: TBTS, TBL, KEK, SLAC, Stand-alone test stand, PSI, Trieste/Elettra RF components: Loads Phase shifters Attenuators Hybrids Splitters Directional couplers WR 90 (E/H) bends RF flanges (SLAC design) RF flanges (CERN design) The status of RF components

3 Photos of RF components RF flanges HP load Splitter Directional coupler Hybrid Phase shifter Attenuator RF components

4 TBTS NRF componentsTBTS P1TBTS P2.1TBTS P2.2Total TBTS 1Loads2237 2Phase shifter1 1 3Attenuator11 2 4Splitter 224 5Directional coupler23 5 6WR90/H-Bends12TBC 7WR90/E-Bends610TBC 8SLAC RF flanges - male1525TBC 9SLAC RF flanges - female1725TBC Phase 2.1 difference with respect to Phase 1 Phase 2.2 difference with respect to Phase 2.1 Phase 2.1 is under installation Already supplied

5 TBL For 1 PETS (L = 0.8 m) -1 directional coupler (DC) - 2 loads (L) Also contribution from CEA/Saclay

6 Stand-alone test stand in CTFII F-Cup+Isolator Concrete block girder ACC pump Pump Tee load coupler Circular WG Mode converter WG valve 0.5 m coupler load The 12 GHz Test Stand activity was split in two steps: Step 1: XL5 Klystron testing at SLAC (RF components were supplied at SLAC in December 2009) Step 2: Accelerating structure testing without and with pulse compressor

7 Stand-alone test stand in CTFII ABCD Max(A,B)+C ComponentsSymbol Quantity for klystron testing at SLAC (step 1) Quantity for Test Stand with Pulse Compressor (Step 2) Spare Redundancy for preparation of 2 additional structures in parallel TOTAL Directional coupler WR90DC1612 7 RF Load WR90RFL2414 5 TE 10 □ to TE 01 ○ mode converterMC-61- 7 RF valveRFV-3-- 3 Hybrid TeeHT-2-2 2 SLED1 overmoded (GYCOM)-1-- 1 Circular pumping port Φ50 or 38 mm TBD Rectangular pumping port WR90 TBD Straight rectangular waveguide WR90 TBD H bend rectangular waveguide WR90 TBD E bend rectangular waveguide WR90 TBD NEW! Splitter1 1 Already supplied The information was taken from “12 GHz RF components meeting – 8 April 2009”

8 X-Band system – PSI Layout ITEMQtyStatus Bidirectional coupler5To be supplied HP Load3To be supplied Power splitter2To be supplied WR90 for wg network20mTo be supplied E-Bend4To be supplied H-Bend12To be supplied Flanges60 (30m + 30f)To be supplied Pumpout ports9In house production WR90 for pumping port2mAlready delivered Flanges for measurements8 (4m + 4f)Already delivered Proposed strategy: Receive components as soon as they are available! FLANGES have high priority and should be sent a.s.a.p.

9 X-band WG circuit layout (Trieste/Elettra ) NRF componentsneedssparetotal 1WR90 117.0 Fx113.0 M (H BAND)4TBC4 2WR90 117.0 Fx181.2 F (H BAND)2TBC2 3Power splitter (X-BAND T)1TBC1 4WR90 directional coupler3TBC3 5WR90 load2TBC2 6Gasket WR9050TBC50

10 The status of RF components

11

12 Loads - 10 from CINEL (in 2 month, in the worst case by the end of April 2010) – we asked to double the production rate - two machines will run in parallel Directional couplers - 5 from COBHAM (delivery time of the prototype - June 2010, series - 11 Sep 2010) - 1 from NIHON KOSHUHA (delivery time - 5 July 2010) - 16 from ? (we have asked the price enquiry) - production line also started with China, IHEP Flanges - 100 male from SLAC - 100 female from SLAC We have just received them

13 Conclusions New components will have to be ordered: Loads RF flanges WGs WR90 H/E bends Dates when the components will be needed have to be confirmed