PROJECT SELECTION RIGHT TOOLS, RIGHT TIME, RIGHT PROJECT Presented by Joe Ririe, PE PAVEMENT ENGINEERING INC. September 9, 2015
2
Pavement basics Pavement preservation principles Project selection Pavement evaluation and testing Cost analysis and life cycle cost benefits Quality control and quality assurance PRESENTATION GOALS
3
PAVEMENT BASICS
4
Pavement Design Loading ESALS = Traffic Index or TI PAVEMENT BASICS Soils (R-value) GE = 0.0032 (TI)(100-R)
5
Pavement Deterioration Cycle PAVEMENT BASICS
6
Asphalt concrete deteriorates in two ways: Pavement Deterioration Oxidizing effects of sun and water Fatigue from heavy wheel loads PAVEMENT BASICS
7
The Impact of Sun and Water PAVEMENT BASICS
8
The Impact of Heavy Loads PAVEMENT BASICS
9
What is a Traffic Index? The projected equivalent single axle loading that a pavement will experience over its design life PAVEMENT BASICS
10
ESAL = (Axle Wt / 18,000 lbs) 4.2 Equivalent Single Axle Load PAVEMENT BASICS
11
Traffic Index vs. ESALs PAVEMENT BASICS
12
Alligator cracking Block cracking Distortions Longitudinal / transverse cracking Patches / utility cuts Rutting / depressions Weathering / raveling Common Pavement Distresses PAVEMENT BASICS
13
Block Cracking Alligator Cracking Transverse or Longitudinal Cracking Weathering or Raveling Common Pavement Distresses PAVEMENT BASICS
14
PAVEMENT PRESERVATION PRINCIPLES
15
Applying the RIGHT TREATMENT to the RIGHT PAVEMENT at the RIGHT TIME using the RIGHT MATERIALS PAVEMENT PRESERVATION PRINCIPLES
16
Pavement Preservation Timing PAVEMENT PRESERVATION PRINCIPLES
17
Best-First “Top Down” Management: focuses maintenance and rehabilitation on the best streets in the system. Interim procedure. Worst-First “Bottom Up” Management: focuses maintenance and rehabilitation on the worst streets in the system. Interim procedure. Critical-Point Management: focuses maintenance and rehabilitation on streets above rather than below a critical PCI. Most economical in the long run. Good Pavement Management PAVEMENT PRESERVATION PRINCIPLES
18
Pavement Condition vs. Maintenance / Rehabilitation Cost PAVEMENT PRESERVATION PRINCIPLES
19
Pavement Condition vs. Maintenance / Rehabilitation Cost PAVEMENT PRESERVATION PRINCIPLES
20
PROJECT SELECTION
21
Time of year Proximity to schools Day or night Traffic control needs Project Timing
22
Selecting the Right Streets PROJECT SELECTION PMS data Multi-year plan Visual conditions Grouping streets Public input Staff input Budget Utility coordination Grants Drainage ADA
23
Selecting the Right Treatment Visually dividing your street list Project Street ListMaintenance StreetsRehabilitation Streets Environmental determination Extent of loading failures Extent of ADA improvements Physical testing to determine structural adequacy If adequate, consider maintenance option PROJECT SELECTION
24
PAVEMENT EVALUATION AND TESTING
25
Rehabilitation Streets Design controlled by Reflective Cracking Structural Adequacy
26
Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
27
Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
28
Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
29
Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
30
N Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
31
Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
32
Deflection Testing and Coring PAVEMENT EVALUATION AND TESTING
33
Resistance R-Value Testing PAVEMENT EVALUATION AND TESTING
34
R-Value Design PAVEMENT EVALUATION AND TESTING
35
Design Considerations Previous overlays / existing crown Road improvements Shallow utilities PAVEMENT EVALUATION AND TESTING
36
Design Considerations for Sustainable Options Cold-in-place recycling (CIR) Pulverization and resurfacing / full-depth reclamation (FDR) Milling and resurfacing requirements PAVEMENT EVALUATION AND TESTING
37
Cold In-place Recycling Pavement must be structurally adequate. Pavement must have a minimum HMA layer thickness. Pavement must have a minimum existing base of 10 inches if R-value is less than 30. CIR depth cannot extend to base layer. Why? 1.75 to 2.50-inch cap is not sufficient if a pavement is structurally deficient (may not meet HMA design). A minimum depth ensures good CIR layer (3-4 inches). A minimum base thickness ensures heavy equipment doesn’t destabilize the grade.
38
Pulverization and Resurfacing/FDR PAVEMENT EVALUATION AND TESTING The preferred Traffic Index (TI) should be less than 7.0. Pavement must have a minimum aggregate base of 12 inches or an R-value less than 30. Pavement must have a minimum aggregate base of 9 inches or an R-value greater than 30. Check crown. Why? Typical build-up is not feasible over 2 to 3 inches unless there are no vertical constraints. Pulverizing, grading and compacting will destabilize a grade if the R-value and corresponding base thickness do not meet minimums. The intent of pulverizing is to create a new aggregate base section. Generally, limiting the off-haul of the pulverized base is important to ensure a sufficient structural section.
39
Milling and Resurfacing PAVEMENT EVALUATION AND TESTING Pavement must be structurally adequate or only slightly deficient. Pavement must have a minimum existing HMA depth of 5 inches. Why? Milling reduces the in-place structural capacity and requires some replacement value. If the pavement is structurally deficient, the mill depth typically becomes excessive. A minimum layer thickness is necessary to ensure milling equipment and loaded trucks do not break through the existing HMA.
40
COST ANALYSIS LIFE CYCLE COST ANALYSIS (LCCA)
41
COST ANALYSIS
42
Develop and Evaluate Recommendations Short-term pavement rehabilitation options These options are not available for this street because of structural deficiencies and/or pavement cracking condition. COST ANALYSIS
43
Develop and Evaluate Recommendations Long-term pavement rehabilitation options Overlay Option: RHMA For option 1, we recommend 4-inch digouts for base failures, placing a 1/2 inch HMA leveling course and a 1-3/4 inch RHMA overlay. Estimated Cost: $241,000Estimated Life Expectancy: 10-12 Years Overlay Option: RHMA For option 1, we recommend 4-inch digouts for base failures, placing a 1/2 inch HMA leveling course and a 1-3/4 inch RHMA overlay. Estimated Cost: $241,000Estimated Life Expectancy: 10-12 Years
44
COST ANALYSIS Develop and Evaluate Recommendations Long-term pavement rehabilitation options Overlay Option: HMA An overlay using HMA is not recommended because the 3-3/4 inch structural requirement exceeds the 3-1/2 inch maximum overlay that is considered feasible to meet geometric constraints. Overlay Option: HMA An overlay using HMA is not recommended because the 3-3/4 inch structural requirement exceeds the 3-1/2 inch maximum overlay that is considered feasible to meet geometric constraints.
45
COST ANALYSIS Develop and Evaluate Recommendations Long-term pavement maintenance options Recycle and Mill and Replace Options These options are not available for this street because of the structural deficiencies and thin pavement layer. Recycle and Mill and Replace Options These options are not available for this street because of the structural deficiencies and thin pavement layer.
46
COST ANALYSIS Develop and Evaluate Recommendations Long-term pavement rehabilitation options Reconstruction Option 1 For option 1, we recommend removing the pavement to a depth of 10-1/2 inches and placing 10-1/2 inches of new HMA. The HMA should be placed in 4 lifts. Estimated Cost: $631,000 Estimated Life Expectancy: 20 Years Reconstruction Option 1 For option 1, we recommend removing the pavement to a depth of 10-1/2 inches and placing 10-1/2 inches of new HMA. The HMA should be placed in 4 lifts. Estimated Cost: $631,000 Estimated Life Expectancy: 20 Years
47
COST ANALYSIS Develop and Evaluate Recommendations Long-term pavement rehabilitation options Reconstruction Option 2 For option 2, we recommend removing 4 inches of the existing structure, lime treating the native soil and aggregate base to a depth of 13 inches and placing 4 inches of new HMA in 2 lifts. Estimated Cost: $292,000 Estimated Life Expectancy: 20 Years Reconstruction Option 2 For option 2, we recommend removing 4 inches of the existing structure, lime treating the native soil and aggregate base to a depth of 13 inches and placing 4 inches of new HMA in 2 lifts. Estimated Cost: $292,000 Estimated Life Expectancy: 20 Years
48
Develop and Evaluate Recommendations COST ANALYSIS
49
QUALITY CONTROL AND QUALITY ASSURANCE
50
QC / QA Vheem Mix vs. Superpave Mix
51
QC / QA Caltrans Section 39 (2010) Method Standard QC/QA
52
Mix Design Submittals JMF – 3511, 3512 and 3513 Production start-up
53
QC / QA Importance of Compaction
54
QUESTIONS?