Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014
2
Upgrade Overview 8/21/14 2 Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab, Newport News, Virginia, USA 5.5 pass capable, with recirculating linacs Energy capability upgraded from 6 GeV to 12 GeV Magnets removed and refurbished Additional cryomodules installed New beam line installed New experimental hall
3
Commissioning Overview A successful commissioning period, December 2013 to May 2014 All major milestones were achieved Some of the success was the result of updated processes and tools used for communication between operations, engineering, and technical staff. 8/21/14 3
4
Communication Challenges Issues: 1.How does the Operations Crew in the Control Room get the most up-to-date information regarding the state of the hardware? 2.How do the Crews know if they are allowed to send beam to a destination? 3.How do the Crews know what they need to do on a given shift? 8/21/14 4
5
Suite of Tools Used 8/21/14 5 Shift Turnover (Word of Mouth Communication) Shift Turnover (Word of Mouth Communication) Operator Work Planning Shift Prep Shift Prep Accelerator Task List (ATLis) Accelerator Task List (ATLis) Hot Checkout Accelerator Bypassed Interlocks (ABIL) Accelerator Bypassed Interlocks (ABIL) Beam Authorization Program Deputy Shift Plan Electronic Log Book
6
8/21/14 6 Required Reading for Operations Checklist requires that the person, read and understand a number of communication tools or documents prior to their shift. I will briefly highlight some of the items on this list, and a few that are not on the list but can be used as resources.
7
Accelerator Task List (ATLis) 8/21/14 7 Can be used to find more information about specific tasks or test plans. Anyone can comment on tasks. All activities that will directly, or indirectly, affect accelerator operations must have a task in this database. Plan is reviewed by several groups before being approved.
8
System Checkout Tool Relates the readiness of hardware. Uses a relational database of elements. Item that is “Not Ready” has not been checked or has been downgraded. Technicians have checklists for their systems and “Check” Equipment. Then the respective group leader elevates the state to “Ready”. 8/21/14 8
9
System Checkout Tool (Cont.) Crews have the ability to check hardware prior to operating the equipment. This is Number 7 on the Operator Checklist Stamp. Tool users have the ability to scroll down to see what components are preventing the “Checked state. 8/21/14 9
10
Accelerator Bypassed Interlocks Log (ABIL) 8/21/14 10 An “Interlock” is either hardware or software protection for some machine component or personnel safety. All Interlocks that are bypassed are inserted into an electronic log. A tag must be placed on the physical device that was bypassed. Log allows crew to see what interlocks they can expect not to be active. Depending on the state of the bypass, it may affect what hardware can be operated. This is Number 8 on the Operator Checklist Stamp.
11
Suite of Tools Used 8/21/14 11 Shift Turnover (Word of Mouth Communication) Shift Turnover (Word of Mouth Communication) Operator Work Planning Shift Prep Shift Prep Accelerator Task List (ATLis) Hot Checkout Accelerator Bypassed Interlocks (ABIL) Beam Authorization Program Deputy Shift Plan Electronic Log Book
12
8/21/14 12 Beam Authorization Beam authorization is issued by the Director Of Operations. Where can we send beam? Are major systems in a state that we can send beam? What is the highest beam mode we can run? What beam current ?
13
8/21/14 13 Program Deputy (PD) Shift Plan Web-based tool used to document activities related to a specific shift. This is Number 2 on the Operator Checklist Stamp Provides the program for the shift and any shift-specific instructions PD Shift Plan is created by the Program Deputy (PD) PD rotates every 2 weeks PD is selected by the Operations Group Leader and cleared with appropriate cross- divisional managers.
14
8/21/14 14 Example shows typical messages Also used as a dashboard for important reminders (the Standing Orders) for the crews Program Deputy (PD) Shift Plan Standing Orders for Operations
15
Log Books 8/21/14 15 Hardware Entry (Technician) Auto Log of Checklist Stamp Auto Log from PD Summary from Meeting Presentation Log of shift activities. Good source to find out the latest activity. Some tools will post automatically. Technicians as well as Operations use this tool. Shift Leader has area to make announcements
16
Suite of Tools Used 8/21/14 16 Shift Turnover (Word of Mouth Communication) Shift Turnover (Word of Mouth Communication) Operator Work Planning Shift Prep Accelerator Task List (ATLis) Hot Checkout Accelerator Bypassed Interlocks (ABIL) Beam Authorization Program Deputy Shift Plan Electronic Log Book
17
8/21/14 Shift Turnover Word of mouth is still a great source of information. All crew members are required to arrive 15 minutes before the shift begins to receive passdown of information from the outgoing crew. Equally, the outgoing crew must stay late 15 minutes to give the passdown. Crew Chief and Operators also overlap by one hour for information flow. 17
18
Beyond Commissioning During commissioning, good communication was key to progress. Some of the tools outlined were old tools and some were brand new. The set of communication tools used for commissioning worked well for getting up-to-date information to the crews. Prior to the fall run, many components were downgraded in readiness and then rechecked. Some of this same process will be used again, after commissioning is complete. 8/21/14 18
19
Questions??? 8/21/14 19