1
Cluster Active Archive Status of DWP Data Activities Simon Walker, Keith Yearby, Michael Balikhin Automatic Control and Systems Engineering, University of Sheffield
2
18th CrossCal Workshop Cosners House, Abingdon, UK Overview Management Current Status –Datasets –Software –Documentation –Delivery Delivery plans Action Items
3
18th CrossCal Workshop Cosners House, Abingdon, UK Management Michael Balikhin DWP PI Keith Yearby TM DWP TCOR Simon Walker COR, LOG, PIOR ICD, UM, CR Contract: New Change Notice received from ESA. Finance/Contracts currently in process of completing the paperwork.
4
18th CrossCal Workshop Cosners House, Abingdon, UK Current Status TCOR –Processing of the 2013 data set has begun. DWP_LOG UT_PIOR –Delivered to end September 2013 CORR_FX, CORR_ST –Delivered to end September 2012.
5
Delivery Status 18th CrossCal Workshop Cosners House, Abingdon, UK
6
Software Development 18th CrossCal Workshop Cosners House, Abingdon, UK Production of CORR data requires a PEACE application to extract various parameters from PEACE science files. A problem occurred in the processing of PEACE science data files, causing a segmentation fault and incomplete PEACE mode listings. Affects files from around May 2013 onwards for satellite 3. Code modified to fix problem. Currently testing. Currently production of CORR files unaffected.
7
18th CrossCal Workshop Cosners House, Abingdon, UK Header Files Harri reported some inconsistencies in CAA DWP header files. CORR – Buckley listed as first contact EXP – Alleyne listed as PI CAA is using OLD versions of the header files ! The current set of CORR and EXP headers will be redelivered.
8
18th CrossCal Workshop Cosners House, Abingdon, UK Documentation ICD User Manual Calibration Report No changes
9
Caveats 18th CrossCal Workshop Cosners House, Abingdon, UK ALL DATA SETS DWP produces one caveat file per satellite per dataset. No new files produced.
10
18th CrossCal Workshop Cosners House, Abingdon, UK Delivery Schedule Year0102030405060708091011121314 CORR 1 CORR_PLOT DDDDDDDDDDD8/133/143/15 TCOR DDDDDDDDDDDD4/144/15 DWP_LOG DDDDDDDDDDDD3/143/15 UT_PIOR DDDDDDDDDDDD3/143/15 D – Data delivered, 1 Depends upon FGM 5VPS and SP AUX data sets FGM available to end April 2013, (no FGM files for Nov 2012 ) AUX available to end May 2013
11
Problems 18th CrossCal Workshop Cosners House, Abingdon, UK Delivery. CORR files slightly behind schedule. Data files have been produced, just require validation. Production Problems with obtaining science parameters from PEACE Affects period May 2013 onwards. A solution has been found and requires testing. Does not affect data already delivered.
12
Action Items 18th CrossCal Workshop Cosners House, Abingdon, UK OR7-R02 The board recommends that all teams ensure that they have provided detailed information to the CAA regarding the pointing of instrument sensors relative to the spacecraft reference frame. Response DWP uses the PEACE HEEA sensor. Its location is detailed in the UG. OR7-R03 The board recommends hat instrument teams provide information regarding special operations, including their description and time on operation. Response This list is being compiled.
13
Action Items 18th CrossCal Workshop Cosners House, Abingdon, UK OR8-R13 The board recommends that instrument teams ensure that all ancillary data sets are fully described in their ICDs. Response All DWP data sets are fully described in the ICD. OR8-R14 All instrument teams should ensure that their user guides contain a detailed description and time-line of instrument operations and failures. Response We are currently collecting this information together. OR8-R15 The board recommends that all teams investigate data quality at mode changes and instrument switch-on or switch-off. Response We are currently looking into this aspect of operations. It is dependent upon PEACE HEEA sensor.