Download presentation
1
Quebec Bridge Collapse
2
Head Engineer Head Engineer: Theodore Cooper
Highly respected reputation Wanted a monumental project to end his career Unrivalled for the tender Overconfident
3
The Quebec Bridge company
Lack of funds Never built a bridge with a span larger than 300 feet Wanted “quickest and cheapest” solution
4
Cooper only visited the site 3 times
Cooper appointed, Norman McLure, with no experience, to be his eyes and ears on site.
5
Pre-Construction No preliminary tests and research studies done
Bridge was extended an extra 200 feet without any calculations No recalculations of assumed weights for the bridge after revised specifications Theoretical estimates of weights used
6
Construction continued without dead load being calculated
Phoenix Bridge Company’s inspector of materials projected weight of the steel was 11 million pounds heavier than previously estimated. Cooper concluded that Edwards was wrong by 7 to 10%. This was after much of the bridge was fabricated or in place
7
During Construction Horizontal compression members started deflecting
Unable to line up members for riveting As span increased many weight-bearing lower chords were still unriveted Eventually two of the chords from the south cantilever arm bent
9
Chief engineer in Phoenixville insisted that these chords were bent when they left the shop and that they were still serviceable Cooper sent word to Phenoix Bridge Company to suspend construction which was ignored
10
Collapse
11
Two compression cables failed.
Sudden collapse! 75 were killed
12
2nd Collapse A second collapse occurred in 1916
Similar design but two and a half times heavier than its predecessor During the construction the central span which was pre-fabricated dropped into the river while being lifted into place 11 men died.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.