Presentation is loading. Please wait.

Presentation is loading. Please wait.

Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Interface and Logistics Workshops August 10-12, 2015.

Similar presentations


Presentation on theme: "Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Interface and Logistics Workshops August 10-12, 2015."— Presentation transcript:

1 Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Interface and Logistics Workshops August 10-12, 2015

2 LBNF Surface Scope 07.15.15Joshua Willhite | FSCF Scope2

3 LBNF Surface Scope 07.15.15Joshua Willhite | FSCF Scope3 Ross Dry & Control Room Cryogenic Compressor Building Power Feed

4 LBNF Control Room Requirements: Minimum 400 GSF for 10 occupants Data connection and fire alarm system connection All data systems provided by experiment HVAC to maintain personnel comfort and control data rack temperature Design: Utilize existing room within Ross Dry Building Make ADA compliant (this is the only scope with this requirement) Lead AHJ has formally approved this 07.15.15Joshua Willhite | FSCF Scope4

5 LBNF Power Supply Existing Ross Substation has 20 MVA capacity, using ~5 (plenty of capacity) Surface Power Requirement: ~5.3 MW Underground Power Requirement: ~2.9 MW Add additional switchgear in substation for new feeders Utilize existing utility bridge to connect to existing steam tunnel Protect new cables by embedding conduits within new concrete floor in the steam tunnel Split power at shaft, one cable set feeding the underground, one feeding the surface compressor building and control room 07.15.15Joshua Willhite | FSCF Scope5

6 LBNF Power Supply Route 07.15.15Joshua Willhite | FSCF Scope6

7 LBNF Cryogenic Compressor Building Interfaces and Requirements Cryogenics group responsible for dewars, purity monitoring system, vaporizers, compressors, and gas piping inside the building CF responsible for building, civil works, cooling towers, coolant recirculation, power supply (normal, emergency, standby), and gas piping from building to the underground. Cryogenics group defined building footprint by providing drawings and compressor specifications. (DocDB 9965)DocDB 9965 Compressor sizing and pipe sizing is based on desired filling rate of the detectors. Once full, fewer compressors will operate to circulate nitrogen to the underground. 07.15.15Joshua Willhite | FSCF Scope7

8 LBNF Cryogenic Compressor Building 07.15.15Joshua Willhite | FSCF Scope8

9 LBNF Cryogenic Compressor Building Elevations 07.15.15Joshua Willhite | FSCF Scope9

10 LBNF Ross Dry 07.15.15Joshua Willhite | FSCF Scope10

11 LBNF Other Surface Scope (early work managed by SURF) SURF has identified several surface projects that are believed to pose risks to the facility and should be addressed prior to LBNF construction as follows: Near-surface adit repairs (Tramway, 300L) Crusher building roofs at both shafts Hoist upgrades (motor rebuilds) Headframe reinforcement at both shafts Administrative Building Parking lot/roadway Oro Hondo Fan 07.15.15Joshua Willhite | FSCF Scope11

12 LBNF Shaft Scope Utilities in the shaft include: Power Fiberoptics for data separate from fire alarm Nitrogen (three 12”, two 8”) and argon (one 8”) gas pipes Concrete slick line for construction in 6 winze Fire water pipe from 4100L to 4850L Existing 4” water line will feed a sump at the 4100L and continue past to service other water needs. 6” fire line from 4100L sump to 4850L Other shaft scope (early work managed by SURF): LBNF paying for 2016/2017 rehab New cage and skips 07.15.15Joshua Willhite | FSCF Scope12 Changing for 100% (2) 16” N2 pipes rather than (3) 12”

13 LBNF Yates Shaft Scope For the 100% design, Arup is including the following work for the Yates Shaft: Removal of bracing in the headframe to accommodate 17m long beams Replacement of timber within shaft from just above the 4850L to the bottom with steel Raising the brow at Yates to accommodate 17m long beams Enlarging the 4850L station to allow beams to come out of skip compartment Mike Johnson is working on special conveyance designs to expedite beam delivery. This is not in Arup’s scope. The corner beams are an unsolved problem at this time. 07.15.15Joshua Willhite | FSCF Scope13

14 LBNF From Dimitar and Diamante 07.15.15Joshua Willhite | FSCF Scope14

15 LBNF Cryostat Structure Bill Of Materials 07.15.15Joshua Willhite | FSCF Scope15

16 LBNF Yates Brow 07.15.15Joshua Willhite | FSCF Scope16

17 LBNF Delivery Route 07.15.15Joshua Willhite | FSCF Scope17

18 LBNF Monorails 07.15.15Joshua Willhite | FSCF Scope18 For 100%, two monorails located 1.5m from side walls, one centered on cavern No known height requirement, so placed as close to back as possible 10 metric ton capacity meeting deflection criteria of L/1000 5 m gap between detector caverns to allow room for utilities to cross caverns Beams do NOT extend into east or west access drifts – only to cavern end (see next slide) Unclear interface with clean room

19 LBNF AHU Placement 07.15.15Joshua Willhite | FSCF Scope19

20 LBNF Underground Excavation 07.15.15Joshua Willhite | FSCF Scope20 No

21 LBNF Cavern Locations 07.15.15Joshua Willhite | FSCF Scope21

22 LBNF Stress Evaluations 07.15.15Joshua Willhite | FSCF Scope22

23 LBNF Drifts – slashed and new access at the 4850L 07.15.15Joshua Willhite | FSCF Scope23 5m x 6m based on old assumptions – will optimize in FD

24 LBNF Cavern Excavation Sequence 07.15.15Joshua Willhite | FSCF Scope24

25 LBNF Phasing 07.15.15Joshua Willhite | FSCF Scope25

26 LBNF Controlling Impacts to other Facilities The Davis Campus is ~1 km upwind of LBNF, so controlling impacts to this campus during construction is relatively straightforward. The Ross Campus is fairly close - ~100m from the nearest extent of the campus to the nearest excavation. CF proposed a limit of 0.5 in/sec vibration and 134 dBL air blast overpressure, both derived from standard mining criteria. The two primary users of the Ross Campus (CASPAR and BHUC) accepted these recommendations. 07.15.15Joshua Willhite | FSCF Scope26

27 LBNF Vibration Control (load size vs. vibration) 07.15.15Joshua Willhite | FSCF Scope27

28 LBNF Air Blast Control Most extreme situation is when building a cryostat in cavern 1 while blasting the second pit due to proximity and cross section – draft concept shown at right (under development) Control at Ross Campus is most challenged by retaining ventilation 07.15.15Joshua Willhite | FSCF Scope28

29 LBNF Life Safety Life safety analysis has defined compartmentation layouts and fire rated egress pathways in each phase. Note that ODH analysis and control is the responsibility of the cryo group, who have defined minimum air flow. Compartmentation for fire events also provides for ODH, but is not designed specifically for it. An existing refuge chamber is currently outfitted for 72 persons, 96 hours occupancy. One SURF Operations project is planning to upgrade this room to support as much as 150 occupants. Any refuge needs beyond this upgraded chamber during construction will be the responsibility of the construction contractor. A logistics study will be completed later this year to understand potential occupancy for all stakeholder. A draft life safety assessment has been posted to DocDB 4395 evaluating the current scope and offering suggestions for improvement.4395 07.15.15Joshua Willhite | FSCF Scope29

30 LBNF Compartmentation and Egress 07.15.15Joshua Willhite | FSCF Scope30

31 LBNF Cyberinfrastructure 07.15.15Joshua Willhite | FSCF Scope31 Need Help Here

32 LBNF HVAC – Chilled water system 07.15.15Joshua Willhite | FSCF Scope32

33 LBNF HVAC - Ducting 07.15.15Joshua Willhite | FSCF Scope33 Note all exhaust through central cavern

34 LBNF HVAC - Ducting 07.15.15Joshua Willhite | FSCF Scope34

35 LBNF Facility Ventilation 07.15.15Joshua Willhite | FSCF Scope35 Intake/Fresh Exhaust/Hot Adding Borehole for 100%

36 LBNF Plumbing and Fire Suppression The cryogenic gas pipes that come through the shaft are taken to the west entrance of the central utility chamber – then responsibility transfers to the cryo group. Water is only required for the HVAC system (spray chamber makeup, cooling) and fire protection. Both will use industrial water supply. Potable water is provided via UV treatment (identical to Davis and Ross Campus systems) for miscellaneous use (no actual requirement exists). Fire suppression systems (sprinklers) are provided in all areas (except mucking ramp) created for LBNF. Hose stations are provided every 200 feet as well. 07.15.15Joshua Willhite | FSCF Scope36

37 LBNF Electrical Loads 07.15.15Joshua Willhite | FSCF Scope37 Underground Electrical Load by AreakW Underground Load by FunctionkW Cryostat 1&2 Detector Electronics450Detector2088 Cryostat 1&2 Argon Pumps98CF1846 Cryostat 1&2 CF350898Total =3934 Cryostat 3&4 Detector Electronics450Aggregate Demand Factor0.736 Cryostat 3&4 Argon Pumps98 Demand Total = 2894 Cryostat 3&4 CF342890 Central Utility Cavern - Detector Cryogenics956 Central Utility Cavern - DAQ36 Central Utility Cavern - CF7531745 Spray Chamber165 Maintenance/Assembly Shops (2)84 Surface Electrical LoadkW Drifts152401Cryogen Building5000 Total =3934Control Room250 Aggregate Demand Factor x0.736Emergency/Standby Generator50 Demand Total = 2894 Total Surface Load 5300 Emergency/Standby Generator = 848Temporary Electrical LoadkW Aggregate Demand Factor = 0.393Construction Power 1653 Generator Demand Total = 334 Emergency/Standby Power 699

38 LBNF Electrical Equipment 07.15.15Joshua Willhite | FSCF Scope38

39 LBNF Lighting Lighting at floor level in all space except detector caverns at 24 lux with occupancy sensors in drifts using UL wet location watertight fluorescent fixtures Lighting at 0.7m above the cryostats at 100-150 lux using UL wet location watertight LED fixtures Emergency lighting throughout with 90 minute battery supply and tied to standby generator 07.15.15Joshua Willhite | FSCF Scope39

40 LBNF Controlling EMI To control electrical interference between facility and experiment electronics, separate shielded transformers are provided, and the experiment ground is isolated using inductors and insulators. Additional requirements have been stipulated to avoid ground paths through detector caverns and provide minimum cable lengths to dampen EMI frequencies. 07.15.15Joshua Willhite | FSCF Scope40

41 LBNF Fire Detection Fire detection monitoring will include Smoke detection (VESDA) Oxygen concentration monitors CO detection Heat detection Sprinkler water flow switches Manual pull stations Notification will include alarm, voice, and visual (strobe) Control panels will be strategically located at the 4850L, as well as within the surface control room. 07.15.15Joshua Willhite | FSCF Scope41

42 LBNF Structural 07.15.15Joshua Willhite | FSCF Scope42

43 LBNF Architectural 07.15.15Joshua Willhite | FSCF Scope43

44 LBNF Waste Rock Handling - Underground 07.15.15Joshua Willhite | FSCF Scope44

45 LBNF Waste Rock Handling - Surface The surface waste rock handling included in this design was developed during the 60% preliminary design for DUSEL. No updates were made beyond updating costs based on escalation. A design-build contract is planned to capture all waste rock handling scope from the skip discharge to a truck loading system as shown on the following slides. 07.15.15Joshua Willhite | FSCF Scope45

46 LBNF Surface waste rock handling plan and elevation 07.15.15Joshua Willhite | FSCF Scope46

47 LBNF Interfaces 07.15.15Joshua Willhite | FSCF Scope47 Weekly meetings to define interfaces, a sampling of which are shown below. The full working document can be found in DocDB 11173.11173

48 LBNF 07.15.15Joshua Willhite | FSCF Scope48


Download ppt "Long-Baseline Neutrino Facility LBNF Far Site CF Scope Joshua Willhite Interface and Logistics Workshops August 10-12, 2015."

Similar presentations


Ads by Google