Whiteland & Graham Roundabout Project Update Trent Newport, PE,LS
2
2
3
Utility Relocations Ongoing and completed by middle or end of April Construction Start Immediate following utility relocations Construction Duration 60 Day Closure/90 Day Completion Fall Plantings 3 Project Construction Schedule
4
4 Striping Plan Details
5
5 Landscape Plan Details
6
6 Detour – Interstate 65 and US 31
7
7 Detour – Local Roads
8
Construction Budget $986,975 $789,580 Fed/$197,395 Local Construction Bid from Reith Riley $980,800 $784,640 Fed/$196,160 Local Inspection Cost $120,000 $96,000 Fed/$24,000 Local 8 Project Cost Update
9
Construction Field Office Location 410 US 31 (SW quad of US 31 and Brahmin Park Drive) On Site Construction Inspection Personnel Justin Schneck jschneck@crossroadengineers.com jschneck@crossroadengineers.com 765-346-0746 cell phone Brad Stahley bstahley@crossroadengineers.com bstahley@crossroadengineers.com 317-417-4126 cell phone Trent Newport tnewport@crossroadengineers.com tnewport@crossroadengineers.com 317-502-2760 cell phone 9 CrossRoad Engineers Contact Info
10
10 Questions?