How the PCIs are developed Céline Heidrecheid System Development Business Area Manager TYNDP perspective on project progress Copenhagen – 24 June 2016.

Similar presentations


Presentation on theme: "How the PCIs are developed Céline Heidrecheid System Development Business Area Manager TYNDP perspective on project progress Copenhagen – 24 June 2016."— Presentation transcript:

1 How the PCIs are developed Céline Heidrecheid System Development Business Area Manager TYNDP perspective on project progress Copenhagen – 24 June 2016

2 2 Gas infrastructures implementation Girland - Artère de Guyenne Phase B Support to north-west market Compressor station (CS) Pipeline LNG Storages Alveringem-Maldegem Reverse capacity from France to Belgium at Alveringhem Extension of existing gas transmission capacity in the direction to Denmark – Step 1 and 2 CS Border at Biriatou Arc de Dierrey Klaipéda LNG Capacity enhancement of Klaipeda- Kiemenai pipeline in Lithuania Nordschwarzwaldleitung Świnoujście LNG Carriço UGS development Slovakia - Hungary interconnection Dunkerque LNG From PCI 1st List Artère de l'Adour (former Euskadour) (FR-ES intercon.) Developments for the Dunkerque LNG Gas Compressor Optimisation Program Gas Storage Bergermeer 19 projects commissioned since TYNDP 2015… …among which 9 from 1st PCI list

3 3 Overview of TYNDP 2017 projects >Significant project progress since TYNDP 2015 >49 Advanced projects 19 projects commissioned 17 projects took their FID 8 projects reported earlier commissioning date TYNDP 2017 Total 231 Advanced: FEED or permitting started and commissioning by 2022 TYNDP 2017 release: December 2016 Project collection: April-May 2016

4 4 2 nd PCI list projects Total 100 2 nd PCI list projects per commissioning year number of projects comm. year 2 nd PCI list projects: status reported in TYNDP 2017 1 2 8 2 14 3 1 4 8 21 2 7 1 13 6 3 12 20 29 9 14 1 3 3

5 5 PCI projects: barriers to investment 37 projects from 2 nd PCI list reported delays compared to TYNDP 2015, mainly due to >worsened and uncertain market conditions >delays in permitting or authorizations from competent authorities >lack of coordination between hosting countries / political uncertainties >delays in contract award procedure >lack of funds / financing >delay resulting from concluding pre- feasibility study

6 6 TYNDP builds on ENTSOG Project Portal >An ever-improving web-based tool... >...keeping track of project progress over time TYNDP reports on project progress >Project schedule >Reasons for project delay and perceived barriers to investment Join our 13 July Workshop to learn more on TYNDP 2017 projects >Detailed information on submitted projects >More insight on project progress TYNDP reports on project progress

7 Thank You for Your Attention ENTSOG -- European Network of Transmission System Operators for Gas Avenue de Cortenbergh 100, B-1000 Brussels EML: WWW: www.entsog.eu Céline Heidrecheid System Development Business Area Manager Celine.heidrecheid@entsog.eu