Presentation is loading. Please wait.

Presentation is loading. Please wait.

Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted.

Similar presentations


Presentation on theme: "Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted."— Presentation transcript:

1 Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted until 2006 ?  Upper & Front Parts - Review - Goals

2 Rad. Shield 2 Feb. 06D.LACARRERE2 HISTORY (in brief)  1996 : Creation of EST/LEA Group for preparing the LHC Expt Areas.  1997 : Concept for dividing the UX85 area in 2 zones – LHCb Note.  1998 : LHCb Technical Proposal – CERN LHCC 98-4 Feb. 1998.  1998 : LHCb Experiment approved in Sept. 1998.  2000 : LEP Stop in November 2000.  2001 : Dismantling of DELPHI (June 01).  2002 : Civil Engineering Work in UX85 (Tympanum + fixed pillars).  2003 : Assembly of the LHCb Magnet (nearby radiation shield)  2004 : Installation of the Central Part of radiation shield (5 beams)  2004 : Bridge crossing the UX85 for LHC transport activities (Sept. 04)  2004 : Assembly of muon filters (MF1-MF3) close the radiation shield.  2005 : QRL 8-1 junction – large scaffolding removed Oct. 05 only.  2006 : Construction & Installation of Upper & Front Parts  2006 : LHC Milestone – Injection Test scheduled for Dec. 06

3 Rad. Shield 2 Feb. 06D.LACARRERE3 FIG. 1 ½ Bridge RB86 until mid-Sept. 04 ½ Bridge RB84 removed 10 May 04 LHC Transport Activities until mid-Sept. 2004 LHCb Magnet from 10 July 04 Metallic Structure 5 July 04 Ass. Area mu-filters from 1 July 04 Concrete beams; 5x 30t Installed 09 June 04 Ventil. ducts / Zone B achieved 25 June 04 Cutting concrete from 24 June 04 Instal.QRL/UX85 End of Oct.04 LHCb Expt. Area - Status June 2004 A B

4 Rad. Shield 2 Feb. 06D.LACARRERE4 13 May 2004 POINT 8 – Main Radiation Shield Delivery - 5 concrete beams 14400 x 1000 x 800 ; 30 t Shield – Central Part FIG. 2

5 Rad. Shield 2 Feb. 06D.LACARRERE5 Radiation Shield Central Part Counting Rooms Assembly of Magnet FIG. 3 09 June 2004 POINT 8 – UX85 Cavern

6 Rad. Shield 2 Feb. 06D.LACARRERE6 Access - Checking Personnel AB A Zone = Protected Area B Zone = Detector Area ACCESS PERSONNEL PZ SHAFT CHICANE MOBILE DOOR Normal Access Emergency exit IP8 MAIN ACCESS EQUIPMENT PX SHAFT ACCESS PM SHAFT RADIADION SHIELD FENCE Access – Checking Tools & small equip. FIG. 4 Conceptual Design (1)

7 Rad. Shield 2 Feb. 06D.LACARRERE7 12/2004 08/200610/200611/2006 FIG. 4 3000 t heavy concrete Average thickness about 3.2 m Apertures ( 2 slits 5400 x 350 mm2) for Services & Cabling 12/2002 Chicanes for ventilation & gas extraction ducts Conceptual Design (2)

8 Rad. Shield 2 Feb. 06D.LACARRERE8 Why installation shifted until 2006 Crane PR 768 1 hook 3.2 t A area B area C Crane PR 720 1 hook 40 t Crane PR 721 2 hooks 40 t LONGITUDINAL VIEW FIG. 5 A : Protected area B : Detector area C : LHC Cryogenics area + LHC beams INSTALLATION SCHEDULED FOR FEB. – DEC. 06 Radiation Shield

9 Rad. Shield 2 Feb. 06D.LACARRERE9 Upper & Front Parts - Review Goals  Fix last details such as option 1 or 2 for the upper part ?  Launch orders for non-standard concrete blocks.  Specify and launch orders for additional lifting means.  Preparation of safety documents for March 06.  Installation of the upper part scheduled for June-July 06  Installation of the front part by December 2006.


Download ppt "Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted."

Similar presentations


Ads by Google