P. 1Mario Deile – TOTEMino: Status and Schedule Mario Deile 28.09.2006 1.Zone 2.Gas system 3.Cooling water 4.Cables 5.Safety 6.Schedule, Project Plan 7.Schedule.

Similar presentations


Presentation on theme: "P. 1Mario Deile – TOTEMino: Status and Schedule Mario Deile 28.09.2006 1.Zone 2.Gas system 3.Cooling water 4.Cables 5.Safety 6.Schedule, Project Plan 7.Schedule."— Presentation transcript:

1 p. 1Mario Deile – TOTEMino: Status and Schedule Mario Deile 28.09.2006 1.Zone 2.Gas system 3.Cooling water 4.Cables 5.Safety 6.Schedule, Project Plan 7.Schedule for 2007

2 p. 2Mario Deile – Zone Zone today =+ T2 gas rack + gas pipes + T2 cables.

3 p. 3Mario Deile – Zone

4 p. 4Mario Deile – Setup (Side View) Cables trays ready 1 ground line per tray (both connected to the 1 common ground of the area, no loops so far) power outlets on the 4 support pillars and on the fence X 2007 ( ) no readout

5 p. 5Mario Deile – Setup (Top View)

6 p. 6Mario Deile – Gas System Green: done by central supply group Blue: done by F. Hahn’s group Red: to be done by TOTEM T2 mixing + distribution rack in place; INOX and plastic pipes installed up to patch panel in zone; pipes from patch panel to T2 rack by end of this week.

7 p. 7Mario Deile – Cooling Water Under construction by Aldo Morelli and two technicians from Pisa / Siena. All parts available from CERN have been ordered and partially delivered. Still missing: plunging thermometers manometres flowmetres (to be ordered from company)

8 p. 8Mario Deile – Cables GEMino cables in place. RPino and CSCino cabling in progress (thanks to Frej and the Pisa / Siena Technicians). Connectors still undefined! Nobody to mount them! Optical fibers still need connector protections. Their installation might be delicate (specialist needed?)

9 p. 9Mario Deile – Safety ISIEC form submitted. “Initial Safety Discussion” took place on 14.09.: no major problems, but after installations several inspections by specialists required Everybody needs to have attended the safety course (levels 1 – 3) within the last 5 years! Dosimeter badge needed to enter the counting-room!

10 p. 10Mario Deile – Schedule From now on weekly testbeam meetings: Wednesday, 14:00 h

11 p. 11Mario Deile – Planning ! ! ! ! !

12 p. 12Mario Deile – Schedule for 2007 Beam request to be submitted by 27. October (~1 month from now) SPS physics from 26. May to 11. November


Download ppt "P. 1Mario Deile – TOTEMino: Status and Schedule Mario Deile 28.09.2006 1.Zone 2.Gas system 3.Cooling water 4.Cables 5.Safety 6.Schedule, Project Plan 7.Schedule."