Site lay out Tanks area Building area Unloading area GT21 GT22GT23 GT24.

Similar presentations


Presentation on theme: "Site lay out Tanks area Building area Unloading area GT21 GT22GT23 GT24."— Presentation transcript:

1 Site lay out Tanks area Building area Unloading area GT21 GT22GT23 GT24

2 Buildings in site E & control building Administration building Singles room building canteen

3 Buildings area in site Administration building canteen Single rooms building

4 Workshop area and internet camera Workshop area Internet camera1 Internet camera2

5 Tanks 81,82, 83 Tank No.81 Tank No.82 Tank No. 100

6 GTs area in site

7 Tanks area in site Tank LDO 071 Tank LDO 072 Tank Treated HFO 061 Tank Treated HFO 062 Tank LDO 073 Tank Treated HFO 063 Tank 051 Treated HFO Tank 052 Treated HFO Tank RAW HFO 042 Tank RAW HFO 041

8 Internal roads in site Road No.1 Road No.4 Road No.2 Road No.3

9 Unloading area position in site Unloading area

10 Tank No. Size of tank m3 Tanks Excavation Ground Compaction Backfilling and Compaction 4-10 sub base layers 1 st layer 2 nd layer 3 rd layer 4 th layer 5 th layer 6 th layer 7 th layer 8 th layer 9 th layer 41 1389.7100% 42 1389.7100% 51 516.56100% 52 516.56100% 61 854.85100% 62 854.85100% 63 854.85100% 71 1699.9100% 72 1699.9100% 73 254.19100% 81 1027.4100% 82 1027.4100% 100 1027.4100% 9040 100% Tanks foundation works progress – Excavation & sub base layers compaction

11 Tank No. Size of tank m3 Backfilling and Compaction 4-10 sub base layers 1 st layer 2 nd layer 3 rd layer 4 th layer 5 th layer 6 th layer 7 th layer 8 th layer 9 th layer 41 1389.7 42 1389.7 51 516.56 52 516.56 100% 61 854.85 62 854.85 50% 63 854.85 71 1699.9 72 1699.9 100% 73 254.19 81 1027.4 82 1027.4 100 1027.4 9040 Tanks foundation works progress –sub base layers compaction inside tanks area

12 Tanks foundation civil activities progress CuringPouring main Found. Wooden Formwork Instal. Rebar works Pouring lean concrete Achievement compaction Total Depth backfilling No. Tank 100% 1.4 m41 100% 1.4 m42 100% 1.6 m51 100% 1.6 m52 100% 1.4 m61 100% 1.4 m62 100% 1.4 m63 100% 1.4 m71 100% 1.4 m72 100% 2.03 m73 100% 1.3 m81 80%100% 1.3 m82 77%1.3 m100 100%1.3 m90

13 Compaction 1 st layer sub base for inner area of tank 62

14

15 Removing wooden formwork for foundation of tank 81

16

17

18 Wooden formwork works for foundation of tank 82

19

20

21 Building Total Depth backfilling Excavation works Compaction 4 layers sub base Casting of Lean concrete Rebar works Pouring concrete 1 st layer 2 nd layer 3 rd layer 4 th layer Administration building 1 m 100% finished 40% Canteen building 1 m 100% finished 40% Singles room building 1 m 100% finished 100% finished Electrical & control building 1 m 100% finished Fire fighting building 1 m 100% finished Buildings foundation progress

22 Pouring lean concrete layer for foundation of admin building

23

24

25

26

27 Q.C test for lean concrete layer of admin building

28

29 Pouring lean concrete layer for foundation of canteen building

30

31

32

33

34 Q.C test for lean concrete layer of canteen building

35

36 Extra excavation for foundation of E&C building

37

38

39 curing Pouring concrete Wooden formwork Rebar works Lean concrete 4 th layer sub base comp. 3rd layer sub base comp. 2nd t layer sub base comp. 1 st layer sub base comp. Sub grade comp. Excavation NO 12%100% GT21 70%100% GT22 35%100% GT23 20%87%100% GT24 Main foundation installation progress of stacks

40 Rebar works for stack foundation of GT21

41

42

43 Rebar works for stack foundation of GT22

44

45

46 Rebar works for stack foundation of GT23

47

48 Rebar works for stack foundation of GT24

49

50

51 Main foundation curing Pouring main foundation Wooden formwork installation Rebar formwork installation Pouring lean concrete 4th layer sub base compaction 3rd layer sub base compaction 2nd layer sub base compaction 1 st layer sub base compaction Subgrade compaction Excavation NO 60%100% GT21 60%100% GT22 60%100% GT23 50%100% GT24 Fin Fan coolers foundation progress

52 Compaction 4 th layer sub base for fin fan cooler foundation of GT21

53

54 Compaction 4 th layer sub base for fin fan cooler foundation of GT22

55

56 Compaction 4 th layer sub base for fin fan cooler foundation of GT23

57

58 Ground compaction works for roads achievement 100% 1.Road No. 1 achievement 100% 2.Road No. 2 achievement 100% 3.Road No. 3 achievement 100% 4.Road No. 4 achievement 100% 5.Widening roads. 6.Compaction 1 st layer for road No.1

59 Excavation for foundation of PECC & CO2 for GT21

60

61

62 Excavation for foundation of PECC & CO2 for GT23

63

64

65 Installation boundary fence 1.1 st sub base layer compaction 100% 2.2 nd sub base layer compaction 100% 3.Pouring concrete for blinding level of foundation. 4.Pouring concrete to panels of fence. 5.Extract concrete panels from steel forms.

66 Boundary fence progress

67 Installing panels at north side of fence

68

69

70

71 Installing bases at east side of fence

72

73

74 Installing columns at east side of fence

75

76

77 Mechanical works 1. Stack pre assemble Stack support shaft for GT21 (100%) Stack support shaft for GT24 (100%) Stack support shaft for GT24 - fabricating works for gangways (40%) Stack thermal shield for GT21 (1%) (hold) Application of stack support shaft for GT22 ( 60%) Application of stack support shaft for GT23 (95%) Transition duct GT21 70% Transition duct GT22 50% Transition duct GT23 50% Transition duct GT24 30% Protection duct GT21,GT22,GT23,GT24 (50%)

78 Stack Pre Assemble remarksProtection duct Transition duct Thermal shield Support shaft Stack no. 50%70%hold100%GT21 50% hold60%GT22 50% hold95%GT23 50%30%hold100%GT24

79 Welding horizontal joints for stack support shaft of GT23

80 Welding vertical joints for stack support shaft of GT22

81

82 Fabrication works for stack support shaft of GT23

83 Welding works for stack support shaft of GT23

84 Fabrication works for stack support shaft of GT22

85 Q.C test for vertical joints of stack support shaft for GT22

86 Mech. Daily Progress Report 1-Dec-12 Site:- Haydaria site Mechanical Engineering Department Date: 1-Dec-12 Mech. Daily Progress Report Arrival Time:7:00 AM Departure Time: 5:00 PM Overtime:0Hours TAEngineerForeman MCH. Technicians WELDE R laborsTotal 21301531751 Mech. Manager Signature TA ZEKI AL SAADI

87 MECHANICAL ACTIVITIES Activities Minister of Electricity Visit Store 1- Inventory of the generator accessories Unit-21 1- Transport of the exhaust frame parts 2- Installation of the extension duct 3- Preparations to install the Aux. compartment Unit-22 1- Preparations to install the extension duct Unit-23 1- Installation of the upper exhaust plenum Unit-24 1- Preparations to install the extension ducts 2- Installation of the upper exhaust plenum

88 Minister of Electricity Visit

89

90

91

92 Store

93 Inventory of the generator accessories

94

95

96 Unit 21

97 Transport of the exhaust frame parts

98

99

100 Installation of the extension duct

101

102

103 Preparations to install the Aux. compartment

104

105 Unit 22

106 Preparations to install the extension duct

107

108

109

110 Unit 23

111 Installation of the upper exhaust plenum

112

113

114

115

116

117 Unit 24

118 Preparations to install the extension ducts

119

120

121

122

123

124 Installation of the upper exhaust plenum

125

126

127 Preparation for installing generator of GT21

128

129

130

131

132

133 Preparation of installation aux. comp

134

135 Installation aux. comp for GT 24

136

137

138

139

140 Installation aux. comp for GT 23

141

142 Installation aux. comp for GT 22

143

144 Installation aux. comp for GT 21

145

146

147 Grounding grid laying for stack of GT24

148

149 Fabrication electrical service boards

150

151 Maintenance for sockets & lighting

152

153

154

155

156

157 Preparation to do the Inspection thermo shied

158

159

160 inspection and inventory for EXTENSION EXHAUST for GT23 and GT 21

161

162

163 inspection and inventory for transition duct for GT 24,21

164

165 inspection and inventory for Generators parts boxes for GT21,22,23,24

166


Download ppt "Site lay out Tanks area Building area Unloading area GT21 GT22GT23 GT24."