Site lay out Tanks area Building area Unloading area GT21 GT22GT23 GT24
2
Buildings in site E & control building Administration building Singles room building canteen
3
Buildings area in site Administration building canteen Single rooms building
4
Workshop area and internet camera Workshop area Internet camera1 Internet camera2
5
Tanks 81,82, 83 Tank No.81 Tank No.82 Tank No. 100
6
GTs area in site
7
Tanks area in site Tank LDO 071 Tank LDO 072 Tank Treated HFO 061 Tank Treated HFO 062 Tank LDO 073 Tank Treated HFO 063 Tank 051 Treated HFO Tank 052 Treated HFO Tank RAW HFO 042 Tank RAW HFO 041
8
Internal roads in site Road No.1 Road No.4 Road No.2 Road No.3
9
Unloading area position in site Unloading area
10
Tank No. Size of tank m3 Tanks Excavation Ground Compaction Backfilling and Compaction 4-10 sub base layers 1 st layer 2 nd layer 3 rd layer 4 th layer 5 th layer 6 th layer 7 th layer 8 th layer 9 th layer 41 1389.7100% 42 1389.7100% 51 516.56100% 52 516.56100% 61 854.85100% 62 854.85100% 63 854.85100% 71 1699.9100% 72 1699.9100% 73 254.19100% 81 1027.4100% 82 1027.4100% 100 1027.4100% 9040 100% Tanks foundation works progress – Excavation & sub base layers compaction
11
Tank No. Size of tank m3 Backfilling and Compaction 4-10 sub base layers 1 st layer 2 nd layer 3 rd layer 4 th layer 5 th layer 6 th layer 7 th layer 8 th layer 9 th layer 41 1389.7 42 1389.7 51 516.56 52 516.56 100% 61 854.85 62 854.85 50% 63 854.85 71 1699.9 72 1699.9 100% 73 254.19 81 1027.4 82 1027.4 100 1027.4 9040 Tanks foundation works progress –sub base layers compaction inside tanks area
12
Tanks foundation civil activities progress CuringPouring main Found. Wooden Formwork Instal. Rebar works Pouring lean concrete Achievement compaction Total Depth backfilling No. Tank 100% 1.4 m41 100% 1.4 m42 100% 1.6 m51 100% 1.6 m52 100% 1.4 m61 100% 1.4 m62 100% 1.4 m63 100% 1.4 m71 100% 1.4 m72 100% 2.03 m73 100% 1.3 m81 80%100% 1.3 m82 77%1.3 m100 100%1.3 m90
13
Compaction 1 st layer sub base for inner area of tank 62
15
Removing wooden formwork for foundation of tank 81
18
Wooden formwork works for foundation of tank 82
21
Building Total Depth backfilling Excavation works Compaction 4 layers sub base Casting of Lean concrete Rebar works Pouring concrete 1 st layer 2 nd layer 3 rd layer 4 th layer Administration building 1 m 100% finished 40% Canteen building 1 m 100% finished 40% Singles room building 1 m 100% finished 100% finished Electrical & control building 1 m 100% finished Fire fighting building 1 m 100% finished Buildings foundation progress
22
Pouring lean concrete layer for foundation of admin building
27
Q.C test for lean concrete layer of admin building
29
Pouring lean concrete layer for foundation of canteen building
34
Q.C test for lean concrete layer of canteen building
36
Extra excavation for foundation of E&C building
39
curing Pouring concrete Wooden formwork Rebar works Lean concrete 4 th layer sub base comp. 3rd layer sub base comp. 2nd t layer sub base comp. 1 st layer sub base comp. Sub grade comp. Excavation NO 12%100% GT21 70%100% GT22 35%100% GT23 20%87%100% GT24 Main foundation installation progress of stacks
40
Rebar works for stack foundation of GT21
43
Rebar works for stack foundation of GT22
46
Rebar works for stack foundation of GT23
48
Rebar works for stack foundation of GT24
51
Main foundation curing Pouring main foundation Wooden formwork installation Rebar formwork installation Pouring lean concrete 4th layer sub base compaction 3rd layer sub base compaction 2nd layer sub base compaction 1 st layer sub base compaction Subgrade compaction Excavation NO 60%100% GT21 60%100% GT22 60%100% GT23 50%100% GT24 Fin Fan coolers foundation progress
52
Compaction 4 th layer sub base for fin fan cooler foundation of GT21
54
Compaction 4 th layer sub base for fin fan cooler foundation of GT22
56
Compaction 4 th layer sub base for fin fan cooler foundation of GT23
58
Ground compaction works for roads achievement 100% 1.Road No. 1 achievement 100% 2.Road No. 2 achievement 100% 3.Road No. 3 achievement 100% 4.Road No. 4 achievement 100% 5.Widening roads. 6.Compaction 1 st layer for road No.1
59
Excavation for foundation of PECC & CO2 for GT21
62
Excavation for foundation of PECC & CO2 for GT23
65
Installation boundary fence 1.1 st sub base layer compaction 100% 2.2 nd sub base layer compaction 100% 3.Pouring concrete for blinding level of foundation. 4.Pouring concrete to panels of fence. 5.Extract concrete panels from steel forms.
66
Boundary fence progress
67
Installing panels at north side of fence
71
Installing bases at east side of fence
74
Installing columns at east side of fence
77
Mechanical works 1. Stack pre assemble Stack support shaft for GT21 (100%) Stack support shaft for GT24 (100%) Stack support shaft for GT24 - fabricating works for gangways (40%) Stack thermal shield for GT21 (1%) (hold) Application of stack support shaft for GT22 ( 60%) Application of stack support shaft for GT23 (95%) Transition duct GT21 70% Transition duct GT22 50% Transition duct GT23 50% Transition duct GT24 30% Protection duct GT21,GT22,GT23,GT24 (50%)
78
Stack Pre Assemble remarksProtection duct Transition duct Thermal shield Support shaft Stack no. 50%70%hold100%GT21 50% hold60%GT22 50% hold95%GT23 50%30%hold100%GT24
79
Welding horizontal joints for stack support shaft of GT23
80
Welding vertical joints for stack support shaft of GT22
82
Fabrication works for stack support shaft of GT23
83
Welding works for stack support shaft of GT23
84
Fabrication works for stack support shaft of GT22
85
Q.C test for vertical joints of stack support shaft for GT22
86
Mech. Daily Progress Report 1-Dec-12 Site:- Haydaria site Mechanical Engineering Department Date: 1-Dec-12 Mech. Daily Progress Report Arrival Time:7:00 AM Departure Time: 5:00 PM Overtime:0Hours TAEngineerForeman MCH. Technicians WELDE R laborsTotal 21301531751 Mech. Manager Signature TA ZEKI AL SAADI
87
MECHANICAL ACTIVITIES Activities Minister of Electricity Visit Store 1- Inventory of the generator accessories Unit-21 1- Transport of the exhaust frame parts 2- Installation of the extension duct 3- Preparations to install the Aux. compartment Unit-22 1- Preparations to install the extension duct Unit-23 1- Installation of the upper exhaust plenum Unit-24 1- Preparations to install the extension ducts 2- Installation of the upper exhaust plenum
88
Minister of Electricity Visit
92
Store
93
Inventory of the generator accessories
96
Unit 21
97
Transport of the exhaust frame parts
100
Installation of the extension duct
103
Preparations to install the Aux. compartment
105
Unit 22
106
Preparations to install the extension duct
110
Unit 23
111
Installation of the upper exhaust plenum
117
Unit 24
118
Preparations to install the extension ducts
124
Installation of the upper exhaust plenum
127
Preparation for installing generator of GT21
133
Preparation of installation aux. comp
135
Installation aux. comp for GT 24
140
Installation aux. comp for GT 23
142
Installation aux. comp for GT 22
144
Installation aux. comp for GT 21
147
Grounding grid laying for stack of GT24
149
Fabrication electrical service boards
151
Maintenance for sockets & lighting
157
Preparation to do the Inspection thermo shied
160
inspection and inventory for EXTENSION EXHAUST for GT23 and GT 21
163
inspection and inventory for transition duct for GT 24,21
165
inspection and inventory for Generators parts boxes for GT21,22,23,24