March 2014.  Finish Joint Sealing on Highlands Ranch Parkway  Finish Grinding on Lucent and Plaza and then Complete Joint Sealing  Start in Late.

Similar presentations


Presentation on theme: "March 2014.  Finish Joint Sealing on Highlands Ranch Parkway  Finish Grinding on Lucent and Plaza and then Complete Joint Sealing  Start in Late."— Presentation transcript:

1 March 2014

2

3  Finish Joint Sealing on Highlands Ranch Parkway  Finish Grinding on Lucent and Plaza and then Complete Joint Sealing  Start in Late Spring

4  Major Replacement on Broadway and Plaza Dr  Grinding Has Improved Ride Quality

5 Traffic Control on Arterials was Big Issue

6  Completed Broadway/C470 improvements  Completed 2 nd Phase on Quebec/University/Lincoln Intersection

7  Over $14M on concrete repair and maintenance (ACPA Award Winner)  Over $4M on asphalt maintenance  Over $6M on capital projects

8

9 --- Arterial Repairs --- Cape seals --- Overlays

10  Concrete Remove and Replace Contract – Shorter work zones - Break up arterials into segments - Night work in Commercial Areas  Grinding and Sealing Contract - Moving work zones – Instead of work zone being set up all day and overnight, they will close ahead and open behind as work moves down roadway

11  Curb, Gutter and Sidewalk Repair and Ramp Replacement

12

13  Complete 2013 Grinding/Sealing – April  Arterial Concrete Work – May  Residential Street Surface Treatments –June  Residential Street Overlays – June  Arterial Concrete Grinding – Late July