Mike Andrews January 31, 2012. Weeks 19-25 Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.

Similar presentations


Presentation on theme: "Mike Andrews January 31, 2012. Weeks 19-25 Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil."— Presentation transcript:

1 Mike Andrews January 31, 2012

2 Weeks 19-25 Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil Refill with glycol, test, start coil system Horn 2 RAW Upgrades in Chase Fabricate flex lines on 1.5 ejector pump supply line Fabricate 1” spray supply lines Align & install piping in chase Absorber RAW Upgrade for Exchange System Install flow meters, sampling ports, filtration system Piping for DI & exchange systems Install 3” Dbl Walled PVC Drain Line in Absorber Passageway

3 Weeks 19-25 Activities Absorber Intermediate RAW Upgrade Weld in thermo wells & install flow meter Install piping mods for exchange system Install 1” PVC Drain Line in Absorber Passageway Install five DI bottle casks in new DI Room Install piping hardware Terminate new controls cabling for MI65 RAW skids Target RAW Drain Piping outside of chase

4 Weeks 19-25 Activities NoVA Horn 2 Relocation Install Air Dam of LE Horn 2 location Install stripline extension Survey, install, & grout in stands Install tap conductor assembly Install chase stripline assemblies Install remainder of ME west battlement Pour custom concrete blocks in ME west battlement Install grout around piping for custom blocks Extend Horn 2 instrumentation cables to ME location Replace hardware on existing walkway stripline section

5 Horn 2 LE Air Dam

6 DI Cask Installation

7 Horn 2 ME West Battlement

8 Horn 2 Stripline & RAW Upgrade

9 TP Fan Coil Piping

10 Weeks 26-30 Activities Complete PVC drain piping in Absorber Passageway including fill station Fabricate, test, install 1.5 & 2” ball valve seals on RAW skids Install new heat exchangers on Horn 1, Horn 2, & Decay Pipe RAW skids Pressure test Absorber/Decay Pipe RAW & Absorber Intermediate drain piping Decay Pipe RAW System Upgrades Drain 800 gallons of water (17) barrels Install new flow meters and thermo wells

11 Weeks 26-30 Activities NoVA Horn 1 pulse testing at MI-8 (100,000 pulses) Complete NoVA Target DS Hanger flow testing Complete radiography on RAW piping welds in RAW Room, Target Hall, & Absorber Hall Complete vibration testing on NoVA Horn 1 Repair electrical & mechanical support room floor Complete terminating new controls cabling to RAW skids & cooling coil Complete installation of DI cask hardware

12 RAW Skid Valve Seal Replacement

13 NoVA Target & Horn 1 Testing

14 DI Cask Installation

15 Absorber RAW Fill Station

16 Weeks 31-35 Activities Fabricate, Test, Install 1”, ¾” & 3” ball valve seals on RAW Skids Install New Profile Monitors 108 & 112 in NuMI Stub Contine re-work on Target DS Hanger Continue Outfitting of NoVA Horn 1 Attach water tank Complete under drain treatment for calcium deposits New Hadron Monitor delivered from UTexas Complete leak testing of midstream section of NuMI Beamline

17 Weeks 31-35 Activities Target Beryllium Window Investigation & Repair Complete leak testing of Target Beryllium Window Visually inspect window with camera Remove OTR, multiwire, BPM, toroid, & vacuum tee spool Borescope titanium window inside vacuum tube Remove vacuum tube with beryllium window Complete leak testing & hands on visual inspect Complete RGA testing of beryllium window Conduct analysis of beryllium present window design & modifications

18 MI Profile Monitors 108 & 112

19 DS Beamline & Beryllium Window

20 Titanium Window

21 Target Beryllium Window Removal

22 Beryllium Window Inspection

23 Weeks 36-40 Activities Complete installation 3” ball valve seals on RAW Skids Complete NoVA Horn 1 ready for installation Complete work on NoVA Target except for installation of Hylen device Install profile monitors 114, 115, 117 in NuMI carrier region Complete leak testing of NuMI upstream beamline Dry set all Target Pile R-blocks Clean stripline area along west walkway All hardware on Target Hall stripline visually inspected, tightened, and QA inspected

24 Weeks 36-40 Activities Remove stripline jumper between pulse power & stripline Complete hi-pot testing of Target Hall stripline Install protective cage for Target Hall stripline Complete hydrostatic test of Target, Horn 1 & Horn 2 Raw skids Complete cable pulls from surface to PT for LBNE BPM Drill three hydrostatic relief holes in east wall of Target Hall Install controls for MI65 RAW exchange skid Move Hadron Monitor 1 from AH coffin to TSB Install remote handling equipment for hadron monitor 2 replacement Install spool piece in 121 section of NuMI beamline for LBNE BPM

25 Target & Horn 1

26 MI65 RAW Exchange Skid

27 Target Hall Stripline Inspection

28 Target Hall Configuation

29 Path through April 26th Install stripline protective fence (1/23 - 2/6) Install new hadron monitor (2/4 – 2/15) Install Horn 2 stripline jumper (Wk. 2/4) Hydrostatic testing of Target, Horn 1, Horn 2 RAW (1/28 – 2/8) Install RAW exchange system in MI65 in DI room (2/11- 2/22) Connect & commission Horn 2 RAW system (Wk. 2/4) Remove Target & Horn 1 old water & instrumentation lines (Wk. 2/4) Install Target Hall rail system (Wk. 2/4) Remove old Horn 1 stripline block to morgue (Wk. 2/4) Install new Horn 2 stripline block (Wk. 2/4) Move Horn 1 into Target Hall work cell (Wk. 2/4) Install Horn 1 into chase (2/11-2/22) Dry set R-blocks over Horn 1 (Wk. 2/25)

30 Path through April 26th Complete hydrostatic testing of Absorber RAW, Intermediate, &Decay Pipe piping (Wk. 2/11) Fill & commission Abs RAW & Intermediate skids (Wk. 2/18) Dry set R-blocks over Horn 1 (Wk. 2/25) Seal R- blocks between Horn 1 & Horn 2 (Wk. 3/4) Install Target beryllium window assembly Wk. (3/11) Beryllium window with gold coating being fabricated off-site Titanium window (catcher) in hand Fabricate Beryllium window assembly (2/18 – 3/8) Re-assemble downstream beamline (Wk. 3/11) Connect hardon monitor cabling & commision(Wk. 3/11) Install new Target profile monitors (Wk. 3/18) Install LBNE BPM prototype in beamline (Wk. 3/18)

31 Path through April 26th Install muon monitor in Alcove 4 (Wk. 3/18) Install LBNE muon monitor in Alcove 2 (3/18 – 4/19) Complete pulse testing at new rep rate & thermal imaging of stripline & Horns (Wk. 4/1) Test Power supplies (Wk. 4/1) Fill Decay Pipe RAW system (800 Gallons) from LCW system & commission (Wk. 4/1) Install Target into chase (4/1 – 4/12) Complete dehumidifier PM’s (Wk. 4/15) Prep Target Hall & Absorber Hall for beam scans (4/15- 4/26)


Download ppt "Mike Andrews January 31, 2012. Weeks 19-25 Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil."