Download presentation
Presentation is loading. Please wait.
Published byLesley Miller Modified over 8 years ago
1
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014
2
PIP Report F.G. Garcia AEM - PIP Report 10/06/2014 Ongoing Complete 3 L2 tasks 9 L3 tasks 31 L4 tasks 30% Linac 70% Booster
3
Linac
4
Modulator Upgrade 35kV, Marx-topology modulator Progress made on various fronts Enclosure design complete and near delivery Gate driver circuit board design/layout done Short circuit testing continues Successful design and tests, with available end-of-year funds procure the long-lead items for the full voltage modulator PIP - Linac 200 MHz RF Power System F.G. Garcia AEM - PIP Report 10/06/2014 HLRF – SBK201 Successful CDR review early July Focus now shifted to drafting & purchase of long-lead items
5
PIP - Linac Accelerator Physics Laser Notch Internal review carried out early August Readiness for vacuum cavity / optical cavity installation during shutdown F.G. Garcia AEM - PIP Report 10/06/2014 Laser port Assembly at lab area Assembly installed RIL beam
6
PIP - Linac Utilities Power distribution (Dec’11-Sept’14) L1 transformer fully installed 13.8kV to 480Y/277V Better heat loss (80C vs 115C) Low voltage breakers, trip control and instr. What will become of the removed equipment? Transformer will be kept as spare for Linac additional 2 other old-style transformers in use Breakers & primary switch will be rebuilt and tested – spares L4 task complete! F.G. Garcia AEM - PIP Report 10/06/2014 July’14 Sept 17 ‘14 Sept 24 ‘14 Original L1 sub-station
7
PIP - Linac Utilities LCW system Dual temp. system Replace cooling provided by EOL DTW piping and fan coil units to a rooftop AC unit Contract awarded and pre-meeting conducted Gallery work starts Oct10 th CUB 55 LCW backup pump Extensive delay Overran in costs forced the project to be restructure to a FP rather T&M Process complete in time for the shutdown Job still has not started! Vacuum upgrade Turbo pumps (shutdown’14) Original pumps in service since day-one Belt driven / oil reservoir Heavy, big, replacement parts no longer available New pumps are sealed clean bearings, compact, high speed, freq. drive control L4 task complete! F.G. Garcia AEM - PIP Report 10/06/2014
8
Booster
9
PIP - Booster RF Anode & Bias Supplies Anode Supplies Goal: install both supplies during shutdown 2014 Delays in the delivery of long lead items prevented this task to be complete AD/EE continue to make progress with assembly Supplies may be built but not tested by the end of the shutdown Await for opportunistic shutdown next year to install F.G. Garcia AEM - PIP Report 10/06/2014 Bias Supplies Scope of work: Replace transformers, re-plumbing and re-wiring for 15 Hz operation Current Situation East gallery: 100% complete West gallery: 10% complete
10
PIP - Booster RF Cavity & Tuner Refurbishment Work progressing well with the cavity refurbishment Scope of work: refurbish all 19 cavities in Booster Up to now, 11 cavities fully refurbished and re-installed in tunnel Additional cavity (#20) installed prior the shutdown Cavity built from leftover parts F.G. Garcia AEM - PIP Report 10/06/2014 Current Situation Cones are bottleneck Time consuming to rework a used cone 10 step process
11
PIP - Booster Notch system Scope of Work: Reconfigure and replace notch kickers & corresponding high voltage system for faster rise/fall time F.G. Garcia AEM - PIP Report 10/06/2014 Short kickers beam 3 bucket notch Current Situation Complete installation of 6 “short” kicker magnets & corresponding high voltage system redesigned S12 spool piece improve aperture at downstream of notch kickers (~10%) standard Booster BPM’s pickup plates proved to be aperture restriction
12
PIP - Booster Radiation Shielding Scope of Work: Revised Booster shielding assessment to allow high intensity operations. Present SAD allows for 1.8E17 p/hr Above ground radiation protection Practical limit determined by the array of detectors spread around the ring 50+ interlocked detectors placed above ground at specific locations covering all loss points Tunnel radiation protection Overall loss rate limited by the “watt meter” – 525W & Local control loss possible with array of 60+ BLMs along the tunnel During the shutdown, 8 TLM’s installed in Booster tunnel High loss points: Injection, extraction, collimator, notch regions Beam tests to characterize system F.G. Garcia AEM - PIP Report 10/06/2014
13
PIP - Booster Utilities Power distribution Transformers First transformer replaced 09/27 (west side) Problems with the breaker will prevent the installation on the east side this shutdown F.G. Garcia AEM - PIP Report 10/06/2014 Vacuum upgrades Turbo pumps All pumps on-hand Auxiliary cables and relay rack work moving along Pump installation progressing well Unlikely to complete this shutdown BWG - transformer
14
PIP PIP-II adjustments F.G. Garcia AEM - PIP Report 10/06/2014 Meetings and discussions began to adjust PIP to PIP-II
15
PIP - Conclusions PIP continues to make positive progress towards its goals Linac Lots of progress made on the 200 MHz RF system First step completion of R&D project to create a notch within linac beam pulse using laser system Completion of two L4 tasks during shutdown 2014 Vacuum system Power Distribution Booster >50% cavities refurbishment complete Complete installation of BW house transformer Setup complete for TLM’s beam tests run Complete installation of short kicker magnets for notch creation PIP plan adjustments for PIP-II Discussions started between PIP and PIP-II to redirect and modify existing PIP activities to line up with PIP-II program F.G. Garcia AEM - PIP Report 10/06/2014
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.