1 2010 Environmental Change Orders

2 Tom Harris, PE Field Engineer Division of Construction Management

3 INDOT had a total of $70,555,380 in change orders approved in 2010. Of those a total of $2,831,093 for environment causes Of all of the Change Orders in 2010 4.01% were for environment reasons.

4 Common Environmental reasons for Change Orders Underground Storage Tanks Standard Spec 202.08 and 202.09 spell out requirements for removal and closure of the tank.

5

6 Total of $821,867 17 projects found unknown tanks About 30 tanks were found

7 IDEM/INDOT OES Request Total of $124,458.14 in 2010 Change Orders. 4.40% of all environment CO’s 0.18% of all CO’s in 2010 7 contracts total

8 Added Erosion and Sediment Control Total of $185,051 24 contracts Average cost of $7,710 added to each contract.

9

10 BMP’s Left out of plans 15 contracts had BMP’s included in approved plans but did not make it into the contract set of plans. Change Orders to correct this added $181,477 to 15 contracts.

11 Not counting the 2 largest Change Orders for BMP’s that were not in the plans, the average cost to add into the contract was $5,188

12 Added Wetland Mitigation 2 contracts had wetland mitigation added totaling about 2 AC. Averaged $108,439 Caused by changed criteria on Wetland Definition

13 Asbestos Asbestos found in 8 projects Total cost of $92,927 Standard Specification 202.07, also see 326 IAC Ave cost to mitigate was $11,616

14 Hazardous Bridge Coatings 3 projects in 2010 Cost $212,469 Formula in Standard Specification section 619.18

15 What was found: Most change orders were for work that should or could have been in the original contract.

16 Permits $329,305 resulted from INDOT being notified that we had specific permit requirements that were not followed in the plans or in the special provisions.

17 $2.8 million out of $70.55 million is low percentage overall, about 4.0%.

18 Additional work required by IDEM/INDOT OES inspections amounted to $124,650 on 7 different contracts.

19 Overruns and work added by project personnel amounted to $185,051 on 24 contracts.

20 UST, Asbestos, Hazardous Material found on bridges cost $1,127,262 INDOT obligated to mitigate and Standard Specifications provide means to compensate contractor

21 Tom Harris, PE Field Engineer Division of Construction Management