Download presentation
Presentation is loading. Please wait.
Published byBuddy Barrett Modified over 8 years ago
1
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November 12-13, 2007
2
Topics Accelerator Cost –Methodology –Listed activities PEP-II Components –Types of items –Availability Construction Schedule –Planning
3
November 12-13, 2007 Tor Vergata Site (from F. Forti)
4
November 12-13, 2007 Ring Layout (from F. Forti) SuperB Ring (about 1800m) SPARX Roman Villa 100m SuperB Injector (about 400m) SuperB Main Building
5
November 12-13, 2007 Super-B Parameters
6
November 12-13, 2007 KEKBSuperB current1.7 A2.3 A betay6 mm0.3 mm betax300 mm20 mm sigmax~80 m~6 m sigma y~3 m0,035 m Sigma z6 mm L1.7 10 34 1 10 36 Beams are focused in the vertical plane 100 times more than in the present factories, thanks to: - small emittances - small beta functions - large crossing angle - Crab waist Tune shifts and longitudinal overlap greatly reduced SuperB Beams distributions at the IP KEKB Beams distributions at the IP Higher Luminosity from smaller beam sizes
7
November 12-13, 2007 Accelerator status SBF accelerator layout has converged and been defined. Site constraints suggest 1650 m + polarization component length for a total of 1800 m. A luminosity of 1x10 36 with longitudinal polarization of one beam at the interaction point is the primary goal. Overall parameters have a x4 luminosity growth potential to the 4x10 36 level. Many of the systems use existing components or component designs. Interaction region has new features. Most of the future design work will be concentrated there.
8
November 12-13, 2007 Costing Methodology Identified all needed accelerator components. Bottoms up cost evaluation from existing designs for new components. Scaled costs of shipping components from PEP-II accelerator from present experience. Reuse and refurbishment costs escalated from construction costs in 1995 to 2007 Euros. Detailed work breakdown structure used. The cost estimate for the Conceptual Design Report CDR has not yet received a level of scrutiny needed for the Technical Design Report TDR.
9
November 12-13, 2007 Cost Breakdown Items EDIA –Engineering, Design, Inspection, Acceptance Labor –Person hours which could (likely) be done at an existing laboratory M&S –Work and parts that could be purchased from industry or a laboratory as needed. Replacement value: Reuse/Refurbishment –Replacement costs of PEP-II components if built in 2007
10
November 12-13, 2007 “Accelerator Components” Project management Magnets –(dipoles, quadrupoles, sextupoles, kickers) Mechanical supports Interaction region Water systems Vacuum systems RF system (klystron, cavities, waveguide, controls) Controls and instrumentation Polarization manipulation Injection –(source, linac, damping rings, septa, injection lines)
11
November 12-13, 2007 Activities Estimated for each Component Engineering, design and prototyping Remove and refurbish Construction Shipping Power supplies Water cooling connection Supports Alignment Installation
12
November 12-13, 2007
13
Interaction Region +
14
November 12-13, 2007 Summary of Expected Accelerator Costs (2250 m) WBSAcceleratorEDIALaborM&SRep. Value (mm) (kEuro) 1.Totals54293497191166126330 1.1Project Managem’t21129618000 1.2Magnets/supports66611992896525380 1.3Vacuum6205202760014200 1.4RF system2723042230060000 1.5IR370478109500 1.6Controls/Diag.963648129518750 1.7Injection4262528660018000
15
November 12-13, 2007 Summary of Costs of Tunnels and Utilities (2250 m) WBSSite/UtilitiesEDIALaborM&SRep. Value (mm) (kEuro) 2Totals142416601057000 2.1Site Utilities8201040317000 2.2Tunnel & Support buildings 604620740000 (See F. Forti’s talk)
16
November 12-13, 2007 Polarization Components in the Estimate The following items are included in the Super-B cost estimate: –Polarization magnets in the IR –Polarization vacuum chambers –Polarization diagnostics –Injector polarization manipulation hardware –Refurbished polarized gun from SLAC The total effort is about: –Labor = 140 man-months –New M&S = 5 MEuros –Replacement value of reused parts = 2 MEuros
17
November 12-13, 2007 Savings for Ring Size Reduction from 2250m (CDR) to 1800 m (Tor Vergata site) Costs are lower with reduce ring sizes. Costs do not scale directly as the ring “Arcs” are the same length, just the straight sections are shorter and fewer. Injector is the same cost. Power related costs are the same as the power remains roughly the same. Initial look at cost savings for accelerator and site/utilities: –Labor: -400 man months –M&S: -35 MEuros –Replacement : -3 MEuros
18
November 12-13, 2007 Available Components from the PEP-II B Factory at SLAC Located at the Stanford Linear Accelerator Center
19
November 12-13, 2007 PEP-II Components and Beam Lines HER = 2200 m LER = 2200 m HER injection line = 2300 m LER injection line = 2900 m Damping rings = 2 x 33 m Total length of beam line = 9600 m –( 6.0 miles)
20
November 12-13, 2007 PEP-II Arc Section Usable PEP-II components for Super-B Magnets (Over 1500) Vacuum chambers (4400 m) RF systems (15 stations, 28 cavities) Power supplies Bunch-by-bunch feedback systems Diagnostics Instruments Injection septa and kickers Supports
21
November 12-13, 2007 Dipoles Summary L mag (m)0.455.4 PEP HER-194 PEP LER194- SBF HER-130 SBF LER22418 SBF Total224148 Needed300 130 (112 in Arcs+18 in FF) “PEP-II HER” dipoles are used in SuperB HER 18 dipoles are used in FF for SuperB LER 224 “PEP-II LER” dipoles are used in SuperB LER need to build 30 new ones SuperB magnet list M. Biagini
22
November 12-13, 2007 Quadrupoles Summary L mag (m)0.560.730.430.70.4 PEP HER20282--- PEP LER--353-- SBF HER165108-22 SBF LER8810816522 SBF Total25321616544 Needed51134044 M. Biagini
23
November 12-13, 2007 B-Factory RF Klystrons C. Pearson
24
November 12-13, 2007 PEP-II RF Cavities
25
November 12-13, 2007 PEP-II injection system in Linac Linac LER injection line HER Injection Line
26
November 12-13, 2007 Availability of PEP-II Components PEP-II will shut down September 2008. Many of the parts will be available for other projects. SLAC staff is in the middle of a study for long range science projects (~20 years). There are several future possibilities for PEP-II components and tunnel: –Contribute components to Super-B. –Install new LCLS undulator in the PEP-II tunnel. –Make a moderate ring light source (use one ring only-HER). –Make a state-of-the-art light source (one ring with mostly new parts). No decisions on light sources will be made soon.
27
November 12-13, 2007 Schedule Inputs (CDR) for Super-B Accelerator Included calendar time to: Do initial engineering. Prepare site, bore tunnels, build buildings. Ship components from SLAC to Italy. Install components for two rings. Construction time for injector. Commission the injector and two rings. Both KEKB and PEP-II were built in 4 years. SBF schedule came in at about five years with the new tunnel and injector.
28
November 12-13, 2007 SBF CDR Schedule of events
29
November 12-13, 2007 Condensed Summary of Yearly Activities Year 0: –Agency work –Engineering –Environmental studies Year 1: –Start boring tunnels –Start erecting buildings –Start building IR hall –Refurbish components –Start constructing new accelerator components Year 2: –Finish over half of civil construction –Construct new components –Ship refurbished components –Buy power supplies and controls Year 3: –Ship refurbished components –Finish constructing parts –Start installation Year 4: –Finish installation –Start and finish linac commissioning –Start commissioning rings
30
November 12-13, 2007 Conclusions Super-B Accelerator layout has been defined and an initial cost estimate made. –All components have been included. Accelerator costs have been estimated using past experience. –Escalation (then year costs) and contingency have not been added. A reasonable schedule has been made which is consistent with the construction times of PEP-II and KEKB.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.