TOWER A Bldg. As of July 21,2009 SCHEDULED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67% SUMMARY OF ACCOMPLISHMENTS PROJECT DURATION.

Similar presentations


Presentation on theme: "TOWER A Bldg. As of July 21,2009 SCHEDULED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67% SUMMARY OF ACCOMPLISHMENTS PROJECT DURATION."— Presentation transcript:

1

2 TOWER A Bldg.

3 As of July 21,2009 SCHEDULED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67% SUMMARY OF ACCOMPLISHMENTS PROJECT DURATION 423 Calendar Days NUMBER OF DAYS LAPSED191 Calendar Days NUMBER OF DAYS REMAINING248 Calendar Days PROJECTED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67%

4 GROUND FLR RIGHT WING AREAGROUND FLR. LEFT WING AREA RETOUCHING AND FINISHING

5 2 nd FLOOR LEVEL LEFT WING AREA 2 nd FLOOR LEVEL RIGHT WING AREA RETOUCHING AND FINISHING

6 3 rd FLOOR LEVEL RIGHT WING AREA3 rd FLOOR LEVEL LEFT WING AREA RETOUCHING AND FINISHING

7 4 th FLOOR RIGHT WING AREA4 th FLOOR LEFT WING AREA RETOUCHING AND FINISHING, PILING OF CHB 4” AND 6”

8 5 th FLOOR LEFT WING AREA 5 th FLOOR RIGHT WING AREA, PILING OF CHB 4” AND 6”

9 6 th FLR. LEFT WING AREA: 6 th FLR. RIGHT WING AREA CLEARING OF FORMWORKS

10 7 th FLR. RIGHT WING AREA7 th FLR. LEFT WING AREA CLEARING OF FORMWORKS

11 8 TH FLR. LEFT WING AREA8 TH FLR. RIGHT WING AREA CLEARING OF FORMWORKS

12 9 TH FLR. LEFT WING AREA 9 TH FLR. RIGHT WING AREA SHORING AND FORMWORKS FOR 10 TH FLOOR

13 10 TH FLR. LEFT WING AREA: CONCRETED SUSPENDED SLAB 10 TH FLR. RIGHT WING AREA: FORMWORKS FOR SLAB AND ROUGHING- INS


Download ppt "TOWER A Bldg. As of July 21,2009 SCHEDULED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67% SUMMARY OF ACCOMPLISHMENTS PROJECT DURATION."