TOWER A Bldg.
3
As of July 21,2009 SCHEDULED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67% SUMMARY OF ACCOMPLISHMENTS PROJECT DURATION 423 Calendar Days NUMBER OF DAYS LAPSED191 Calendar Days NUMBER OF DAYS REMAINING248 Calendar Days PROJECTED ACCOMPLISHMENT21.79% ACTUAL ACCOMPLISHMENT29.46% VARIANCE+7.67%
4
GROUND FLR RIGHT WING AREAGROUND FLR. LEFT WING AREA RETOUCHING AND FINISHING
5
2 nd FLOOR LEVEL LEFT WING AREA 2 nd FLOOR LEVEL RIGHT WING AREA RETOUCHING AND FINISHING
6
3 rd FLOOR LEVEL RIGHT WING AREA3 rd FLOOR LEVEL LEFT WING AREA RETOUCHING AND FINISHING
7
4 th FLOOR RIGHT WING AREA4 th FLOOR LEFT WING AREA RETOUCHING AND FINISHING, PILING OF CHB 4” AND 6”
8
5 th FLOOR LEFT WING AREA 5 th FLOOR RIGHT WING AREA, PILING OF CHB 4” AND 6”
9
6 th FLR. LEFT WING AREA: 6 th FLR. RIGHT WING AREA CLEARING OF FORMWORKS
10
7 th FLR. RIGHT WING AREA7 th FLR. LEFT WING AREA CLEARING OF FORMWORKS
11
8 TH FLR. LEFT WING AREA8 TH FLR. RIGHT WING AREA CLEARING OF FORMWORKS
12
9 TH FLR. LEFT WING AREA 9 TH FLR. RIGHT WING AREA SHORING AND FORMWORKS FOR 10 TH FLOOR
13
10 TH FLR. LEFT WING AREA: CONCRETED SUSPENDED SLAB 10 TH FLR. RIGHT WING AREA: FORMWORKS FOR SLAB AND ROUGHING- INS