Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 LHCb - Install Meeting 24/05/06 TS/CV/DC activities for LHCb: - IT, TT, OT & SPD/PS, RICH 1 & 2 Detectors cooling machines -VELO CO2 transfer lines -MUON ventilation units STATUS - PLANNING
2
Cooling machines production Inner Tracker / Tracker Trigger Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 -test at Contractor’s premises partially failing: heat intake from pumps engines exceeding expectations, new exchangers and compressors needed to be installed modifications performed -new tests to be done on site to validate thermal performances -connection to transfer lines, water and air networks, backup chiller, cabling, construction of retention bund, connection to waste water done -powering done by TS/EL -filling up with C6F14 concluded -backup chiller installed and cabled -electric and control cubicle tested, functionalities checked, XBT control panel verified, few minor modifications demanded NEXT STEPPerformance test with dummy load on the stations only
3
Cooling machines production OT/SPD/PS - RICHes stations Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 -performance tests at Contractor’s premises simulating heat charge and impedance satisfactory -connection to transfer lines, water and air networks, backup chiller, cabling, construction of retention bunds, connection to waste water done -powering done by TS/EL -filling up with C6F14 for RICH concluded -refill line from demineralised water network done Thanks to Sylvain and DBS team for stations and tanks handling NEXT STEPComplete test on the cooling loop
4
COMMISSIONING strategy Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 Pre-acceptance: - Test with dummy load on IT/TT Final acceptance : - Hydraulic test on detector cooling loops Final commissioning worth to be perfomed individually for each cooling station at the presence of the company agreement ongoing
5
-provisional acceptance on the four machines will start as the corresponding percentage over global contractual amount defined [two days for RICH and OT, five for IT and TT] -final request shall be sent at the soonest to INEO ALPES containing a likely date for commissioning on detector cooling lines -inner cooling loops shall be previously pressure and leak tested Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 COMMISSIONING strategy
6
VELO CO2 transfer lines Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 -Concentrical lines installed, pneumatic pressure test [125 bar] and helium leak test [10-7 mbar l/s] successfully performed, insulation partially installed -Modification to be evaluated with LHCb, agreed and planned with SIMIND
7
MUON ventilation units Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 List of material [orders out, latest delivery in about 1 month]~ 45 kCHF -Flexible hoses AIRSPIR PUR polyurethane polyether transparent, DI 30 mm -Blowers ELEKTROR [2 x 6.5 kW, 2 x 10.5 kW] 280 mbar outlet pressure -Distribution manifolds brazed copper 8 spurs -Post coolers 5410 kW for mixed water connection [12.9 l/min each] -Accessories [thermoswitch, pressoswitch, reductions, …] control [via DSS] strategy to be discussed