Presentation is loading. Please wait.

Presentation is loading. Please wait.

Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status.

Similar presentations


Presentation on theme: "Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status."— Presentation transcript:

1 Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status

2 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 Summary: Where we stand 2 A1-A3Installed, cabled, read-out in technical run A4-A8Installed, ready for cabling A11At CERN, ready to install A9 & A10 Vessels under construction at Fantini Bananas under construction at Frascati No real changes from last meeting

3 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 Cabling and operations in ECN3 3 A1-A3 cabling Full test of signals from all installed detectors Threshold scan in situ? Adjustments to rack cabling A1-A3 Move HV crate upwards in rack Protection for cables protruding from front of rack Cable A4-A5 a la A1-A3 Develop cable routing for A6-A8 To be done this spring

4 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 A9-A10: Status of vessels 4 Progress on A9: End flanges welded before winter shutdown Recently finished first turning on vertical lathe Progress on A10: Vessel welded and weld tested End flanges straightened on lathe – planarity checked Progress in parallel (A9 and A10): DN200 nozzles complete and ready to be welded DN630 manholes lathed and ready for final work on milling machine DN100 nozzles lathed Work on support structures in progress: Carpentry and foot plates ready Ready to begin working pieces in Bronal (threaded rods, foot cups)

5 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 Work in progress at Fantini 5 A9 lathingA10 vessel welding and weld testDN200 nozzle on lathe

6 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 Work in progress at Fantini 6 DN200 nozzles Support structures DN630 manhole

7 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 Work in progress in Frascati 7 A9: 60 of 60 bananas ready A10: 27 of 60 bananas ready 49 blocks ready (→ 12 bananas)

8 LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 05 February 2013 Conclusions 8 Still expect A9 vessel to be delivered week of 11 March 2013 A9 banana assembly complete A10 banana assembly will be complete before A10 delivered


Download ppt "Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 5 January 2013 LAV construction & installation status."

Similar presentations


Ads by Google