Download presentation
1
HYDROGRAPH ANALYSIS Topic 4 NATURAL HYDROGRAPH
Base flow separation technique, Qb: a. Empirical formula b. Master depletion curve c. Simple straight lines Topic 4 HYDROGRAPH ANALYSIS EXPLAIN CONCEPT OF UNIT HYDROGRAPH CONSTRUCT UNIT HYDROGRAPH CALCULATE Volume Of Direct Runoff From Direct Runoff Hydrograph. DETERMINE The Change Of Unit Hydrograph Duration Using: a. S-curve b. Superposition Concept.
2
HYDROGRAPH A hydrograph is a graph showing the rate of flow (discharge) versus time past a specific point in a river, or other channel or conduit carrying flow. The rate of flow is typically expressed in cubic meters or cubic feet per second (cms or cfs).
3
DEFINITION OF NATURAL HYDROGRAPH
A natural hydrograph is one recorded at a stream gauging site and is a finger-print of the upstream drainage area’s response to rainfall
4
CONCEPT OF UNIT HYDROGRAPH
A Hydrograph is a graph showing changes in the discharge of river over a period of time. It can also refer to a graph showing the volume of water reaching particular outfall or location in a sewerage network, graph are commonly used in the design of sewerage,more specillcally, the design of surface water sewegare systems and combination system.
5
A hydrograph consists of:
a) A rising limb or concentration curve b) A peak or crest segment c) Falling limb or recession curve
6
The properties or characteristics of a unit hydrograph are
a) the volume under a unit hydrograph is equal to 1 unit (1cm or 1in) rainfall excess b) If the duration of two rainfall excess events is equal, without regard to their respective rainfall intensities, they must result in the same hydrograph time base. c) The unit hydrograph results in a linear system whereby the direct runoff for a storm of a specified duration is directly proportional to the rainfall excess amount or volume d) Rainfall distribution for all equal duration storms is identical in space and time.
10
Calculate direct runoff from stream flow & base flow data
Direct runoff = stream flow – base flow
11
Schedule below shows observation data from stream flow with base flow depth in catchment's area 250 km2. from that data , get direct runoff magnitude. Time (hour) Stream flow, Q (m3/s) Base Flow, (m3/s) 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 1.37 1.25 1.12 5.00 12.00 15.60 17.15 14.40 8.80 6.80 5.50 4.10 2.75 2.00 1.20 0.65 0.15 0.32 0.62 1.28 1.35 1.42 1.65 1.82 1.88 2.05 2.55 1.91 1.53 1.15 0.28 example
12
Calculate Direct Runoff Depth Base On Volume DRO And Cathment Area.
DRO Depth,rd = Vd A DIMANA; Vd = RUNOFF VOLUME = Qn Δt A = CATCHMENT WIDE Qn = HYDROGRAPH ORDINATE Δt = HYDROGRAPH TIME INTERVAL
13
Calculate runoff volume and excess rain depth to a 7 acres catchment's area. Schedule below show a direct runoff data resultant from one precipitation Time (minute) Flow, Q (cfs) 2 4 6 8 10 9 21 17 13 EXAMPLE
14
Convert the duration of unit hydrograph from short to long (superposition)
15
Convert The Duration Of Unit Hydrograph From Short To Long (Superposition Method)- graphic
The following are the ordinates of a 4-hour unit hydrograph. Derive the ordinates of a 12 - hour unit hydrograph Time (Hour) 4hr-UH (m3/s) 4 3 8 33 12 96 16 63 20 35 24 25 28 32 6 36 Lagged 4hr-UH Combined 12hr-UH 4hr-UH
16
Convert The Duration Of Unit Hydrograph From Short To Long (Superposition Method)- table
Time 4j-UH Lagged (+) 4j-UH 12j-UH (Hour) (m3/s) 4 3 1 8 33 36 12 96 132 44 16 63 192 64 20 35 194 64.67 24 25 123 41 28 72 32 6 43 14.33 21 7 40 9
17
Example : The following are the ordinates of a 3-hour unit hydrograph. Derive the ordinates of a 6-hour unit hydrograph and plot the graph.
18
Solution
19
Time 4j-UH Lagged (+) 4j-UH 12j-UH (Hour) (m3/s) 3 1.5 2 0.75 6 4.5 3.00 9 8.6 13 6.55 12 12.0 21 10.30 15 9.4 10.70 18 4.6 14 7.00 2.3 7 3.45 24 0.8 1.55 27 1 0.40 30
21
Question 1: Determine the 4hr-UH from the 2hr-UH given in the table using the superposition principle method
22
Changing a Short Duration Unit Hydrograph to Long Duration using S-Curved method
23
Example The ordinates of a 4-hour unit hydrograph for a particular basin are given below. Determine the ordinates of the S-curve hydrograph and there from the ordinates of the 6-hour unit hydrograph
24
Solution Time (Hour) 4hr-UH S- Curve Addition S- Curve Ordinates
Lagged S- Curve S- Curve difference 6hr - UH 2 25 4 100 6 160 8 190 10 170 12 110 14 70 16 30 18 20 22 1.5 24
25
Time 4hr-UH S- Curve Addition S- Curve Ordinates Lagged S- Curve S- Curve difference 6hr - UH (Hour) 0.00 2 25 16.67 4 100 66.67 6 160 185 123.33 8 190 290 265 176.67 10 170 355 255 170.00 12 110 400 215 143.33 14 70 425 135 90.00 16 30 430 75 50.00 18 20 445 45 30.00 436 11 7.33 22 1.5 446.5 16.5 11.00 24 -9 -6.00 26 10.5 7.00 28 -10.5 -7.00
26
Question 1 Determine the 3hr-UH from the 1hr-UH given in the table using the S-curve method.
27
Time 3hr-UH S- Curve Addition S- Curve Ordinates Lagged S- Curve S- Curve difference 1hr - UH (Hour) 1 66 198 2 134 68 204 3 266 132 396 4 534 600 334 1002 5 466 6 400 666 7 934 268 804 8 866 -68 -204 9 200 10 1068 202 606 11 932 -136 -408 12 -66 -198 13 14 Changing a Long Duration Unit Hydrograph to Short Duration using S-Curved method
28
Question The following are the ordinates of a 4hr – UH. Derive the ordinates of a 3hr-UH
29
Derive the S-curve for 4hr-UH
30
Hydrograph Unit from Stream Discharge Data
31
Example Table below show runoff from hydrograph data, for a 50km2 catchment . Calculate the unit hydrograph (UH)10mm. Assume that the basic flow is 5.0m3/s
32
Solution
33
Mendapatkan Hidrograf Jumlah
Penggunaan UH10 bagi kawasan tadahan yang sama dengan contoh 1. Diberikan ribut yang lain dengan tempoh yang sama bagi kawasan tadahan yang sama iaitu 50km2. Anggapkan aliran dasar 7 m3/s
34
Latihan Cerapan kadaralir bagi satu kejadian hujan berkesan 12 jam bagi kawasan seluas 1150km2 adalah seperti yang ditunjukkan. Dapatkan hidrograf unit (UH)10mm untuk kawasan ini.
35
Diberi UH 4jam dan dapatkan UH -12jam dengan menggubakan kaeadah tindihan
36
REFERENCES
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.