IMPROVEMENT OF STANDARDS IN PRISONS AND DETENTION CENTRES BY RENOVATING INFRASTRUCTURE TO ENSURE RESPECT FOR HUMAN RIGHTS NFM-2013- BG15-1
2
Initial budget of the project 5 620 780 euro Additional annexes October 2014 – three new sites are added, the budget is increased with 980,000 euro and the deadline of the project is extended till 15 January 2015. 7. Lovech prison 8. Atlant hostel 9. Stara Zagora prison
3
Project budget as of October 2014 6 600 780 euro Additional annexes November 2014 – a new site is added, the budget is increased with further 216,805 euro. 10. Burgas prison
4
Project budget as of November 2014 6 817 585 euro Additional annexes February 2015 – new funding is allocated to the sites, amounting to 240,471 euro. 1. Debelt. 2. Razdelna.
5
Total budget of the project 7 058 056 euro Or 13 804 357,67 leva
6
Sites 1. Debelt 2. Razdelna 3. Training centre Pleven 4. Shumen 5. Lovech prison hospital 6. Sliven 7. Lovech 8. Atlant hostel 9. Stara Zagora 10. Burgas
7
Implementation as of 24.06.2015 Outcome 1: Reconstruction of building complex owned by the Ministry of Justice in the region of Debelt village for use as a new prison hospital to the Burgas prison, with a total capacity of 450 inmates, supplying with the necessary equipment and furnishing of the persons accommodated. Budget: 2 194 000 euro Investment design project complete; Selected construction contractor; Building site started. Upcoming: Construction works – 180 days’ term; Procurement for equipment and furnishing.
8
Outcome 2: Renovation and modernization of prison hospital at Razdelna village, part of the Varna prison, supplying with the necessary equipment and furnishing. Budget: 866 471 euro Investment design project complete; Selected construction contractor on 04.12.2014; At the moment the selection of contractor is being appealed. Upcoming: Contracting the selected construction company; Construction – 120 days’ term; Procurement for equipment and furnishing.
9
Outcome 3: Renovation and modernization of the Training Centre of the General Directorate “Execution of Sentences” in Pleven, supplying with the necessary equipment and furnishing. The activity has been completed. Total costs of construction, delivery of equipment and furnishing - 312 467,26 euro
10
Martial arts hall
11
Fitness hall
12
Kitchen
13
Canteen
14
Outcome 4: Building new investigative detention facility and probation service on the basis of reconstruction of a building – ex-military barracks in Shumen, supplying the necessary equipment and furnishing. The activity has been completed. Total costs of construction, delivery of equipment and furnishing – 1 231 142,33 euro
15
Before
16
After
17
Detention centre
18
Outcome 5: Renovation and modernization of the hospital and kitchen block in the hospital department of the Lovech prison, supplying the necessary equipment and furnishing. Budget: 360 000 euro Investment design project complete; Selected construction contractor; Selected contractors for delivery of equipment and furnishing; Construction works completed in the kitchen block and first floor of psychiatric dept. Upcoming: Accepting the construction work done in the psychiatric dept. until 10 July Delivery of equipment and furnishing; Expected to complete activity by 31.07.2015
19
Outcome 6: Renovation and modernization of medical centre at the Sliven prison, the only female prison in Bulgaria, and supplying with equipment and furnishing. The activity has been completed. Total costs of construction, delivery of equipment and furnishing – 97 277,30 euro
20
Medical centre
22
Nursery
23
Outcome 7: Renovated kitchen block for inmates in Lovech prison Budget: 297 060 euro Investment design project complete; Selected construction contractor; Upcoming: Construction works for 60 days – after launching use of kitchen in the prison hospital; Starting procurement for equipment and furnishing; Expected completion of activity until 1.11.2015
24
Outcome 8: Renovated prison hostel of closed type Atlant to the Lovech prison Budget: 212 270 euro Investment design project complete; Selected construction contractor; Upcoming: Construction works for 60 days – after launching use of kitchen in the prison hospital; Starting procurement for equipment and furnishing; Expected completion of activity until 1.11.2015
25
Outcome 9: Renovated corp of the Stara Zagora prison Budget: 470 670 euro Selected construction contractor. Upcoming: Starting the building site; Finishing construction work in 100 days. Expected completion of activity until 1.11.2015
26
Outcome 10: Design, renovation, equipment and furnishing of new kitchen block in Burgas prison Budget: 216 805 euro Investment design project complete; Committee for selection of construction contractor working until 10 July 2015; Upcoming: Contracting and building – after the contractor has been selected without appeals; Procurement for equipment and furnishing.
27
Procurement procedures held Since the start of the project the team has held 32 procurement procedures, of which 2 are still ongoing. Upcoming: holding 5 procurement procedures for delivery of equipment and furnishing, two of them ongoing.
28
Risks in implementation of the project Complex project in which starting procurement depends on the results of previous contracts; Delay in procurement – complicated procedures with long-lasting appeals; Financial risks – limited security of financial resource, delay or relocation and approval, delay of verification; Delay in contracts; Insufficient administrative capacity of the project promoters.
29
Real delay Complex projects in which starting procurement procedures depends on results from previous contracts. Delay in starting construction because of delay in design contracts. - Activity 1 Debelt; - Activity 2 Razdelna.
30
Real delay Procurement delay – complicated and long-lasting procedures, possibilities for appeal. Appeal of procurement for design - Activity 1 Debelt – delay of 180 days; - Activity 2 Razdelna – delay of 180 days. Appeal of procurement for construction - Activity 2 Razdelna – delay of more than 200 days.
31
Real delay Delay in contracts. Delay in design contracts - Activity 1 Debelt – delay of 73 days.
32
Risk delay - Activity 1 Debelt – more than 250 days; - Activity 2 Razdelna – more than 380 days.
33
Project progress: Predefined project 1 „Improve standards in prisons and IDFs by refurbishment of infrastructure to ensure respect for human rights”
34
Project progress: Predefined project 1 „Improve standards in prisons and IDFs by refurbishment of infrastructure to ensure respect for human rights”