DRAFT Status Report: Five-Year Energy Plan Town of Athol January 2013
2
Framework for Discussion Objective and Strategy Current Status o Timeline of Municipal Energy Use Selected Case Studies Funding and Payback Critical Success Factors Issues and Approach in Response Next Steps: Timeline
3
Reduce fossil fuel use by 20% by June 30, 2015, to fulfill leadership commitment of Green Community designation FY2009 baseline: 22.4 MMBTUs Three-part strategy: o Optimize energy conservation measures (ECMs) defined by investment grade audit to reduce energy use by 3.1 billion BTUs, or @ 14% o Develop renewable energy resources to produce more than 1.3 billion BTUs, representing @ 6% of municipal energy use o Identify and implement alternative, more cost- effective ECMs for greater energy savings
4
Current Status: Timeline of Municipal Energy Use FY2009 Baseline FY10FY11 (Year 1) FY12 (Year 2) FY13 (Year 3) FY14 (Year 4) FY15 (Year 5) Most Recent Year / Baseline Year (%) Buildings7,1876,879 6,38089% Water/ Sewer 9,2698,2158,8108,34290% Vehicles6,0145,5695,7775,14686% TOTAL22,47020,66321,46619,86888% Reduced energy use by 12% with 27 projects since FY2010 – leveraging state grants, utility rebates and town operating costs o Assume mild 2011-2012 winter contributed to savings Procured 2.5MW solar PV project to meet 100% of municipal electricity demand, representing 9 billion BTUs or 45% of total municipal energy use
5
Selected Case Studies: Buildings Fire Station No. 2 o Reduced energy use by 58%, from 884 MMBTU to 368.3 MMBTU by cutting oil from 4,852 to 1,114 gallons, saving @ $11,650 in FY2012. o Building envelope, roof insulation, solar hot water, water fixtures @ $21,104 Millers River Environmental Center o Reduced energy use by 51.75%, from 513 MMBTU to 247.6 MMBTU, by cutting oil use from 3,480 to 1,116 gallons, saving @ $7,375 in FY2012. o $30,126 building envelope; winserts, a project by North Quabbin Energy Police Station o Reduce energy use by 38.9%, from 817.4 MMBTU to 499.7 MMBTU, by cutting propane from 4,105 to 1,055 gallons, saving @ $6,620 in FY2012. o $8,344 building envelope project
6
Selected Case Studies: Water / Sewer, Vehicles, Other South Street Process Building, Propane Furnaces o Reduced energy use by 65.2%, from 738.5 MMBTU to 257.3 MMBTU by cutting propane from 8,116 to 2,828 gallons, saving @ $11,475 in FY2012. Vehicles o Need input from DPW, Fire and Police to explain 14% reduction in fuel usage from FY2009 through FY2012, particularly from 5,777 MMBTU in FY2011 to 5,146 MMBTU in FY2012, e.g. application of no idling policy, retirement of older less-efficient vehicles, milder winter translating into less plowing, fewer police and fire calls?
8
Payback Saved $81,832 in FY2012 based on energy reductions since FY2009 o Payback period of 6.8 years on total investment of $560,017 o Payback period of 6 months for Town of Athol, based on $40,917 in operating costs Avoided electricity costs in range of $30,000 in 12-month period o In FY 2011, installed variable speed pumps at Tully Well Pump Facilities, a $68,574 project to save 285,027 kWh, reducing annual use by largest municipal user of electricity by 972.4 MMBTU and saving @ $30,013 o Major water leak started January 18, 2011, responsible for additional annual electricity use by pump facilities in range of 260,000 kWh
9
Critical Success Factors Collaborative approach by Town of Athol to public projects o Energy Committee o Capital Programs Committee / Finance and Warrant Advisory Committee o Board of Selectmen Partnership with National Grid: energy expertise and funding o Tully Well Pump Facilities o Whole Building Assessment and Town Hall Light Replacement Project o Ornamental Street Light Replacement Project o Athol Public Library Renovation and Expansion Project
10
What are we doing now and going forward? Athol Public Library in FY2013 – Green design and sustainable construction to achieve Platinum- level certification for Leadership in Energy and Environmental Design (LEED) – would be first-of-its-kind in the United States – Library may attract @ $100,000 in utility incentives Update five-year plan through FY2014 and FY2015 – Unfinished business – New projects
11
Unfinished business: Projects with potential savings of 1.32 billion BTUs, or 6% of FY2009 baseline – Town Hall HVAC System – Computer networks and vending machines – Lighting retrofits at animal shelter – New energy management systems DPW garage and water treatment plant, South Street Well Process Building
12
Issues and Approach in Response Need three members for Energy Committee o Seek volunteers, including residents, business leaders and youth Need to identify cost-effective finance for geothermal for Town Hall o Investigate state grants, private markets, town capital / operating funds Need to assess water supply, treatment and distribution facilities and wastewater collection, treatment and disposal works o Engage National Grid for facilities assessment and projects Need to examine municipal building use to optimize operations o Fire Station No. 1 used 1,114 gallons of oil and 2,880 kWh in FY2012
13
Next Steps: Timeline January 2013: Discuss status of five-year energy plan January 2013-March 2014: Conduct project analysis April 2013: Review projects, secure necessary approvals and update five-year energy plan May 2013: Submit Green Community grant proposal June 2013: Start implementation of funded projects